Estimating Flashcards
WHAT IS INVOLVED IN SUCCESS OF A PROJECT?
Success involves controlling deployment and ensuring that there is good information about progress and performance.
What is a team?
Groups of people with a common aim are called a ‘team’ on the assumption that the people will not only cooperate with each other but also collaborate to innovate and perform
what is considered before an estimate is completed?
the point in the life cycle where the estimate is being carried out, the time available and the amount of detailed information that exists concerning scope and working approaches
what is bottom up method?
detailed estimates that can be produced for labour and non-labour resources to complete the activities in scope
what is an analytical estimate used for?
Analytical estimating can only be used to produce a cost estimate and not an estimate of duration
what does parametric method use?
This estimating method uses a statistical relationship between historical data and other variables to calculate an estimate
Parametric estimating can be one of the most accurate techniques for determining what?
a project’s duration and cost,
What is an estimating funnel ?
This increase in accuracy from concept through to implementation