Resource And Scheduling Optmisation Flashcards
Start and finish dates can be calculated with regard to available resources and external constraints as well as project logic. Once established, the schedule will be used throughout the project to produce what ?
• update progress, forecast performance and communicate this information to stakeholders
• show team members when tasks are due to be completed and the overall project duration
• show key milestones and progress towards achievement of these when work starts
what does critical analysis use scheduling technique for?
Critical path analysis uses a scheduling technique to predict project duration by analysing which sequence of activities has the least amount of scheduling flexibility and is, therefore, critical if the planned overall duration is to be achieved
why do dependencies exist?
The dependencies exist because of the logical relationship between the activities dictated by the technical characteristics of each activity
what does establishing a logic between activities enable?
Establishing the logic between the activities enables a precedence network to be determined that shows the relationship between activities
what is the well known common dependency?
The most common dependency is finish to start, and this acts as a default choice until sufficient information is known about the individual activities to consider an alternative
what does the term float mean and what is it created for?
Float’ is a term used to describe the flexibility with which an activity may be rescheduled. Float is created when a shorter-duration activity is in parallel with a longer-duration activity in the network
explain the difference between free float and total float?
Total float is defined as the time by which an activity may be delayed or extended without affecting the overall duration or violating a target finish date.
Free float is defined as the time by which an activity may be delayed or extended without affecting the start of any succeeding activity.
what is a milestone and why is it good to have one?
A milestone is defined as a key event selected for its importance in the schedule, commonly associated with tangible acceptance of deliverables
Why is it a good practice to use milestones?
It is good practice to produce a milestone schedule to show stakeholders the major milestones and for reporting current and forecast progress
What is a Gantt chart created for ?
Gantt chart is created to show the activities against a timeline
what can be used to show a high-level summary of current progress and who needs to see it?
A milestone chart will provide the necessary level of communication
sponsors and senior management
what will a milestone chart show and what will a Gantt chart show?
The milestone chart will show a stripped-down version of the schedule with activity bars removed
Gantt chart is created to show the activities against a timeline
what is a timebox?
A timebox is an iteration with a fixed end date that is not allowed to change, thereby adjusting the scope and quality to deliver on time and to cost
what is the main objective of resource optimisation ?
The main objective of resource optimisation is to make sure that all resources are used optimally
what is a resource histogram?
a block graph showing the quantity of resource that has been allocated over the time schedule