Estimating Flashcards

1
Q

WHAT IS INVOLVED IN SUCCESS OF A PROJECT?

A

Success involves controlling deployment and ensuring that there is good information about progress and performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a team?

A

Groups of people with a common aim are called a ‘team’ on the assumption that the people will not only cooperate with each other but also collaborate to innovate and perform

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what is considered before an estimate is completed?

A

the point in the life cycle where the estimate is being carried out, the time available and the amount of detailed information that exists concerning scope and working approaches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what is bottom up method?

A

detailed estimates that can be produced for labour and non-labour resources to complete the activities in scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what is an analytical estimate used for?

A

Analytical estimating can only be used to produce a cost estimate and not an estimate of duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what does parametric method use?

A

This estimating method uses a statistical relationship between historical data and other variables to calculate an estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Parametric estimating can be one of the most accurate techniques for determining what?

A

a project’s duration and cost,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is an estimating funnel ?

A

This increase in accuracy from concept through to implementation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly