Adhered masonry veneer, AMV, should extend ______ below the foundation top.
At least 1 inch
Adhered masonry veneer, AMV, should be at least _____ above the ground, or ______ above paved areas and roof.
4 inches
2 inches
Does metal wall covering and roof covering materials be grounded or bonded?
No
Rick and natural stone veneer are usually installed by placing the material on a structural support such as _____ or _____.
Foundation ledge
Lentil, L shaped steal
Brick and natural stone veneer should have an expansion joint which is formed by omitting motar from between bricks and filling the joint with _____ and ______
Backer rod and sealant
The absence of _____ can be the explanation for some cracks observed in brick veneer.
Expansion joints.
Which are not common in residential construction
Home inspector should report the presence of ______ motor joints.
Joints that provide a shelf where water can collect.
Raked and struck
Stucco should be placed over a water resistant barrier, such as grade D paper.
How many layers of building wrap or paper are recommended because the stucco will adhere to the top layer and interfere with the drainage plane.
Two layers
Three coat cement stucco is installed by applying scratch, brown, finish layers of Portland cement.
The total thickness of all three layers is approximately _______.
7/8 inch
EIFS is not stucco. What do the initial stand for?
Exterior insulation and finish system
Visible siding flashing, _____ flashing above window and door header trim and _____ flashing at horizontal seams between sheet of panel siding should be visible Such as cement fiber, hardboard, and would.
______ flashing should be installed around windows, doors and other wall penetrations when vinyl siding in aluminum siding is used.
“L”
“Z”
J channel
Where is the frieze board located?
Under the soffit that meets the vertical wall.
What is the name of the door containing many horizontal pains of glazing that are open and close together with a crank?
jalousie door
Every house should have at least one side hinge door that is accessible from all parts of the house and opens directly to the outside, not through ______.
The garage
The egress door should be at least _____ wide and _____ tall
36” x 80”
The egress door should have a landing or finish floor at least _____ and ______ I’m both sides of the door.
36” x 36”
A landing or finish floor should exist on ______ of every exterior door.
The landing should be at least ______ and ______ in the direction of travel.
Both sides