You have received a request to add a new scope item to your project and need to follow the change management process.
Move the four actons to the answer area and place them in the correct order.
Actons in Order
A. Identfy the change
B. Assess the change impact
C. Approve or deny the change
D. Implement the approved change
ABCD
Your manager explains that the project team starts every new project with a design stage where they create a design, test the design,
make updates to the design, retest, and then create a final design. After this design stage, they create and follow a detailed project
plan for all the remaining project deliverables
Which project management approach are they using?
A. Hybrid
B. Predictve
C. Scrum
D. Adaptve
C. Scrum
or pwede ring A. Hybrid
You have contracted an external supplier to provide a tool needed for the development phase in a project. The tool has been
delivered and the project team finds the tool acceptable and they are using it.
Why should you now close the contract with the supplier?
A. To inform the procurement team that the new tool has been delivered
B. To prevent the supplier from contacting team members for payment
C. To request that the supplier be paid for the delivery of the tool
D. To thank the supplier for delivering the tool according to the contract
C. To request that the supplier be paid for the delivery of the tool
A community center director hires your project team to build a playground for the families in the community
Upon completion of the playground, who is responsible for the final acceptance of the project?
A. The director (your client)
B. The project team
C. The families in the community
D. The project manager (you)
A. The director (your client)
As a project manager, which actvity should you perform when using a predictive project management approach?
A. Create a detailed project plan that includes all of the project activities
B. Begin the current sprint before planning for the next one
C. View the backlog to determine the next planning actvity required
D. Review deliverables after each iteration with the customer.
A. Create a detailed project plan that includes all of the project activities
What is the purpose of following a change management process?
A. To document a change in scope and any impact to the project
B. To delay a new feature request so the customer will reconsider any changes
C. To inform the customer that your team takes their suggested product changes seriously
D. To show the project sponsor that you follow correct procedures
A. To document a change in scope and any impact to the project
You are one of the event planners for a large town festval. You are reviewing a list of potental bakeries that will supply the desserts
at the festval. When you review the list, you notce that your favorite aunt owns one of the bakeries, but no one else on your team
knows this informaton
According to project management ethical guidelines, what should you do?
A. Tell your aunt to lower her prices so that she can be easily selected for the event.
B. Inform your aunt that she will need to remove her bakery from the selecton list.
C. Proceed with the selecton process, confident that you will act fairly.
D. Notfy your supervisor that your aunt’s bakery is on the list.
D. Notfy your supervisor that your aunt’s bakery is on the list.
A project team is arguing about the start date for an important task in the project. The project sponsor intervenes and sets the start
date.
Which type of conflict resoluton technique is the project sponsor using?
A. Avoiding
B. Smoothing
C. Forcing
D. Collaboratng
C. Forcing
Who is responsible for overseeing the daily actvites of a project from start to finish?
A. Project manager
B. Client
C. Vendor
D. Sponsor
A. Project manager
What is the primary goal of creatng a work breakdown structure (WBS)?
A. To prepare an organizatonal chart for the project team members
B. To describe the key stakeholders and their roles in the project
C. To decompose the project work into assignable work actvites
D. To determine which team members will be responsible for each project actvity
C. To decompose the project work into assignable work actvites
As a project manager, how should you encourage your team to be focused, energized, and positve for the duraton of a project?
A. Discover what personally motvates each team member.
B. Report poor behavior to upper management.
C. Give each team member the authority to change project deadlines
D. Rank team members’ performance during team meetngs.
A. Discover what personally motvates each team member.
Your project team is using an agile project delivery method. In preparaton for an upcoming meetng, your manager asks you to
review the prioritzed list of deliverables.
What should you review?
A. Kanban board
B. Backlog
C. User story
D. Work breakdown structure (WBS)
A. Kanban board daw
Pero dapat: D. Work breakdown structure
As a project manager, what informaton do you need to include in a status update to your boss?
A. Project work that has been completed
B. A list of project stakeholders
C. Project goals and objectves
D. A descripton of the project scope
A. Project work that has been completed
What is a vendor?
A. A business analyst who works with the finance team for a project
B. An external supplier who provides goods or services to a project
C. A procurement team member who negotates contracts for a project
D. An experienced business professional who can sell the final product
B. An external supplier who provides goods or services to a project
Predictve and adaptve project management approaches have different key characteristcs.
For each key characteristc, select Predictve or Adaptve.
- Reliance on customer input throughout the project
- Increased flexibility to make project adjustments
- Completon of project according to the project management plan created at the
beginning of the project
Adaptve, Adaptve, Predictve (in order)
You are managing a project that is experiencing significant scope creep
What is the impact on the project?
A. The project will require fewer resources to develop.
B. The project will take additonal tme to complete.
C. The project will be assigned a new project manager.
D. The project will include fewer deliverables.
B. The project will take additonal tme to complete
You are estmatng the cost of a project by using the budget from a similar project last month.
Which type of budget estmaton technique are you using?
A. Expert judgment estmaton
B
B. Three-point estmaton
C. BoƩom-up estmaton
D. Analogous/historical estmaton
D. Analogous/historical estmaton
Why should you archive project documents and processes?
A. To complete the project management plan
B. To store all project documents on the project manager’s personal computer
C. To keep a historical record of project actvites
D. To redistribute remaining resources to other projects
C. To keep a historical record of project actvites
In a project, what describes work that should be included and work that should be excluded?
A. Project baseline
B. Scope statement
C. Business case
D. Work breakdown structure (WBS)
B. Scope statement
What is project procurement?
A. The purchasing of external goods and services needed to complete a project
B. The analysis of the business requirements needed to complete a project
C. The identficaton of all the funding requirements needed to complete a project
D. The planning of all communicaton methods needed to complete a project
A. The purchasing of external goods and services needed to complete a project
Which project characteristc suggests that a predictve project management approach should be used?
A. High levels of change and risk
B. Defined deliverables and deadlines
C. Evolving goals and requirements
D. Multple releases of product features
B. Defined deliverables and deadlines
Which component of the project management plan outlines the work needed to meet project objectves and deliverables?
A. Cost management plan
B. Scope management plan
C. Resource management plan
D. Schedule management plan
B. Scope management plan
You are evaluatng the skills needed in your project team to successfully complete a project.
Which component of the project management plan are you working on?
A. Cost management plan
B. Scope management plan
C. Schedule management plan
D. Resource management plan
D. Resource management plan
What impact does gold platng have on a project?
A. The scope increases and the cost to the customer remains the same.
B. The scope increases and the cost to the customer increases
C. The scope remains the same and the cost to the customer decreases.
D. The scope remains the same and the cost to the customer increases
A. The scope increases and the cost to the customer remains the same.