Case Study Flashcards
What is the Town and Country Planning Act 1990?
The act regarding planning and development control in the UK. Includes section 106 which requires developers to offset the costs of developments going ahead. Can include affordable homes or local infrastructure.
What are the London Design Guide minimum standards?
The guide is not part of planning policy with the main planning guidance documents remaining the London Plan and the Housing Supplementary Planning Guidance. The guide is instead aimed at complementing planning documents and encouraging designers to aim for the highest quality.
How many kitchen and bathrooms built up to the £1.05m saving?
x
What was the competition requirement for Guinness and the framework contractor?
As the contractor was already part of the framework, they were not subject to OJEU.
After purchasing planning in July 2018, when was the required start on site date?
18 months later. January 2020.
What is a s73 notice?
A part of the Town and Country planning act 1990 which allows an owner to alter their planning conditions or to change the design under a minor material amendment.
What is the LLDC?
The LLDC (London Legacy Development Corporation) was created to continue regenerating East London after the Olympic games. The LLDC are the local planning authority and responsible for approving planning on Imperial Street.
What is the heritage to the area?
There is the three mills studios which are historic listed buildings in the area.
What is a powder coated aluminium window surround?
A surround around the windows which is effectively a window sill all around the window and the outside. Mostly for aesthetic purposes.
What changes in the kitchen and bathroom specification were there?
The premier plus standard included Bosch white goods and premier was Beko. The bathrooms were a different brand of porcelanosa. This includes moving from a floating basin to a pedestal basin.
What was included within your due diligence report?
The report analysed the framework contractor’s submission as well as recommending other options, which included option 1 and 3.
How is a basement constructed?
- Hoarding
- Excavation - open and battened back
- Secant wall piling installed
- Concrete poured
- Drained cavity and pump sump installed
How did you carry out an optioneering exercise for opting for a basement or not?
To do this I measured the basement area, the secant wall piling, piling mat, excavation area, disposal and was able to market test these costs. I then quantified and cost the other option of not having a basement and instead having the plant and cycle stores separately. This amounted to £800k saving.
What were the constraints of building next to a canal?
Very low flood risk however there was a large attenuation tank on the project which was connected with the canal system for water outlet.
What would you do differently if you were to advise the client again on Imperial Street?
x
What is the internal wall build up on Imperial Street?
300mm thick wall. Soundbloc partitions X2 (15mm), Metal I stud with mineral wool insulation(80mm), APR insulation(60mm), Cavity(100mm),Soundbloc partitions X2 (15mm)
Why was there so much detail on internal wall at stage 2?
This element was focused on early and included extra detail than would be typically because of the acoustic requirements by the Trainline.
When was planning approval for the scheme granted?
This was achieved in January 2018, with TGP purchasing the site in July 2018.
What heat source plant was used?
A district heating network - combined heat and power.
How does CHP work?
The heat generated during this process is supplied to an appropriately matched heat demand that would otherwise be met by a conventional boiler.CHPsystems are highly efficient, making use of the heat which would otherwise be wasted when generating electrical or mechanical power. This allows heat requirements to be met that would otherwise require additional fuel to be burnt.
Combined heat and power (CHP) is a highly efficient process that captures and utilises the heat that is a by-product of the electricity generation process.
By generating heat and power simultaneously,CHPcan reduce carbon emissions by up to 30% compared to the separate means of conventional generation via a boiler and power station.
How often do OJEU thresholds get updated?
Every 2 years on 1 January. Last updated on January 1st 2020.
What is the current OJEU minimum?
Threshold for works contracts is £4.7m. Threshold for supplies and service contracts are between £122k - £189k.
What was the price per unit on the consent design and the new design?
This reduced from £236k/unit to £222k/unit.
What is the minimum sprinkler height?
This has recently changed to 11m after a new government review.
What type of sprinklers were used?
Dry pipe sprinklers ( filled with pressurised air, when there is a sudden change in air pressure, the pressure in the system drops and the sprinkler is activated)
Wet pipe sprinkler ( water is released when the room reaches a certain temperature. Facilities must be kept above 0 do the water does not freeze making it useless).
What is required on a fee proposal?
Resource
Client money handling procedure
Complaints handling procedure
Scope outline
How is the heat source brought into the units from the chp?
Heat interface units (HIU) act as a bridge between the central boiler and the heating and hot water systems of the individual apartments.
What are benefits of using CHP than other methods?
Domestic hot water can be provided by heat interface units (HIU) on-demand, without the requirement for cylinder storage, and at a higher flow rate than a typical domestic combiboiler. Heat interface units from Dutypoint Systems are available at standard capacities up to 80kW; most domestic combi boiler ranges have a maximum output of 45kW. Higher capacity units can be configured on request.
How is electricity brought into our homes?
Electricity is distributed via electric distribution substation. At the substation, the high voltage electricity from the high-voltage transmission lines is passed through step-down transformers that lower the voltage. The electricity is then transmitted to network of local electric distribution lines. Before electricity enters a home, the voltage is again lowered using step-down transformers. In most countries the voltage is 220 V AC or 110 V DC. In a home, electricity is distributed to different outlets by network of wires through electrical wiring.
How is electricity brought to substations?
After electricity is generated in power plant, it is time for transmission. This is done by using step-up transformers that increases the voltage. This high voltage electricity is transmitted through a network of electrically conductive wires of aluminum or copper. These lines are called high-voltage transmission lines that can transmit electricity over long distances.
What is included in a fee proposal?
- Fees and payment (resource - hourly/daily rates)
- Clients money handling procedure
- Complaints handling procedure
- The services (scope - EA, QS, PM etc)
- Client’s brief (includes informtion such as description of site, description of project, programme, client objectives)
- Need for collateral warranties/ 3rd party rights
What are the types of OJEU tendering?
Open procedure. There is nopre-qualification processor short-listing process. Anyone that responds to theOJEUnoticeis issued with the fullcontract documentation.
Restricted procedure. There is apre-qualification process, and only short-listed candidates are invited totender.
Competitive dialogue procedure. There is apre-qualification process. Short-listed candidates are invited to take part in a dialogue process during which the nature of theprojectmay be discussed and possible solutions may be developed. When the dialogue process iscomplete, finaltendersare invited.
Competitivenegotiationprocedure. There is apre-qualification process. Short-listed candidates are invited to take part in anegotiationprocess. This process does not have to follow any particular rules, and has no formal ending. This means thatnegotiationscan continue even after the preferredbidderhas beenappointed.
What guidance would you need for RICS appointment?
RICS Form of consultancy appointment/ short form of consultancy appointment
What was the rate of the paving and what was the rate of the hoggin clay based surface?
The paving amounted to £125/m2 and hoggin clay based surface was £60/m2. The area was at 1,500m2. This amounted to £100k saving.
What is the build up to the hoggin clay based surface and the paving?
The paving was pennant stone and included a 100mm sub base, 250mm sub base as well as labour, sundries and subcontractor prelims. This amounted to £125/m2.
The hoggin clay based surface had a much cheaper PC rate at £25/m2. The sub base was still necessary however.. This amounted to £60/m2.
What were the specification differences between premier plus, premier and standard?
x