Remedies I Flashcards
What is primary remedy for breach of contract?
Damages.
Damages are never award to punish the party in breach, not in Australia - Addis v Gramophone.
What are the three ways to assess damages?
- Expectation measure
- Reliance measure
- Restitutionary measure.
Expectation measure Example
Where Anna enters into a contract with Bill. As a result of the contract she has an expectation that Bill will perform. If Bill fails to perform damages are designed to put Anna in the position that she would have occupied had the contract been performed.
Reliance measure example
Anna enters into a contract with Bill. Bill fails to perform. As a result of the contract Anna has relied to her detriment. Damages are designed to put her in the position she would have been if the contract had not been entered into.
Damage is worked out about expenditure that the plaintiff has incurred in reliance.
Restitutionary Measure example
Australia is less concerned with this measure.
Anna enters into a contract with Bill. Bill fails to perform. Damages here reflect a return of profit or gain made by Bill. It’s not about compensation, but getting the gain from Bill that he gets by not performing.
Example of how to calculate.
Anna agrees to buy a car from Bill for $10,000. The market value of such a car is only $10,000. The value of the car delivered is $5,000 (because it’s faulty in some way). Anna receive the car but it is worth less than the car she was promised.
Expectation measure is worked out on the basis that the contract was performed according to it’s term namely the delivery of a car worth $10,000.
Damages are calculated by deducting the value of what was received (the market value) from the value of what was actually delivered i.e. 10,000 - 5,000 = 5,000.
Reliance measure is worked out on the basis that the contract was never entered into. Anna would never have parted with 10,000 and never received a car worth 5,000. Damages are calculated by deducting what was actually received from what was paid i.e. 10,000 - 5,000 - 5,000.
For when the market price and contract price are different.
Anna agrees to buy a car from Bill for 10,000. A car of the sort promise costs of 8,000 in the market. The car delivered is worth 5,000.
Expectation measure: 8,000 - 5,000 = 3,000.
Look at market value of the thing at time of contract and deduct the value of the thing actually received.
Reliance measure: 10,000 (sum paid) - 5,000 (what it was worth) = 5,000.
Another example
The car is worth 12,000 and Anna has paid 10,000. Car delivered is worth 5,000.
Expectation measure: 12,000 - 5,000 = 7,000
Reliance measure: 10,000 - 5,000 = 5,000.
When do you calculate damages for expectation measure?
For the market value of the thing in an expectation measure, the market value of the thing contracted for at the time of BREACH.
When is the date for assessing damages?
Almost always, assessing the damages is at the date of breach.
Burden of proof is on plaintiff to prove loss on the balance of probabilities. - Commonwealth v Amann
What is the rule for Expectation Damages?
As in Robison v Harman - “where a party sustains a loss by reason of a breach of a contract, he is so far as money can do it, to be placed in the same situation, with respect to damages, as if the contract had been performed.”
This statement has been approved in Australia in Commonwealth v Amann Aviation.
Most straightforward case is where market price is stable. E.g. If Anna buys wheat from bill for 100,000 and the market value at time of breach is 100,000. Then her losses are zero.
Suppose market value at time of breach rises to 200,000. THen her losses are 100,000.
Suppose market price drops to 80,000 and Anna refuses to pay. then BILL can recover 20,000 for loss of profit.
Limitations to expectation measure.
Not all losses can be recovered. Limitations include:
- Causation
- Remoteness
- Mitigation
- Contributory Negligence
Special category of damage where special rules apply. What is the problem of cost of cure damages?
For example, the problem where a house is built 30cm too shore. Technically, the house is still worth 100,000 but is not worth less so expectation loss is very low or even 0.
Ruxley v Forsyth - case for Qld
P entered into contract with D to build a swimming pool. Specifications under contract that pool be 7 foot 6 inches. Pool was only 6 foot 9 inches at deep end. He hadn’t gotten the pool he contracted for. But there was no difference between market value and actual value, so damages would be 0 for expectation measure.
He argued he should be entitled to recover the cost of digging up the whole pool and starting again. Damages of this sort are known as COST OF CURE DAMAGES.
You’re asking for damages to in essence, allow you to rectify the breach.
Held: HOL say no. They say such an award would be unreasonable, but also accept that sometimes you can recover in some cases. In this case however, such an award would be disproportionate to any benefit that would result.
What is the position in Australia regarding Cost of Cure damages?
1
HC says you can recover damages to rectify the damage, but it can’t be disproportionate to the benefit.
Bellgrove v Eldridge - House foundations were built very badly and weren’t in accord with the contract. P argued to claim cost of cure damages. He wanted cost of cure damages for destroying the house and rebuilding which would have cost 500% more than just fixing the remedy which was only 3500.
Nevertheless Courts allowed cost of cure damages.
They said they would only award cost of cure damages in exceptional circumstances which are:
1. Reasonable; and
2. Necessary to award cost of cure damages.
Courts also said whether the money was spent to repair it was irrelevant.
Courts have suggested some personal preference is allowed. But not unreasonable. E.g. painting a house yellow, when you wanted purple is allowed. But building a house using second hand bricks in order to get my house looking old, but get’s built using new bricks, not allowed.
What is the position in Australia regarding Cost of Cure damages?
2
Westpoint Management v Chocolate Factory Apartments
Said test for cost of cure damages is:
1. Reasonable
2. Necessary
They also said a consideration is whether the work was ever to be carried out, which is opposite to Bellgrove.
Usually where you won’t get cost of cure damages is where the innocent party is using a ‘technical breach’ to get an enormous sum of money. Ruxley was one such case.
Tepko has made cost of cure damages fundamental. Before Tepko, it was merely an exception.