Risk Management Flashcards
In you initial cost estimate how much contingency did you hold? (Imperial Street)
This was at 10% and was advised based on a risk register which was compiled by myself following a risk workshop with the design team. We looked at the risk list of NRM1 and explored which risks were relevant to the project. The risks amounted to 5% of the contract value.
What is a risk?
Risk is an uncertain future event which would have an effect on the achievement of one or more project objectives.
What is risk management?
- Proactive exercise designed to enable the identification, analysis and effective on-going management responding to risks.
- A process of identifying, assessing and responding to risks associated with the delivery of an objective such as a construction project.
What are the key stages of Risk Management?
1) Identify
2) Assess/Analyse
3 )Respond
4) Monitor and control
Talk me through how you manage risk on your projects.
Risk management workshops where I fill in risk registers and these are monitored and updated at monthly intervals in order to mitigate the risks.
Did you have a risk register on your project? How was it formulated?
This was a document formed following a risk workshop with the project team. Each risks nature was explained qualitatively and quantitatively. This included the probability, impact, mitigation and risk owner of each risl.
How would you go about pricing a risk register?
Firstly I would identify the risks. I would then
What types of risks would you find under employers risks?
- Funds
- Planning refusal
- Force majeure
What type of risks would you find under employer’s change?
- Specific changes in requirements (i.e. in scope of works or project brief during design, pre-construction and construction stages).
- Changes in quality (i.e. specification of materials and workmanship).
- Changes in time.
- employer driven changes/variations introduced during the construction stage.
- Effect on construction duration (i.e. impact on date for completion).
- Cumulative effect of numerous changes.
What type of risks would you find under construction risks?
- Contaminated ground.
- Adjacent structures (i.e. requiring special precautions). Invasive plant growth.
- Tree preservation orders.
- Ecological issues (e.g. presence of endangered species).
- Environmental impact.
What type of risks would you find under design development?
- Inadequate or unclear project brief.
- Unclear design team responsibilities.
- Unrealistic design programme.
- Appropriateness of design (constructionability).
- Ineffective design co-ordination.
What is a risk Mangement strategy?
STARR
S - Share usually through construction contract, exceptional adverse weather, EOT, not loss and expense
T - Transfer - through insurance
A - Avoid - action to ensure risk does not occur. Remove or alternative design/ method
R - Reduce - if a risk does occur the impact will be reduced as much as possible
R - Retain - nothing and keep the risk under control
How do you carry out risk analysis and risk management?
Produce a risk register
- All members of the design team come together and brainstorm as many elements of project risk as possible
- These risks are continually monitored throughout the project progress
- Identified risks can be used to flag, prepare for and reduce the possibilities of their occurrence
What is a risk register?
A tool used in risk management to identify potential risks in a project
The register includes all information about each identified risk, such as nature of the risk, level of the risk, who owns it and what are the mitigation measures in place to respond to it
What approaches can you use to identify risks?
1) Research - similar projects / neighbouring sites
2) Structured interviews / questionnaires - with the project team
3) Checklists / Prompt lists
4) Brainstorming in a workshop environment
5) Risk Register
6) Database of historic risk
What is the aim of risk analysis?
It is concerned with trying to achieve a better understanding of the nature of the identified risks.
Risks have two dimensions that need to be analysed:
- Probability - likelihood of the risk occurring
- Impact - if the risk did occur, what effect could it have on the project objectives?
This allows you to determine which of the identified risks require detailed consideration (high probability with high impact) verses which only need a cursory glance.
What are the benefits of risk management?
1) Increased confidence in achieving project objectives
2) Reduced cost / time overruns
3) Enable decision making based on known variables
4) Risk Management Workshop facilitates team development and encourages communication