Quiz 2 Prep Flashcards

1
Q

Which of the following can be used without coordinating with managers of succeeding activities?

A

Free slack

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Jose is forecasting project time and cost for constructing a new building by multiplying the total square footage by a given dollar amount. Which of the following methods is he using?

A

Ratio

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The amount of time an activity can be delayed and yet not delay the project is termed

A

Total slack

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In selecting the best activity to crash you would first select the activity with the

A

Least steep slope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The critical path in a project network is the

A

Longest path through the network

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The process improvement technique that sorts the vital few from the trivial many is:

A

Pareto analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When work packages are integrated with organizational units, a control point is created called a

A

Cost account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which one is top-down estimating method below?

A

(All of the above) Consensus methods, ratio methods, apportion method, function point methods for software system projects, learning curves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which of the following is a good condition for bottom-up estimating?

A

When there is a fixed price contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly