FORMULAS Flashcards

1
Q

Planned Value(PV)

A

What the project should be worth

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Earned Value (EV) Formula

A

What the project is worth

%Complete* BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Actual Costs (AC)

A

What the project has spent so far

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Budget at Completion (BAC)

A

What the project budget is

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Variance (CV) Formula

A

EV-AC

Positive=Under Budget
Negative=Over Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule Variance Formula (SV)

A

EV-PV

Positive=ahead of Schedule
Negative=Behind Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Variance at Completion (VAC)

A

Projection of being over or under budget based on current performance

BAC-EAC

Positive=Under Budget
Negative=Over Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost Performance Index (CPI)

A

Shows overall cost efficiency on the project
EV/AC

Greater then 1= under budget
Less the 1=over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Schedule Performance Index

A

Shows overall schedule adherence

EV/PV

Greater then 1-ahead of schedule
Less then 1 is behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate at Completion (EAC)
Standard Formula

A

Forecast final project costs based on current performance

BAC/CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Estimate at Completion (EAC)
Future Work at planned costs

A

AC+BAC-EV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Estimate at Completion (EAC)
Initial costs estimates flawed

A

AC+Estimate for remainder of project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Estimate at Completion (EAC)
CPI and SPI affect remainder of project

A

AC+[BAC-EV/CPI*SPI]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Estimate to complete

A

Predict how much the remainder of the project will costs

EAC-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

TCPI
Utilizing BAC

A

Predicts likelihood of reaching BAC

(BAC-EV)/BAC-AC

Greater then 1 = harder to complete and meet BAC
Less then 1=easier to complete and meet BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

TCPI To-Complete Performance Index
Utilizing EAC

A

Predicts Likelihood of reaching EAC

(BAC-EV)/(EAC-AC)

Greater then 1 = harder to complete and meet EAC
Less then 1=easier to complete and meet EAC