Risk Management Flashcards

1
Q

What are the key points highlighted in the RICS guidance note on risk management?

A

The document highlights the following key areas:

  • proactive risk identification
  • collaborative communication
  • contractual clarity
  • compliance with legal standards
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a risk in construction?

A

In construction, a risk is any uncertain event or condition that could impact project objectives, leading to potential delays, cost overruns, or quality issues.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the risk mitigation strategies?

A

risk avoidance,
risk reduction,
risk transfer,
risk sharing,
risk retention.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What were the key points from the Arcadis CPD session on risk management?

A
  • The learning outcome from this webinar was learning how best to manage client expectations and how to mitigate potential risk on construction projects.
  • It also highlighted the importance of the risk register when managing the contingency allocation.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How did you handle the risk workshop on the HTA project?

A
  • I held a workshop with the project team to gather any potential risks that the project and ensured they were captured within the risk register.
  • I then ensured that it was agreed between all parties which risks each would take ownership of so everyone was aware of their responsibilities.
  • I also ensured that future meetings were put in place in order to review and update the risk register accordingly.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What were some of the risks captured during the risk workshop and how did you propose to handle them on the HTA project?

A
  • Risk to the programme of not having ownership of the building in time before construction.
  • Site Conditions and the impact of not having the enabling works package completed prior to the main works construction.
  • Supply Chain Disruptions with delays or shortages in materials and equipment can affect project timelines in Q3 of 2021.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the purpose of the risk register?

A
  • The risk register in construction projects serves to systematically identify, assess, and manage potential risks.
  • It provides a structured document for tracking and mitigating risks throughout the project lifecycle, aiding in proactive decision-making and ensuring the project’s successful delivery by minimizing adverse impacts.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why only at stage 2 did you compile a risk register? how did you determine the 10% allowance during the early design stages on project X?

A
  • During the early design stages, risk was allowed for with a contingency allowance as a overall percentage of the cost estimate.
  • Contingency is a sum included within the estimate to cover unknown expenses or unmitigated risks during a project.
  • As the design develops a risk register can be compiled with probability and cost impact assigned to each item which can then form the total project contingency.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What was the impact on the Russia/Ukraine war on Project X and how did you tackle managing this?

A
  • With the project already procured and a contract sum agreed the main concern was any supply chain disruption with getting materials on site.
  • When the news became apparent we immediately put in a meeting with the contractor to discuss if they could see any risks within the supply chain that would impact the programme.
  • The contractor explained that they could not foresee any risks however we chose to monitor this until project completion.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What does NRM1 say about managing risk and contingencies?

A

It is recommended that separate allowances be made for each of the following:

  • Design development risks:
  • an allowance for use during the design process to provide for the risks associated with design development, changes in estimating data
  • Construction risks:
    an allowance for use during the construction process to provide for the risks associated with site conditions
  • Employer change risks:
    an allowance for use during both the design process and the
    construction process to provide for the risks of client driven changes.
  • Employer other risks:
    an allowance for other client risks (e.g. early handover, postponement, acceleration, availability of funds, liquidated damages).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly