Frustration Flashcards
What is frustration?
“Frustration of a contract takes place when there supervenes an event (without default of either party and for which the contract makes no sufficient provision) which so significantly changes the nature of the outstanding contractual rights and/or obligations from what the parties could reasonably have contemplated at the time of its execution that it would be unjust to hold them to the literal sense of its stipulations in the new circumstances; in such cases the law declares both parties to be discharged from further performance.” - Lord Simon in National Carriers v Panalpina.
Basically, frustration is:
1. An event which significantly changes the nature of contractual rights.
Remedies for Frustration?
The traditional rule for frustration, money paid prior to the frustrating even can’t be recovered back. Re Continental.
This is because obligations prior to the frustrating event remain binding. Where a contract is frustrated, obligations which arise after the point at which the contract is frustrated, are extinguished.
Exception to the rule in Fibrosa v Fairbairn - where a payment was made and the consideration had totally failed, then the money could be recovered. Reflects common law in Baltic Shipping v Dillon. There needs to be TOTAL non-performance.
Damages are only prior to the frustrating event, not post it. You won’t be liable for loss of profits.
You can’t recover for work partly done. Appleby v Myers
What theories support the justification of Frustration?
- Implied Terms theory that there is an implied term in the contract that where the frustrating event occurs, the contract will be at an end - Taylor v Caldwell.
- Construction theory where the contract on it’s true construction, does not apply to the new factual situation. So the facts have changed and the original contract, because of a frustrating event, was not intended to apply to this new factual situation. Codelfa
The Australian Courts prefer this approach.
What doest the Construction theory entail?
The contract is only frustrated if the change of circumstances were such that the obligation was so significantly changed that the ‘thing’ would be, if performed, be different than what was contracted for. - Davis Contractors
Where do you start with frustration?
You start by looking at the terms of the original contract.
The courts will look to see where the risk should/does fall.
Davis Contractors v Fareham
In this case, they said the the contract was not frustrated because the new contract applied to the new circumstances, but was just more expensive. Therefore having a contract that is more expensive won’t be enough.
The facts of Codelfa were almost the same in that all it was, was an event which made the process of completion longer and more expensive, but essentially was the same. However the Courts rejected this. Why?
Codelfa v State Rail Authority of NSW
They said in this case, the contract was frustrated.
Atkin J summarised:
The doctrine is now generally expressed as depending on changes in the significance of the obligations undertaken and the surrounding circumstances in which the contract was made. Both of these had changed in the current case and therefore on it’s true construction, the contract did not apply to the new facts.
Nevertheless, the question to ask is still: whether or not the contract, after the frustrating event, cover the new factual situation?
What is the last theory?
This was adopted by some of the judges in National Carriers.
They said the contract was frustrated where a foundation of the contract was removed so that there was total failure of consideration.
So where the frustrating event means that there’s a total failure of consideration, the contract is frustrated.
What are some frustrating events?
- Impossibility
- Illegality
- Frustration of common purpose of the parties
Frustrating event: Impossibility
This is when a contract is impossible to perform - Taylor v Caldwell
The subject matter of the contract, the music hall, was burnt down. It was said clearly the contract was frustrated because it would be impossible to perform the contract.
When has impossibility as a frustrating event been rejected?
Tsukiroglou v Noblee
Contract for the sale of some nuts.
The Siris Canal was closed. Sellers of the ground nuts had to take ship around South Africa which was twice as expensive.
They argued contract was frustrated because the Canal was closed. They argued it was impossible to perform what was agreed.
HOL rejected this argument. A mere increase in expenses doesn’t mean contract is frustrated. The contract is not impossible to perform, it’s just more expensive.
Can there be temporary impossibility?
It can sometimes be frustrated, but it depends on the duration of the contract.
If it was a contract for 5 years, and it was impossible to perform for 5 months, then it wouldn’t be frustrated.
Jackson v Union Marine
The Eugenia
Charter’s took vessel on a time charter party for a trip to India via the Black Sea.
Crucial fact was there was a war clause forbidding the ship to enter into a dangerous zone without owner’s consent.
Ultimately ship entered Siris canal at a dangerous time.
Ship was trapped in Siris Canal.
On release of the ship, the charterers said the contract was frustrated.
Owner said there had been a breach.
COA held: there had been a breach of the war clause and the contract was not frustrated.
The ship could have gone around the cape of Glutou (or something) and simply because the contract was more onerous, did not frustrate it.
Weight was also placed on the cargo, which was iron and steel. Non perishable on a longer voyage, so it wasn’t time dependent.
What is illegality?
Where the contract is impossible to perform because it is illegal to perform. Fibrosa v Fairbairn.
Fibrosa v Fairbairn
A contract to deliver machinery was entered into with a Polish company.
Before machines were manufacture, Poland was occupied by German army.
Problem was, it was illegal to trade with enemy during war time.
It was physically possible to manufacture machines and deliver them, but was illegal.
Held: Contract frustrated on illegality.