Resource And Scheduling Optmisation Flashcards

1
Q

Start and finish dates can be calculated with regard to available resources and external constraints as well as project logic. Once established, the schedule will be used throughout the project to produce what ?

A

• update progress, forecast performance and communicate this information to stakeholders

• show team members when tasks are due to be completed and the overall project duration

• show key milestones and progress towards achievement of these when work starts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what does critical analysis use scheduling technique for?

A

Critical path analysis uses a scheduling technique to predict project duration by analysing which sequence of activities has the least amount of scheduling flexibility and is, therefore, critical if the planned overall duration is to be achieved

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

why do dependencies exist?

A

The dependencies exist because of the logical relationship between the activities dictated by the technical characteristics of each activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what does establishing a logic between activities enable?

A

Establishing the logic between the activities enables a precedence network to be determined that shows the relationship between activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what is the well known common dependency?

A

The most common dependency is finish to start, and this acts as a default choice until sufficient information is known about the individual activities to consider an alternative

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what does the term float mean and what is it created for?

A

Float’ is a term used to describe the flexibility with which an activity may be rescheduled. Float is created when a shorter-duration activity is in parallel with a longer-duration activity in the network

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

explain the difference between free float and total float?

A

Total float is defined as the time by which an activity may be delayed or extended without affecting the overall duration or violating a target finish date.

Free float is defined as the time by which an activity may be delayed or extended without affecting the start of any succeeding activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what is a milestone and why is it good to have one?

A

A milestone is defined as a key event selected for its importance in the schedule, commonly associated with tangible acceptance of deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why is it a good practice to use milestones?

A

It is good practice to produce a milestone schedule to show stakeholders the major milestones and for reporting current and forecast progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a Gantt chart created for ?

A

Gantt chart is created to show the activities against a timeline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what can be used to show a high-level summary of current progress and who needs to see it?

A

A milestone chart will provide the necessary level of communication

sponsors and senior management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what will a milestone chart show and what will a Gantt chart show?

A

The milestone chart will show a stripped-down version of the schedule with activity bars removed

Gantt chart is created to show the activities against a timeline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what is a timebox?

A

A timebox is an iteration with a fixed end date that is not allowed to change, thereby adjusting the scope and quality to deliver on time and to cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

what is the main objective of resource optimisation ?

A

The main objective of resource optimisation is to make sure that all resources are used optimally

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

what is a resource histogram?

A

a block graph showing the quantity of resource that has been allocated over the time schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

what is one question answered by resource levelling?

A

With the resources available, when will the work be finished?

17
Q

list 5 ways resource levelling can be achieved by a project manager?

A

• Redefining the scope of the activities to be undertaken by the particular resource concerned.
• Redefining the specification
• Increasing task duration to reduce the overall resource requirements.
• Increasing resources on earlier tasks to bring workload forward, such that peaks in the future are reduced.
• Moving activities that are not on the critical path to reduce demand at peak times

18
Q

what is resource smoothing and its objective?

A

Resource smoothing is used when time is more important than cost. The objective is to deliver the work within the fixed timescale.

19
Q

what is a procurement strategy?

A

The procurement strategy is the high-level approach for securing the goods and services required from external suppliers to satisfy project, programme and portfolio needs

20
Q

what are the key two questions asked by sponsor and when using a procurement strategy?

A

• How much risk to retain in the project and how much to share with suppliers in the supply chain?
• On a continuum from transactional to collaborative, what type of relationship is desired with different suppliers, and why?

21
Q

what is considered when deciding the best route for the procurement strategy?

A

• make or buy decision
• supplier selection
• contractual relationship
• reimbursement methods
• contract administration