Quiz 3 Flashcards

1
Q

Which three of the following are main activities done during the Decision Management process?

A

Prepare for decisions.
Analyze the decision information.
Make and manage decisions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which four of the following that are just some of steps under the activity “Define and authorize projects,” within the Portfolio Management process?

A

Establish project scope
Specify the project governance process
Allocate adequate funding and other resources
Identify, assess, and prioritize investment opportunities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which three of the following are Outputs from the Acquisition Process?

A

Acquisition Strategy
Acquisition Agreement
Acquisition Report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A system architecture is formally represented with sets of architectural entities. These entities are many and varied. Which four of the following are possible system architectural entities?

A

physical elements
function flows
links
resource flow items

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which three of the following are some of the Outputs from the Operation process?

A

Operation constraints
Operation strategy
Operation record

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which three of the following are some of the Outputs from the Life Cycle Model Management process?

A

Organizational policies, procedures, and assets
Organizational process performance measures needs
Life cycle model management report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which three of the following are true statements about Environmental Engineering/ Impact Analysis?

A

Disposal analysis is a significant analysis area within environmental impact analysis
The focus of environmental impact analysis is on potential harmful effects of a proposed system’s development, production, utilization, support, and retirement stages.
Failure to comply with environmental protection laws carries penalties and should be addressed in the earliest phases of requirements analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which three of the following are some of the Outputs from the Maintenance process?

A

Maintenance report
Maintenance strategy
Maintenance constraints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Architectural entities may possess many and varied architectural characteristics. Which three of the following are possible architectural characteristics that an architectural entity can possess?

A

dimensions
robustness
execution efficiency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which two of the following are the Inputs into the Configuration Management process?

A

Candidate configuration items (Cls)
Project change requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which three of the following are some of the Inputs into the Supply process?

A

Supply payment
Disposed system
Organization strategic plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which four of the following are some of the Outputs from the Measurement process?

A

Measurement report
Measurement record
Measurement repository
Measurement strategy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which three of the following are some of the basic verification techniques?

A

Inspection
Analogy or similarity
Demonstration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the two approaches to Maintenance?

A

Corrective Maintenance
Preventive Maintenance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which three of the following are some of the outputs from the Stakeholder Needs and Requirements Definition Process?

A

Stakeholder Needs and Requirements Definition strategy
Stakeholder Requirements Traceability
Measures of Effectiveness Data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the four reconfigurable principles from Agile Architectural Design?

A

Self-Organization
Peer-peer interaction
Distributed control and information
Deferred commitment

15
Q

The main objective of reliability engineering is to apply engineering knowledge and specialist techniques to prevent or to reduce the likelihood or frequency of failures. What are the three other objectives of reliability engineering?

A

To identify and correct the causes of failures that do occur, despite the efforts to prevent them
To determine ways of coping with failures that do occur, if their causes have not been corrected
To apply methods for estimating the likely reliability of new designs and for analyzing reliability data

16
Q

What is the purpose of the Integration process?

A

to synthesize a set of system elements into a realized system (product or service) that satisfies system requirements, architecture, and design.

17
Q

Which three of the following are some of the Inputs into the Stakeholder Needs and Requirements Definition?

A

Preliminary Measures of Effectiveness needs & data
Life cycle constraints
Stakeholder needs

18
Q

Which three of the following are some of the Inputs into the Architecture Definition process?

A

Life cycle concepts
System functional interface identification
Design traceability