Roof Components Flashcards

1
Q

Steep slope roof coverings may be defined as roof coverings installed on roof that _____ vertically in ______ horizontally or greater

A

Slope 2”
12”
2:12

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Low slope roof coverings that may be installed on roofs or between _____ and ______ slope.

A

¼:12

2:12

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the traditional underlayment for shingle roof covering?

A

15 Asphalt-Impregnated Felt

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Shingles. Close to cut and woven valleys should be flashed using a______ wide strip of smooth roll roofing, or any open valley flashing material.

A

36”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Shingles. Open valleys should be flashed using at least a ______ wide strip of aluminum or galvanize steel or two layers of roll roofing.

A

24 inch

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Concrete and clay tiles.

Underlayment at least _____ is specified under tiles.

Double underlayment is usually specified for a re-slopes between ______ and ______.

A
#30 felt 
2 ½:12 and 4:12
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Clay and concrete tiles.

The minimum slope should be ______.

A

2 ½:12

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Clay and concrete tiles.

Common tile valley types are open and closed. Both valley types should be flashed using a_______ as a base layer.

A

36 inch wide strip of at least #30 felt

An additional layer of at least 22 inch wide strip of galvanized steel with a 1 inch tall diverter in the center should be installed above this base layer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Metal panels are defined as being_____ or more. This distinguishes metal panels from metal shingles.

A

3 ft.²

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Metal panels are installed in one of three ways.
Standing seam roof, Considered a low slope roof. Minimum slope of ______.

Sealed seam roof, minimum slope of _____.

Non-sealed seam roofs, considered steep roof covering with the minimum slope of _____.

A

¼:12
½:12
3:12 same as metal shingles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Is underlayment specified under metal panels?

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The best preventative measure is to correct the cause of ice dams. This involves…

A

Reducing air leaks that allow heat to escape into the attic.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Ice barrier underlayment is often required in areas where ice dams occur. These barriers consist of and impervious underlayment that extends from the eaves at least______ horizontally past the ____ of the house.

A

2 feet

Wall

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Low slope roof coverings maybe defined as roof covering’s installed on roofs that slow between ______ and ______

A

¼:12 and 2:12

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Low slope roof coverings are ______ roof coverings.

A

Waterproof

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Mineral surfaced roll roofing. Can be installed on minimum roof slope?

Is underlayment specified?

A

1:12

Yes. #15

17
Q

Common defect for low slope roof coverings or blisters, cracks, _____ in depressions.

A

ponding

18
Q

Ruth surrounded by vertical sidewalls may drain through rectangular openings in the wall called______.

A

scuppers

19
Q

One scupper or internal drain may not be the only roof drain. The secondary system that is at least the ______ as the primary system should be located ______ above the primary drainage system.

A

same size

2 inches

20
Q

Roof penetrations such as plumbing vents and fuel fired appliance that should be flashed with a ______ , ______, ________

A

Boot, roof jack, thimble

21
Q

Flashing between a roof and sidewall and headwall should be installed in a two component system. The two flashing components are the______ and ______.

A

base flashing any counter flashing.

22
Q

The base flashing should be installed on top of the underlayment. The base flashing vertical flange on the wall should be covered with counter flashing and the counter flashing covered with the water resistive barrier.

Flashing from the high side should overlap the lower flashing at least _____. Base flashing should be at least _____ on the vertical and horizontal legs.

A

2 inches

4 inches

23
Q

Home inspector should carefully evaluate visible areas around the side walls for evidence of water infiltration

A

True

24
Q

Flashing at brick veneer sidewalls should be installed using ______ base and counter flashing.

A

Stepped

25
Q

Kick out flashing should be installed at the end of a roof when the sidewall extends past the roof.

Kick out flashing should turn about a ______ and should be at least_____

A

120° angle

4x4”

26
Q

Head wall flashing. The leg of the base flashing that extends above the roof covering is called the_____ and should be at least _____ wide.

A

apron

4 inches