[S] BJ5 Make-to-Stock Production – Discrete Manufacturing Flashcards
Describe the scope item BJ5 Make-to-Stock Production – Discrete Manufacturing.
BJ5 Make-to-Stock Production – Discrete Manufacturing
This scope item enables production planning in make-to-stock scenarios for a serial-number-managed finished good.
BJ5 Make-to-Stock Production – Discrete Manufacturing
How does the process of Make-to-Stock Production start?
BJ5 Make-to-Stock Production – Discrete Manufacturing
The process starts with the creation of a demand forecast for finished goods represented by Planned Independent Requirements (PIRs).
Based on PIRs, Material Requirements Planning (MRP) creates a production plan for finished goods and explodes the entire bill of material structure.
As a result, semi-finished component production and raw material demand is planned. Production planners can analyze and manually change the planned order-based production plan.
BJ5 Make-to-Stock Production – Discrete Manufacturing
What does raw material demand lead to?
BJ5 Make-to-Stock Production – Discrete Manufacturing
Raw material demand leads to purchase requisitions that trigger alternative procurement scenarios referenced in this scope item.
BJ5 Make-to-Stock Production – Discrete Manufacturing
How is the production process covered?
BJ5 Make-to-Stock Production – Discrete Manufacturing
The production process itself is entirely covered by
- using the conversion of planned into production orders
- order release
- material staging and picking
- confirmation of order operations
- and goods receipt posting.
Order-based target and actual cost is created, ensuring fully integrated material and value streams.
BJ5 Make-to-Stock Production – Discrete Manufacturing
What are the key steps of Make-to-Stock Production?
BJ5 Make-to-Stock Production – Discrete Manufacturing
- Process planned independent requirements
- Execute material requirements planning and evaluation of stock requirement list
- Execute production order processing.
- Run scrap reports optionally after production
BJ5 Make-to-Stock Production – Discrete Manufacturing
What are the benefits of BJ5 Make-to-Stock Production – Discrete Manufacturing?
BJ5 Make-to-Stock Production – Discrete Manufacturing
- Trigger production execution with a production plan
- Explode the bill of material automatically when running the MRP
- Calculate target costs during order creation
- Improve usability with intuitive confirmation of production operations
BJ5 Make-to-Stock Production – Discrete Manufacturing
What are “Planned Independent Requirements”?
BJ5 Make-to-Stock Production – Discrete Manufacturing
Planned independent requirements are used to perform demand management functions.
A planned independent requirement contains one planned quantity and one date, or a number of planned independent requirements schedule lines, such as one planned quantity split over time according to dates.
BJ5 Make-to-Stock Production – Discrete Manufacturing
Explain the process step “Material Requirements Planning at Plant Level”
BJ5 Make-to-Stock Production – Discrete Manufacturing
This process step shows you how to use material requirement planning to tailor available capacities and receipts on time to suit requirement quantities. You can use MRP or consumption-based planning for this purpose.
BJ5 Make-to-Stock Production – Discrete Manufacturing
Explain the process step “Evaluate Stock/Requirements Situation”
BJ5 Make-to-Stock Production – Discrete Manufacturing
This process step shows you how to display the stock/requirements situation for the material in the stock/requirements list after the requirement planning has been performed.
BJ5 Make-to-Stock Production – Discrete Manufacturing
Explain the process step “Conversion to Production Orders for Subassembly and Final Assembly”
BJ5 Make-to-Stock Production – Discrete Manufacturing
The daily MRP run creates planned orders for goods that are to be produced internally.
This process step shows you how to convert the planned orders to production orders for both semi-finished goods and finished goods when the planned opening date is reached.
BJ5 Make-to-Stock Production – Discrete Manufacturing
Explain the process step “Review Material Availability Status for Production Orders”
BJ5 Make-to-Stock Production – Discrete Manufacturing
You review the material availability status for production orders in this step.
BJ5 Make-to-Stock Production – Discrete Manufacturing
Explain the process step “Material Staging for Subassembly”
BJ5 Make-to-Stock Production – Discrete Manufacturing
This process step shows you how to stage materials for production. If there is sufficient stock available on the production storage location no line items are generated.
BJ5 Make-to-Stock Production – Discrete Manufacturing
Explain the process step “Release Production Order for Subassembly”
BJ5 Make-to-Stock Production – Discrete Manufacturing
This process step shows you how to release the order at header level, releases the order and all its operations. The order and the operations receive the REL (released) status.
BJ5 Make-to-Stock Production – Discrete Manufacturing
Explain the process step “Confirm Production Operations for Subassembly”
BJ5 Make-to-Stock Production – Discrete Manufacturing
The confirmation documents the processing status of orders, operations, sub-operations, and individual capacities. It is an instrument for controlling orders.
This process step shows you how to confirm the operations of the production order for the material. When you confirm the last operation, the system generates a goods movement document for the material. The backflush is carried out together with the confirmation steps.
BJ5 Make-to-Stock Production – Discrete Manufacturing
Explain the process step “Post Goods Receipt for Subassembly Production Order”
BJ5 Make-to-Stock Production – Discrete Manufacturing
This process step shows you how to post the goods receipt for the production order.
BJ5 Make-to-Stock Production – Discrete Manufacturing