Repudiation and restriction on the right to terminate Flashcards
What is repudiaiton
When a party display an inability or unwillingness to perform their obligations under the contract
What factors can be used to indicate repudiation?
Words, conduct or factual inability to perform. Includes a party seeking to terminate where they have no right to do so.
When is repudiation most useful?
When a party seeks to terminate but there has been no breach of the contract.
Can you terminate for an anticipatory breach?
Yes - an anticipatory breach can indicate an unwillingness/inability to perform obligations under the contract.
When will damages relating to an anticipatory breach will be available?
When the contract is terminated
If the contract is affirmed there will be no right to damages unless and until the breach actually occurs
What are the two choices when there is a right to terminate?
○ Accept the termination
○ Affirm the contract
Test for repudiation
Would a reasonable person believe that the defendant did not intend, or was unable, to perform obligations under the contract that related to the whole, were conditions, or were otherwise fundamental to the contract (Carr v Berriman)
Reasons for repudiation doctrine
• There is an implied promise in every contract that neither party will repudiate his obligations (whether or not the time for performance has arrived) without just cause
A party should not be bound by a contract that the other party is unwilling or unable to perform
Carr v J A Berriman Pty Ltd (1953) CLR principle
If a reasonable person believed that the defendant did not intend, or was unable, to perform obligations under the contract that related to the whole, were conditions, or were otherwise fundamental to the contract the contract will be repudiated
- Can be words or conduct
- Small breaches can be combined to indicate repudiation
Carr v J A Berriman Pty Ltd (1953) CLR facts
• Contract to build a factory between site owner (Carr) and builder(Berriman)
• Site owner was required to excavate the site by a certain date
• Builder required to provide steelwork
• He didn’t show any sign of excavating the site
• Builder entered a tender to get steelwork
• Site owner sourced own steel and wrote to builder saying this
(Breach: not excavating site, getting own steel)
Carr v J A Berriman Pty Ltd (1953) CLR decision
Breach one: Not excavating. Affirmed by buying steal - no right to terminate.
Breach two: Buying steal instead of using builder’s steal. Lost builder significant profits. Carr knew that he had tendered for steal.
Combination of breaches evinced an intention not to be bound by the contract - right to terminate through repudiation
Progressive Mailing House v Tabali 1985 CLR principle
A number of breaches can combine to show an intention to repudiate
Progressive Mailing House v Tabali 1985 CLR facts
• If the rent goes unpaid for 14 days the lessor can re-enter the premises
• Required landlord to carry out works on the property before the tenant entered the property
• Tenant could take possession 14 days after notice in writing by the tenant that works had been completed
• Ignored this and moved in before letter
• Received the letter but wasn’t satisfied with the required work and stopped paying rent
• Damaged the house
• Sublet the premises
The lessor wanted to terminate to claim lost rent and loss of bargain
Progressive Mailing House v Tabali 1985 CLR decision
• None of the breaches in isolation was sufficient to repudiate
- The breaches of contract; damages, refusal to rectify, refusal to pay rent etc. combined to repudiation, therefore the leaser was entitled to damages for the loss of bargain
Goods Act 1958 (Vic) s 38(2)
(2) Where there is a contract for the sale of goods to be delivered by stated instalments which are to be separately paid for, and the seller makes defective deliveries in respect of one or more instalments, or the buyer neglects or refuses to take delivery of or pay for one or more instalments, it is a question in each case depending on the terms of the contract and the circumstances of the case whether the breach of contract is a repudiation of the whole contract or whether it is a severable breach giving rise to a claim for compensation but not to a right to treat the whole contract as repudiated.
Maple Flock Co Ltd v Universal Furniture Products [1934] principle
When considering if a breach of an installment contract is sufficient for repudiation courts must take into account the quantative ratio of the breach to overall contract, and the probability of the breach being repeated
Maple Flock Co Ltd v Universal Furniture Products [1934] facts
- Maple flock provided flock for use in furniture
- 3 1 tonne deliveries each week
- Flock would not exceed statutory standard of chlorine (less than 30 parts of chlorine residual)
- 16th loads had 250 parts of chlorine
- Furniture accepted several more loads then purported to terminated
- Had maple flock repudiated it’s obligations under the whole contract?
Maple Flock Co Ltd v Universal Furniture Products [1934] decision
- Must take into account the quantative ratio of the breach to overall contract, and the probability of the breach being repeated
- Unlikely to be repeated
- 15 uneventful deliveries before, and several after the delivery
- Court could not confer any intention by maple flock to repudiate the contract
- The single incident was not enough
Woodar Investment Devt v Wimpey Constructions 1980 principle
If arguing unwillingness you must evince an intention not to be bound. If the party is attempting (but struggling) to uphold the contract there is no intention.
Woodar Investment Devt v Wimpey Constructions 1980 facts
• Builders licensing board owned the leased land
• Truck company continually late with payments
• Payments were made but late or short (which were made up later)
• Account was constantly in deficit
• Multiple cheques bounced
• Owed about $5500
Builders sought to terminate
Woodar Investment Devt v Wimpey Constructions 1980 decision
- There was not sufficient evidence of a fundamental inability to pay
- Main argument was an unwillingness - the truck company was unwilling to participate in the contract; they were evincing an intention to no longer be bound
- Court: Principle is correct but it does not apply in this case. The only possible inference drawn from these facts was that there was financial difficulties which made it difficult for the rent to be paid - but from this you cannot infer that they didn’t intend to be bound. They continued to attempt to make payments
DTR Nominees v Mona Homes (1978) CLR principle
There will be repudiation if a party insists on the incorrect interpretation ‘willy nilly’ in the face of clear enunciation of the true agreement
- looks at subjective view of parties (honesty in belief)
DTR Nominees v Mona Homes (1978) CLR facts
- Land developer proposed to sell 35 blocks of land
- Contract to sell 9 blocks to one builder
- Condition that plan of subdivision (which was attached to contract) had been lodged with council and vendor would proceed to have lodged with council as deposited plan
- Builder wasn’t required to complete plan until it had been registered with council as deposited plan
- Land developer though it could lodge a plan showing lots 1-9, instead of all 35 lots
- Developer lodged plan with council then asked builder to pay for land
- Builder purported to terminate the contract because of the misunderstanding (all blocks should have been on the plan)
DTR Nominees v Mona Homes (1978) CLR decision
- Land developer genuinely believed he had done the right thing
- Builder took no steps to inform him of the correct method before terminating - he was unaware of the correct interpretation
- No repudiation
Is there repudiation if a party doesn’t comply with the contract due to an erroneous interpretation?
• If a party won’t except a contract except on their erroneous interpretation they may be subject to repudiation
Depends on the honesty of the belief and if efforts have been made to explain the correct terms of the contract to them.
Eminence Property Developments Ltd v Heaney [2010] princple
Looking at all the circumstances objectively, that is from the perspective of a reasonable person in the position of the innocent party, the contract breaker has clearly shown an intention to abandon and altogether refuse to perform the contract.