Reduced Inventory / Mode 6 / Outage Flashcards
State the purposes of 40OP-9ZZ16 RCS Drain Operations to include minimum allowed level.
- Places the RCS in a drained condition. Between 10% LPZR [117’] down to minimum level allowed at Mid-Loop [101’ 6”].
- Supports plant activities that require an RCS drain down be performed, with or without fuel in the Vessel.
- Restores the RCS level within the PZR, in preparation for RCS fill and vent.
State the equipment, limits or classification that correspond to the following levels:
- 149’
- 137’ 9”
- 137’ 4”
- 131’ 5”
- 122’ 1”
- < 117’
- < 114’
- < 111’
- < 103’ 4”
- < 103’ 1”
- 101’ 6”
- 149’ PZR Manway
- 137’ 9” (admin pool level for ALARA)
- 137’ 4” (≥ 23’ above vessel flange, LCO 3.9.6 when moving fuel or fuel in vessel)
- 131’ 5” 50% PZR level
- 122’ 1” (≥ 23’ above top of fuel in vessel, LCO 3.9.7 when moving CEAs with fuel in vessel)
- < 117’ Partial Drain (LPZR 10%)
- < 114’ Lowered Inventory / Vessel Flange level
- < 111’ Reduced Inventory
- < 103’ 4” SG tubes drained, not available for DHR
- < 103’ 1” Mid-Loop entered (Top of Hot Leg), SG tubes begin to drain.
- 101’ 6” Minimum Level for Mid-Loop Operations (2” above Hot Leg Centerline)
What level indication is used for Hot and Cold calibrated Lpzr?
What must be done if > 3% deviation is noticed?
- LT-110X/110Y (Hot cal LPZR) and LT-103 (Cold cal LPZR)
- LT-103 and LT-110Y share a common variable leg tap
- 3%: Max indicated level deviation
- Backfill reference legs if levels deviate or are suspect
State the operating characteristics associated with RWLIS NR and WR indications.
Include ranges, when one or both channels are required, power supplies and what is required if loss of CR indications is experienced.
- Both RWLIS NR and WR start at 99’ 7” (bottom of hot leg)
- NR between 99’ 7” – 102’ 11”
- WR > 102’ 11”
- One channel required in Partial Drain
- Two channels required in R/I and M/L
- Indication is automatically compensated for SDC flow (signals from FTs SIA-306 and SIB-307 in SDC lines).
- Inaccurate if SDC flow > 5000 gpm
- Power Supplies
- NNN-D11 (A) / NNN-D12 (B)
- PNA-D25/PNB-D26 powers the flow compensation
- Level deviations require UOM permission prior to continuing drain down
- Loss of MCR indication: 15 minute local monitoring / recording
What can cause the RWLIS local sightglass to become inaccurate?
What about the FTs?
When SDC is running in that loop(due to venturi effect on the sightglass)
When SDC flow is > 5000gpm(unable to compenate for this much flow)
State the SDC limitations that will prevent vortexing associated with the following levels:
- < 107’
- < 104’
- < 103’ 1”
- > 107’
- 103’ 1” to 102’
- 102’ to 101’ 6”
- 101’ 6”
- when ≤ 103’ 8”
- if ≤ 101’ 4”
SDC Limitations (prevent vortexing):
- < 107’ Limited to 1 SDC pump per loop (both trains can be operated)
- < 104’ Limited to 1 SDC pump and loop.
- < 103’ 1” Cannot use CSP for SDC in mid-loop
- > 107’ SDC flow 3780 – 5000 gpm
- 103’ 1” to 102’ SDC flow rate between 3780 - 4600 gpm
-
102’ to 101’ 6” SDC flow rate between 3780 - 4150 gpm
- 3780 gpm is Tech Spec Minimum flow
- < 4000 gpm may allow RCS heat-up when DHR is high
- Low flow alarm (3615 gpm 1 pump / 7400 gpm 2 pumps in a train)
- 101’ 6” Minimum level for LPSI pump suction
- SI piping vented every 2 hours when ≤ 103’ 8”
- Loss of SDC, refer to Lower Mode FR (40EP-9EO11)
- FR directs stopping SDC pumps if ≤ 101’ 4”
State the drain rates associated with the condition of fuel in the vessel.
Drain Rates (fuel in the vessel):
-
40 gpm: level > 111’ and only using the Vessel Head Vent orifice
- Small head vent path will lead to difference in indicated vs actual vessel level (pulls vacuum on head)
-
135 gpm: Grayloc hubs open
- Creates larger head vent path. Actual vs indicated level should track better
What is the precaution associated with drain paths during operations that lower RCS inventory?
Drain Paths:
- Only one drain path at a time can be used to reduce RCS level.
- Letdown to RWT or HUT, alternate drain path using SDC line to the RWT
State the purpose and limitations associated with gravity makeup source.
-
Gravity Make-up source available
- Available during loss of power
- Does not prevent boiling
- Makes up for boil off
- RWT level high enough to ensure head will push water into the RCS. Surge Line flooding can allow head to pressurize.
State the purpose and limitations associated with a pumped/powered RCS makeup source.
- Pumped make-up source available
- HPSI is 1st source
- Will not maintain subcooling if decay heat is > 16 MW (within 87 hours of shutdown)
- HPSI to cold leg path required if cold legs intact (throttling required to prevent runout)
- HPSI to hot leg injection is preferred if RCP is disassembled with pump bowl open OR any cold leg vent path open
What are the other requirements associated with RCS makeup sources when RCS inventory has beed reduced associated with:
vent path
gravity and hpsi injection.
- Hot leg vent path established (PZR manway removed)
- Gravity makeup and HPSI injection must be on opposite equipment trains
State the consequences associated with the surge line configuration at PVGS during a RCS boiling event.
How is this prevented?
- Should boiling occur the possibility exists of escaping steam velocity in the 12” surge line to not allow water to drain back down from the PZR into the RCS.
- Impacts actual vessel level and RWLIS system indication due to increased RCS pressure.
- Minimum level requirements in the RWT such that water elevation will provide sufficient head to overcome internal RCS pressure due to surge line flooding.
What must be done if RCS boiling does occur during a condition where gravity makeup is being used?
- If RVLMS is available and level is below the hot leg, the strategy is to maintain level below the top of the hot leg to provide a vent path to the PZR Manway and prevent any pressure buildup in the RCS.
- If RVLMS is unavailable or level is above the hot leg, SDC Gravity Feed is initiated at a preset level and controlled to conserve RWT inventory, boiling will occur and pressure will build up in the RCS, the RWT will burp into the RCS as the pressure pushes the water level below the hot leg.
What is considered bulk RCS temperature and how is it indicated?
Bulk Temperature
- Actual temperature in the core
- Indicated at the CETs with no RCS flow
- SDC HX inlet temperature with SDC flow
What conditions will affect the amount of decay heat present in the RCS after shutdown?
- Generated from beta/gamma decay of fission products in the core.
- DHR is dependent upon the power level that the core operated at and the length of time at power.
- DHR is highest immediately following shutdown as decay of both long and short lived fission products is occurring.
- DHR drops quickly in the first 20 days following shutdown as the short lived fission products decay away. As the short lived fission products decay away, DHR becomes relatively constant due to the remaining long lived fission products.
What parameters are calculated from the DHR curves in 40OP-9ZZ16?
- DHR curves used to estimate DHR, core heat up rate, time to boil, time to core uncovery in mid-loop and make-up flow rates for a loss of SDC