Roof Dry-In Flashcards
Roofing edge metal should be a minimum ____ X ____ inches, and installed with no more than a ____ inch space between the metal and the fascia.
2” X 4”
1/4”
How is drip edge installed?
Back to front with a minimum 3” overlap
Drip edge at the front and rear of the home cannot be shorter than _____ feet (unless the wall is shorter than that).
3’
What is the tolerance on dings, dents or damage on drip edge metal?
No tolerance
Corners of valley metal are to extend past the eaves a minimum of _____ of an inch, and a maximum of ____ inch.
1/4”
1”
What size L metal is installed at all head walls?
4” X 5”
What size roofing paper/felt does Shea use?
What is the industry standard?
40lb
30lb
What is the head lap and end lap on roofing paper?
Head lap - 4”
End lap - 6”
What happens to the roofing/felt paper at the drip edge metal?
It’s secured with mastic/adhesive
What is the nailing pattern for roofing felt paper?
A maximum of 12” OC
All felt paper is to be cut back a minimum of ______ inches from all gas vent pipes.
2”
The felt paper at all barges (gable ends) is to extend a minimum of _____ inches past the edge of the roof sheeting.
2”
The hip and ridge pole should be completely wrapped with ________ ________?
Felt paper
Diverters are to be completely __________ at all joints?
Sealed
Diverters are to extend past the edge of the roofline, and not have any _______ _________ in the pan?
Nail penetrations