Quantification And Costing Flashcards
Talk me through NRM and differences between 1,2 and 3.
NRM_1 Order of cost estimating and cost planning
NRM_2 Detailed measurement for building works
NRM_3_Building Maintenance Works
What is IPMS?
International property measurement standards. Introduced to standardise property measurement across the world. Research has found that measurements have been up to 24% different.
Can you tell me what the difference between NRM 1 and 2 are and how this differs from the RICS Code of Measurement.
RICS code of measurement practice is now obsolete but described the different areas used in property.
NRM is measurement rules for construction and lifecycle costing work.
If I was a developer and told you that I had a site in the middle of London which I wanted to build a residential block on what would you advise me in relation to cost.
I would say this depends on site considerations, the method of construction, the procurement and the design, however most residential projects in London range between £2500 to £3500/M2 GIFA.
GIFA v GEA v NIA
GEA - Gross external area (IPMS 1)
GIA - Gross internal area (IPMS 2)
NIA - Net internal area (IPMS 3)
Replaced by IPMS from January 2018, RICS professionals are expected to adopt the Property Measurement Professional Statement in place of the Code for offices and Residential unless local laws, or a client require an alternative. Professional Statements for other property classes including industrial and retail will be added over time as the IPMS is expanded.
How do you quantify internal partitions? Cost Plan. Does this differ from contractor.
Section 2.7 of NRM1. details including thickness to be stated. Measured in m2 on the centre line. No deduction made for openings.
Talk me through how you would measure concrete foundations.
For piles the pile mat would need to be measured in m2. A cost for the piling plant and moving the piling rig would need to be factored in and measured by nr. The pile details would need to include diameter (mm) and depth of piles (m) and measured in nr. The disposal of excavated material would need to be cost and measures in m3. Cutting off tops of the pile would need to be measured by nr.
How do you measure steel. What is the current cost?
Under NRM1 steel needs to be measured in tonnage. The fire protection detail needs to be in the description. The tonnage for each steel member can be found on the structural engineers schedule.
What are the ways of valuing change?
- Similar nature – use pricing schedule
- Contractors quotes
- Dayworks
- First principle
- Schedule 2 quote
How much was the crane hire on St Leonards?
£2,000/week
When did the IPMS residential come into effect?
May 2018
What is the difference between IPMS and code of measurement practice?
IPMS defines GEA, GIA and NIA as IPMS 1, IPMS 2, IPMS3. It is used worldwide not just the UK, and there are slight measurement differences, most notably internal dominant face.
What is the internal dominant face?
The inside finished surface comprising 50% or more of the surface area for each vertical section forming an internal perimeter.
Do you know the valuation rules for changes in the JCT contract?
This differs between contracts. In JCT DB the pricing document will need to be used, if not then a fair and reasonable rate. If this is not applicable, dayworks would need to be used.
What are the valuation rules in the contract for St Leonard’s?
- The valuation of additional or substituted work shall be consistent with the values of work of a similar character set out in the Contract Sum Analysis, making due allowance for any change in conditions under which work is carried out and/or any significant change in the quantity of the work so set out.
- The valuation of the omission of work set out in CSA shall be in accordance.
- Any valuation shall include necessary allowances for any addition or reduction of site administration, site facilities and temporary works.
- Non Measureable Works Day works = prime cost of all material labour and plan with a % for prime cost.
What is a schedule 2 quotation?
The procedure in Schedule 2 aims to regulate the prices of quotations submitted by the contractor. The contractor’s quotation must cross reference, where relevant, to the rates and prices in the contract bills. Therefore, the contractor cannot simply disregard its tender rates and offer inflated prices when quoting for variations.
What is the rule for variations under the adjusted bill rates under JCT?
If the conditions under which the work is carried out or the quantities of work are changed by the variation, the valuation of that variation is based on bill rates with a ‘fair’ allowance made for the difference in conditions and/or quantity.For e.g. if substructure work is due to be done in summer but is then in winter, the cost may be different because of weather related issues and shorter days etc.
What is the rule for variations under fair rates and prices under JCT?
Where the variation relates to work for which there is no bill item, the work should be measured and valued at ‘fair rates and prices’. Usually the parties agree to use actual cost as the basis for establishing a ‘fair rate’. In these cases the employer or its quantity surveyor may ask the contractor to provide copies of invoices and details of labour time and cost for doing the work. Once the cost is established a reasonable percentage is usually added to provide an allowance for contractor’s overheads and profit.
What is the rule for variations under dayworks in JCT?
If variations cannot be properly measured they can be valued on a ‘daywork’ basis.
These can be valued as:
Option 1 - Percentage addition (prime cost to which a % is added for OHP)
Option 2 - All inclusive rates (quoted at tender and incorporated in the contract documents. Include allowance for OHP)
What are the benefits of having a standard method of measurement?
1) Provides structure for information
2) Defines units of measurement for different items (m, m2, m3, t)
3) Provides rules as to what is included within each item
4) Defines terms used to avoid disputes
5) Allows familiarity to development so measurement becomes quicker and easier
6) Provides clear system of structuring other project information