SBC Notes Flashcards
Progressive Assurance
Assurance completed through a process rather than upon completion
Data Drop
Transfer of BIM data from contractor to client
Intrados
Internal face of an arch
Extrados
External face of an arch
RODS
Rolling Origin and Destination Survey
Distribution Network Operators (DNO)
Responsible for distributing the electricity from the transmission system and maintaining the cables, substations and equipment. 6 in the UK, UKPN in London
National Grid maintain the transmission system
Cranked Beam
A beam with an angle change in it
Nominal fixing (blast)
A fixing designed to take standard loading (wind etc.) but fail readily during blast loading so as to fail safely
DLO
Direct labour Organisation - a DLO is a unit of a local authority or housing association that delivers building and maintenance works. Also Direct Service Organisation
Kit-of-parts
Kit-of-parts construction is a special subset of pre-fabrication that not only attempts to achieve flexibility in assembly and efficiency in manufacture, but also by definition requires a capacity for demountability, disassembly, and reuse. Kit-of-parts structures can be assembled and taken apart in a variety of ways like a construction toy.
Quality Assurance
Quality Assurance is known as QA and focuses on preventing defects.
Quality Assurance ensures that the approaches, techniques, methods and processes are designed for the projects are implemented correctly.
Quality assurance activities monitor and verify that the processes used to manage and create the deliverables have been followed and are operative.
Quality Assurance is a proactive process and is Preventative in nature. It recognizes flaws in the process.
Quality Assurance has to be complete before Quality Control.
Quality Control
Quality Control focuses on identifying defects.
QC activities monitor and verify that the project deliverables meet the defined quality standards.
Quality Control is a reactive process and is detection in nature. It recognizes the defects.
QC comes after QA
Extra Over (E/O)
‘Extra over’ (EO) is a term that is often used when taking off for a bill of quantities (BoQ). Taking off is the process of identifying elements of construction works that can be measured and priced. When taking off for a BoQ, the term ‘extra over’ can be used to refer to items that to a certain extent have already been measured, but have not been priced at the full value of all their labour and materials. A common example of this is when measuring drain pipes, for which the estimator may determine a cost based on the full length of the pipe measured along its centre-line, and then assess an ‘extra over’ cost for the additional cost necessary to pay for fittings such as bends and junctions.
EVC
Emergency Voice Communication
Documents to be handed to D+B contractor upon assumption of PC role
Engineering Safety Hazard Log, Non-Compliance and Concession Log, Assumptions Register, Design Issue and Change Register
Human Factors
The application of psychological and physiological principles to the (engineering and) design of products, processes, and systems. The goal of human factors is to reduce human error, increase productivity, and enhance safety and comfort with a specific focus on the interaction between the human and the thing of interest.[1]
Electromagnetic Compatibility (EMC)
Electromagnetic compatibility (EMC) is the branch of electrical engineering concerned with the unintentional generation, propagation and reception of electromagnetic energy which may cause unwanted effects such as electromagnetic interference (EMI) or even physical damage in operational equipment. The goal of EMC is the correct operation of different equipment in a common electromagnetic environment
Track Clearance Approval Form
Any structure or fixed equipment (whether operational or not) requires a Clearance assessment provided it is less than 5m above or within 3m laterally of the nearest running edge.
LUEX
LU Executive Board
Positive Drainage
Drainage provided by slope
Types of Flooding
Fluvial - River, Pluvial - Surface water (rain), Coastal - Sea, Burst water main
Statutory Authority
A statutory authority is a body set up by law which is authorised to enact legislation on behalf of the relevant country or state.
Aspirating smoke detector
An aspirating smoke detector (ASD) is a system used in active fire protection, consisting of a central detection unit which draws air through a network of pipes to detect smoke (VESDA) more sensitive than a standard fire alarm
Castell Lock system
Trapped key interlocking utilizes locks and keys for sequential control of equipment and machinery to ensure safe operation. Trapped key interlocks are widely used to ensure safe access to potentially live or dangerous plant or equipment in an industrial setting.
Power Service Contract (PSC)
LU Power
Four foot and six foot
Four-foot is the space between the two running rails and six foot is the space between two tracks
Gypsum
Used in plasterboard and has to be disposed of separately due to production of odorous and toxic hydrogen sulphide gas when disposed with biodegradable waste.
Piling mat
A piling mat is a type of working platform used for piling rigs to travel on, providing a stable base on which they can move around the site and operate. The most suitable materials for piling mats are generally well-graded natural gravels, clean-crushed concrete, crushed hard rock, and so on
Rise and Going
Horizontal and vertical lengths of a single stair
Fire-protected routes
3.14.2.1 A fire-protected route shall be any one of the following: a) through which the evacuation load or affected passenger load can proceed; b) which can be segregated from the area of incident (e.g. by fire doors); c) where there is an escape exit to the street.
Technical Content Manager
The manager responsible for the content of a standard, “Standard holder/owner”
Intumescent
A material that swells upon application of heat, often used as a passive fire provision.
Pad Foundation
Pad foundation refers to the foundation which is intended for sustaining concentrated loads from a single point load such as structural columns.
Strip Foundation
Strip foundation is used to support a line of loads such as load-bearing walls. For instance, closely-spaced columns render the use of pad foundation inappropriate and strip foundation may be a better alternative.
Raft Foundation
Raft foundation consists of a concrete slab which extends over the entire loaded area so that loads from entire structure are spread over a large area leading to a reduction of the stress of foundation soils is reduced. Moreover, raft foundation serves to avoid differential settlement which otherwise would occur if pad or strip foundation is adopted.
IP4X trunking rating
The IP4X rating means that protection to persons and equipment is provided by testing with a 1.0mm diameter probe to ensure that it will not penetrate the trunking at, for example, points where the trunking has been joined. No protection is provided against water splashing from any direction.
LU Power -
Electrical power for LU traction, signalling, station and depot services, Docklands Light Railway and other authorised users is taken from Bulk Supply Points (BSPs) and distributed through the LU distribution network comprising high and low voltage distribution systems to AC and DC loads.
The system is capable of being supplied, under emergency conditions, by generation from the LU Greenwich Generating Station.
Distribution Network Operator (DNO) Supply
All LU stations have a LVAC supply from the local Distribution Network Operator (DNO) – often termed “street supplies”.
Emergency Power Supplies (LEPS) Supply -
LEPS loads will be supplied from OLBIs for at least an hour, following a widespread National Grid outage which has resulted in failure of the normal LU and DNO LVAC supplies to stations.
Central Emergency Power Supply (CEPS) Supply -
The LU CEPS supply from Greenwich Generating Station will re-supply the LU network in about a half hour following a widespread National Grid outage to re-instate LU LVAC supplies to stations.
Essential Supplies
Essential supplies are those that will re energise following an outage (CEPS and LEPS are essential)
OLBI
OLBIs provide an emergency power supply to essential loads (LEPS) to ensure the safe evacuation of passengers and staff from LU Section 12 stations following a widespread National Grid outage. The emergency power supply from the OLBI shall be capable of being maintained for a minimum period of 1 hour at full load and rated voltage.
Following completion of the emergency operation any remaining under-used battery capacity from the 1 hour period shall be available to supply further emergency power.
In Normal supply mode - The mode in which the emergency loads are supplied direct from the incoming DNO LVAC supply via the operational bypass.
Vortok Fencing
Magnetic rigid barrier that attaches to rail
Track Licenses (T001-003)
Safety critical licenses for activities involving track - T001 - Inspected Asset, T002 - Repaired Asset, T003 - Modified Asset
Two stage tendering
Two stage tendering is used to allow the early appointment of a contractor, prior to the completion of all the information required to enable them to offer a fixed price. (Early Contractor Involvement)
In the first stage, a limited appointment is agreed allowing the contractor to begin work and in the second stage a fixed price is negotiated for the contract.
The pre-construction services carried out by the contractor in the first phase might include:
- Helping the consultant team develop the design, or the contractor undertaking all design development themselves. - Advise on buildability, sequencing, and construction risk. - Obtaining prices for work packages from sub-contractors or suppliers on an open book basis.
P50 Levels
P50 is defined as 50% of estimates exceed the P50 estimate (and by definition, 50% of estimates are less than the P50 estimate). It is a good middle estimate.
Mean usually lies about the P40-P30 levels and are therefore high estimates.
P90 and P10 are low and high estimates respectively. P90 means 90% of the estimates exceed the P90 estimate. It does not mean that the estimate has a 90% chance of occurring
The central limit theorem indicates that the P50 estimate has more chance of occurring than the P90 and P10 estimates.
Option E Contract (Cost Reimbursable or Cost Plus)
A cost reimbursable contract (sometimes called a cost plus contract) is one in which the contractor is reimbursed the actual costs they incur in carrying out the works, plus an additional fee.
A cost reimbursable contract might be used where the nature or scope of the work to be carried out cannot be properly defined at the outset, and the risks associated with the works are high, such as, emergency work.
High risk for client as cost not known when contract entered (no contract sum).
Computer Based Train Control
Communications-based train control (CBTC) is a railway signalling system that makes use of the telecommunications between the train and track equipment for the traffic management and infrastructure control. By means of the CBTC systems, the exact position of a train is known more accurately than with the traditional signalling systems. This results in a more efficient and safe way to manage the railway traffic. Metros (and other railway systems) are able to improve headways while maintaining or even improving safety.
Out turn costs
The ‘outturn cost’ or ‘out-turn cost’ of a project is its actual construction cost. Generally this refers to the actual, total construction cost calculated at the end of the project.
This contrasts with cost estimates, or target costs, which are calculations of the cost that is expected, or the cost that should be achieved.
Exterion
Media partner of LU, advertising assets
Thales
Provision, installation and maintenance of telecomms assets (connect)
Order of magnitude estimate
Order of Magnitude (OOM) Estimates are rough guesses made at the very beginning of the project. At this time not much is known about the project and everything can change as planning progresses. Order of magnitude estimates use historical project data with analogous mathematics. The numbers are calculated for the whole project, not for individual tasks or major deliverables.
They are usually expressed as a range,
Executives immediately use only the lower (most optimistic) numbers.
But project managers should stick with the ranges in all theirorder of magnitude estimates because the range communicates the project’s uncertainty.
Range narrows as planning progresses and uncertainty declines.
S1371
Station Planning
S1053
Civil Eng - Buildings and station structures
S1088
Managing changes to stations and shafts fire precautions
S1085
Fire Safety Performance of Materials - Stations and Tunnel Infrastructure
S1052
Gravity Drainage Systems
Whole Life Costing
Capex, Opex, Maintenance, project management, decommissioning, disposal
The Management System
Details how we work at tfl. Includes “Working atTfL”and documents in the management system library,will support our ways of working by making them accessible, clear and concise. Includes standards, processes and guidance
Costs to Society of injuries
Broken down into human costs (impact on quality of life/loss of life) and financial (loss of production and healthcare costs, admin, legal, insurance)Fatal injury - £1.2m (human) £0.4m (financial) Non fatal £5.3k/£3.1k, Week absence £19k/11k (2016 figures)
Estimates of average costs per case of workplace injury or ill health are important in the economic appraisal of policy interventions.
Policy appraisal involves comparing the costs of any proposed new health and safety interventions against the likely benefits (in terms of reduced costs associated with reduced workplace ill health and injury cases) the proposed measure is likely to deliver.
Safety
Is the freedom from unacceptable risk of harm (EN 50126 [9])).
Safety Authority
Any organisation from which safety approval is required, for example a railway authority or a regulatory authority. Under ROGS 2006 the approvals process results in Safety Certification for rolling stock and Safety Authorisation for Infrastructure.
London Underground Safety Certificate and Safety Authorisation
The London Underground Safety Certificate and Safety Authorisation was first produced in in 2007 to meet the Railways and Other Guided Transport Systems (Safety) Regulations. It replaced the Safety Case. It was accepted by the ORR and approval has been maintained ever since through various revisions. It specifies how LU maintains a safe operational railway through setting requirements for design, maintenance, audit, control of new risks and emergency planning. The Safety Certification relates to train operations and the Safety Authorisation covers stations and infrastructure.
GIS (Geographic information system)
A geographic information system (GIS) is a framework for gathering, managing, and analysing data. Used for portraying data in many different ways on maps. Its main job is to help in analysing groups of data and find correlations or patterns.
Engineering Council
Engineering Council is the regulatory body (QUANGO) for the UK Engineering Profession. Sets Standards for competence and commitment via the UK-Standard for Professional Engineering Competence (UK-SPEC), currently in third revision. Oversees 35 separate engineering institutions.The Engineering Council is currently carrying out its five-yearly review of the Standard against which engineers and technicians are registered.
Some interesting findings.
b. Automation is replacing ‘routine’ work, leading to the need for technicians to have higher skills.
f. The reduction in demarcation between and beyond traditional engineering disciplines, with an increase in multi- and inter-disciplinarily roles.
Maintenance
Keeping something fit for purpose
Safe
when the risk associated with it is controlled to an acceptable level. This level may reduce as technological advances make it practicable to reduce risk even further.
Safety Case
Safety case – a document that describes the measures taken to ensure the safety of some aspects of the railway. There are two main sorts of safety case: Eng and Railway safety cases
Engineering Safety Case
An engineering safety case presents the justification for the safety of a railway product or a change to the railway. Despite its name, an engineering safety case covers more than just engineering.
Business Plan
- Our Business Plan is our contract with the People of London,
- It covers five years in detail and a further five in more summarised form,
- Although historically compiled on a ‘bottom up’ basis, it represents TfL’s strategic focus for the next 10 years,
- It is updated annually,
- It forms the basis for the budget. ,
- Once adopted by the Mayor and published the Business Plan cannot be changed in whole and only in part through strict delegated authority
Financial Authority
- Financial Authority represents the total amount any programme or project can spend,
- Financial Authority is derived solely from the Budget (for the current year) and Business Plan (for future years),
- Ordinarily Financial Authority cannot be changed except through the Budget or Business Plan process in a subsequent year,
- However, by exception Financial Authority can be transferred from one project or programme to another subject to formal approval by the CFO of TfL under delegated authority
Budget
- The budget represents the detailed spend in the coming financial year,
- Budgets are not expected, in total, to differ from Business Plan when drawn up,
- Budgets are a Forecast at a moment in time, albeit that a Budget demands much more detailed review and in coming periods our performance will be measured against Budget,
- However, budgets form no part of the governance process, they are a financial yardstick to measure our performance against,
- Budgets influence, but do not drive, decisions
How are Programme and Project Authorities approved?
- Programme and Project Authority is granted at one or more levels:, At Client Board within that Board’s delegated authority (£10m), At LUX within its delegated authority, At PIC,
- PIC Authority will generally be across a broad programme or like minded projects,
- LUX and/or Client Board Authority will, except in the case of programmatic work, be granted for specific projects,
- Programme and Project Authority cannot exceed Financial Authority,
- A request for Programme and Project Authority that exceeds Budget must be accompanied by details of how the shortfall will be met. ‘Through efficiency savings’ is not a sufficient answer,
- Programme and Project Authority is not a fixed number for a fixed time; as circumstances change additional Authority can be requested,
- Programme and Project Authority does not drive Estimated Final Cost nor Forecast calculations
Forecast
- Forecasts represent the best and most realistic estimate of what the cost will be in the financial year and the phasing thereof.
- Forecasts are updated periodically,
- Forecasts are unconstrained by any other financial measure, Business Plan, Budget, EFC, Programme and Project Authority or Financial Authority,
- They can influence decisions about changing other financial measures, but are not a necessary prerequisite, i.e. they do not automatically lead to changes, but are a leading indicator of potential changes being necessary
Estimated Final Cost
- Estimated Final Cost is a calculation of how much any individual programme or project will ultimately cost to deliver, including Risk ,
- Estimated Final Cost should be reviewed regularly, at least quarterly, and periodically in large and/or problematic cases,
- Estimated Final Cost is not driven or constrained by Programme and Project Authority, Budget, Business Plan, Forecast or Financial Authority. It is a realistic assessment, at a point in time, of what the final cost will be,
- It may though drive necessary action with regards to Programme and Project Authority or Financial Authority. It will also influence Forecast
What is project risk?
- Risk is included in all projects and programmes,
- Risk is assessed based upon the likely occurrence of certain events happening through the programme/project life cycle and the impact if they do,
- If the event does not occur, or incurs less cost than the risk, then it is released as an efficiency or scope saving as appropriate,
- risk should be phased in accordance with the attendant spend profile and not phased at the end of the programme/project/year,
- If the associated spend is rephased in Forecast, Budget or Business Plan, the risk must be similarly rephased,
Value of Work Done (‘VOWD’)
- VOWD is a measure of actual costs incurred to date,
- It does not equate to cash flow, and is independent of invoicing,
- Periodically a calculation must be undertaken to calculate what proportion of a project/programme’s total cost has been completed and that cost is recognised in the accounts,
- If invoices are received or cash paid later in the process, the VOWD cost is accrued onto the balance sheet,
- If invoices have been received or cash paid earlier in the process this is taken to the balance sheet as a prepayment,
- VOWD can include the receipt of goods or materials if these goods or materials can only be used on that project/programme,
Procurement Authority
- Procurement Authority is provided by the Head of Procurement,
- It is a Commercial Authority, permitting the commitment of spend up to that Authority with third parties,
- Procurement Authority cannot exceed Programme and Project Authority,
- Procurement Authority does not influence anything more that Commercial decisions and interaction with suppliers,
What are Causals? Name four.
•Causals explain the reasons for the movements between two numbers; actuals and forecast, actuals and budget, budget and forecast and any other combos
We report ten types of Causals: Acceleration, Cost increase, In year deferral, Out of year deferral, Scope increase, Scope decrease, Slippage, Transfers, Income, Efficiencies
High Impact Low Probability events (HILPS)
- May be asset damage or fatalities
- Tends to result in a disproportionally severe response (politicians want someone/thing to blame-Prosecution-Reputational damage
- Negative response by insurers
Coronavirus, terrorism, nuclear disasters
Ground risk
Which party should accept ground risk, should be shared or held by client.
The risk that ground conditions actually encountered will be less favourable than was expected at the time the contract was entered into.
Normally allocated to the party best suited to manage or control it (contractor)
For example the NEC3 Engineering and Construction NEC Contract provides for a compensation event in certain circumstances where the Contractor encounters physical conditions that had “such a small chance of occurring that it would have been unreasonable for him to have allowed for them” (clause 60.1(12)). However, in judging physical conditions for the purposes of a compensation event certain factors need to be taken into account, including site information provided to the Contractor (clause 60.2).
Accident Triangle
The accident triangle, also known as Heinrich’s triangle or Bird’s triangle, is a theory of industrial accident prevention. It shows a relationship between serious accidents, minor accidents and near misses and proposes that if the number of minor accidents is reduced then there will be a corresponding fall in the number of serious accidents
Anthropogenic Hazards
hazards caused by the action or inaction of man, compare to natural hazards. Anthropogenic hazards are easier to identify and design out than natural hazards in the earlier stages of the project
Mass and Material Properties
Material properties - Colour, Grain size, texture, strength, hardness
Mass Properties - Bedding, discontinuities, faulting, folding
Material properties are those you could identify with a sample in the hand, mass properties are those seen in macro
In soft ground material properties govern design and stability in hard rock mass properties do
Stratigraphy
The branch of geology concerned with the order and relative position of strata and their relationship to the geological timescale.
Lithology
The study of the general physical characteristics of rocks.
Compaction Grouting
Injection of low slump mortar though a casing, causes densification of soil through mortar bulb expansion
FE Analysis limitations
Difficult to take into account construction tolerances, only as good as your inputs
Sensitivity analysis
Sensitivity analysis is the study of how the uncertainty in the output of a mathematical model or system (numerical or otherwise) can be divided and allocated to different sources of uncertainty in its inputs
Steel Fibre Reinforced concrete
Steel fibres in concrete mix provide reinforcement. Removes need for rebar cages which are costly/take time/ have to be stored/ require specialist labourSteel fibres reinforce all parts of the section so can resist cracking at edges- Do not corrode in the presence of chlorides- Provide good crack width and distribution control- Reduce accidental handling damage
Cavitation
When water flows over a discontinuity or irregularity a high pressure bubble can form. If this bubble collapses against a surface it can cause damage to the material
Carbonation
The ph of new concrete is typically 12-13, which surrounds embedded reinforcement with a passivating layer of highly alkaline cement, protecting reinforcement against corrosion., Atmospheric carbon dioxide reacts with calcium hydroxide . The reaction produces calcium carbonate. This reduces the alkalinity of the concrete to a level where the cement paste no longer provides a passive environment for embedded steel, this is said to occur when the ph of concrete falls to approximately 8.6.
Steel reinforcement is then thought to be susceptible to corrosion, The presence of oxygen initiates surface corrosion of the reinforcing steel through oxidation, where iron oxides form on the steel’ s surface. These oxides, although porous and flaky, have a larger volume than the original steel—up to six times greater depending on the composition of the corrosion products, Broomfield notes. The iron oxides expand against the concrete, and the resulting stress causes the concrete cover to crack and eventually spall.
Empirical/analytical
An empirical model is based on experimental data, analytical model relies on fundamental scientific laws.
Ground Settlement in tunneling, how does it behave, what effects it?
Settlement troughs roughly follow a standard distribution
- Also have a “bow” wave ahead of the tunnel face
- Volume loss depends on: Soil, depth, tunnelling method, speed of face closure, groundwater, flexibility of lining, advance length-Deeper tunnels have a wider trough with a smaller max depth, shallower tunnels have the opposite
- Have to consider the long term movements due to the change in groundwater pressure from current to long term
- Base readings of settlement within in a tunnel will not account for settlement that has already occurred due to the bow wave
Causes of Building Movement
- Structural movement- Thermal movement- Exposure to moisture- Ground settlement
What are the damage categories for structures?
Burland scale
Negligible, very slight, slight (aesthetic) 0-2, moderate, severe (Serviceability or function) 3-4, very severe (Stability) 5
Defined by crack width or tensile strain.
Three stage assessment of structures -
S1 - preliminary - Simple screening, if settlement >10mm or 1:500 slope move to stage 2
S2 - Second stage assessment, Idealisation of facade or wall of building to behave like a deep elastic beam (ok results)
S3 Detailed Assessment
Concrete Characteristics
- Compressive Strength
- Flowability
- Segregation/bleed
- Pumpability
- Open time(transport)
- Early Strength
- Heat of hydration
- Shrinkage
- Permeability
- Reinforcement
- Chemical resistance
- Abrasion resistance
Cold joint
- When fresh concrete is poured next to concrete that has already gone off meaning the two batches dont mix
Makeup of SCL concrete v standard concrete
In SCL - More fine aggregates, water, cement and admixtures- Less coarse aggregates
Penetrometer
For measuring early age strength of concrete by inserting needle to a depth and measuring how much force was required
Cost of waterproofing
Waterproofing is around 1% of cost of civils works, water ingress accounts for 80% of damages
DRACCT
Directors Risk Assurance and Change Control Team
Optimism bias
Optimism bias is the tendency for those involved in projects, as funders, managers or beneficiaries, to be too optimistic in terms of forecasting project costs, scale, timing and benefits. Accordingly, advice is that in any appraisal an optimism bias adjustment should be made.
Reference Class Forecasting
Adjusting cost and programme upwards (40%) in line with previous overruns of similar projects (reference class)
Planning Fallacy
The tendency for people to think things will cost less and be quicker to complete
Quality
Compliance with a defined requirement - value for money, fitness for purpose, customer specification
Quantity Surveyor
Commercial oversite of site, preparation of financial reports, budgets and forecasts
Planned Preventative Maintenance
Surveys, inspections examinations and assessments of assets - Designed to prolong service life, reduce failures, maintain required performance and ensure safe operation
Service Affecting Failure
A failure that causes a delay of over two minutes
Culvert
Drainage tunnel under a road or highway
Corporate Governance
The systems of rules, practices and processes by which a company is directed and controlled
Social Identity
Race, ethnicity, age, religion, sex, disability, gender
SCADA
Supervisory control and data acquisition
Operation and Maintenance manuals
Handover documentation detailing the operation and maintenance requirements of an asset. Legally required under HSAWA
Signal Failure
Signals always “failsafe”. Often occur when there is a short circuit between running rails, can be caused by puddles, iron filings between abutting rails, rodents chewing cables, LV current runs in running rails for signalling
Floating Track Slab
Any track slab arrangement that has a suspension system between the track slab and the invert, can be resilient membrane or spring system
Catchpit
Concrete drainage element that Is used to collect sediment that settles out of fluid
Head House
The above ground element of a shaft
Galvanising
Steel or iron coated n zinc to prevent rusting, zinc acts as a sacrificial layer (anode) and protects the steel from corroding elements
Loss Leader
A product sold at a loss to attract customers
Construction Industry Training Board
Collects an annual levy from its members which is then distributed for learning and development.
Stringer
Inclined beam that supports stair treads
Highways Authority
Responsible for the maintenance of public roads - Trunk roads (motorways) - Highways England,
Local roads - Local authority
Pile Cropping
Removal of concrete from top of pile to facilitate structural linking with beam slab etc.
Cross stitching of cracks
Using rebar down to stitch cracks (inserted at an angle from each side)
Caveat Emptor
Buyer beware, buyer knows less than the seller but has more motive to find the truth
Lane Rental Scheme
Charges to those doing works on tfl controlled streets. Price dependant upon duration, traffic, location, sensitivity of time and place
OJEU Procurement
Official Journal of the EU procurement -
Published daily showing include invitations to tender, prior information notices, qualification systems and contract award notices.
If a public authority contract is above certain contract value (above £120k for central govt), EC Procurement Regulations require that the contract has to be awarded using an EU/OJEU compliant route to market. This can include publishing the opportunity via OJEU.
Can add to programme due to mandated advertisement periods.
Stopping up order
When a borough stops up area of public highway meaning it ceases to be a highway road or footpath
Leasehold
Method of owning property where you do not own the land it stands upon, when the lease expires the property reverts to the freeholder
Freehold
Outright ownership of the property and land
Target and forecast dates
Target is your baseline date and forecast date is your best current estimate
1st 2nd 3rd line assurance
1st line - project/programme board, change control procedures, reporting, risk management strategy,
2nd line - Assurance review manager, IAR
3rd line - Independent Investment Programme Advisory Group
Information Asymmetry
When one party knows more than the other
Procure 2 Pay
1 PM raises purchase request - approval by cost centre manager/programme manager/MD dependant upon value
2 PO raised by PM - released by procurement team, vendor receives PO and goods services are delivered
3 PM confirms receipt of goods
4 Vendor sends invoice which is matched to relevant purchasing documents by accounts payable (PO and invoice - two way match, PO invoice and goods receipt., three way match)- SME vendors paid within ten days (mayoral pledge and KPI)
Task order/request
Task request - Asking for price and programme for a stated brief
Task Order - ordering the contractor to commence work
C2/C3 utilities
C2 - Initial enquiry regarding the location of existing apparatus
C3 - Budget estimate for works that are needed to be undertaken to alter existing plant or equipment
C4 - Detailed estimate for works
What is enhancement of an asset?
Works that change the operational capability of an asset
RISQS
Railway industry supplier qualification scheme
Development length of rebar
The length of embedment required for rebar in concrete to develop by bond a force equal to the tensile strength of the rebar
Critical steel ratio
To ensure concrete fails in tension before Steel, If steel fails first large progressive failures are possible ( Ductile failures are good, brittle failures are bad)
Soil arching
The transfer of pressure from a yielding mass of soil on to a stationary part due to shearing resistance between the stationary and yielding masses
Needle beam
Horizontal beam that go through a wall or pier to support the upper section of a structure whilst the lower section is worked upon, used in facade retention
Professional Indemnity Insurance
Covers legal costs of defending a claim related to the provision of inadequate advice, service or design
What is Concrete cover and what is its purpose
- To protect rebar from environmental attack (corrosion, carbonation)
- To provide thermal insulation in case of fire
- To provide sufficient embedding to prevent the rebar from slipping when stressed
Notice to treat
Formal request from a local authority to agree a price for a property, can take months/years to complete
Cold rolling/hot rolling steel
Cold rolling - More dimensional accuracy, less section options
Hot rolling - Can be shaped much easier, larger section sizes can be made, cheaper. Less precise, larger tolerances
Bulking factor
Ratio of volume of soil before and after excavation
Fish plate
Connection plate between two steel sections
Statutory requirement
A requirement designated by law , legal requirement
Patent/latent defects
Patent defects can be discovered by reasonable inspection, latent defects can not (e.g. foundations)
Settlement deed
A binding commitment addressing settlement issues
Greenfield ground settlement contour
Ignores the positive contributions of foundations upon settlement in an area. Less than 10mm settlement tends to have a negligible impact upon buildings (not including listed)
Caisson
Water retaining structure for the purpose of construction below the water level (part of the permanent structure unlike cofferdams)
HIAB
Synonym for a loader crane of any type
Chapter 8 barriers
Red pedestrian barriers
Baseline monitoring
Should be completed several seasons before works commence to take into account seasonal changes-
Visual condition surveys for assets within 1-10mm contour
- More detailed defect surveys for those in >10mm contour (greater than >1mm for listed buildings)
Cracked concrete
Concrete that may experience cracking through the plane of the anchor, determined through stress analysis
Blinding
In construction, blinding is a base layer of weak concrete or sand that is laid above a layer of hardcore to provide a clean, level and dry working surface.