Quantification & Costing Flashcards
What, in your opinion, would constitute a difference in nature to say, installation of a ceiling rose?
Not installing a ceiling rose
An increase in size of the ceiling rose
An increase in the complexity of design or materials being used to create the ceiling rose
What impact would this have on the prelims/programme?
Prelims and programme were both reduced, however, as composite decking requires on site manufacturing and more support/propping there were more labour costs involved, however the savings made due to the complexity of precast were still achievable.
What is the reasoning behind doing the CAT-A fit out first, then structural works? Would structural works not potentially cause damage to the fit out?
The timeframe between phase 1 and phase 2 would be 5-10 years.
Talk me through NRM and differences between 1,2 and 3.
“NRM_1 Order of cost estimating and cost planning
NRM_2 Detailed measurement for building works
NRM_3_Building Maintenance Works”
What is IPMS?
International property measurement standards. Introduced to standardise property measurement across the world. Research has found that measurements have been up to 24% different.
Can you tell me what the difference between NRM 1 and 2 are and how this differs from the RICS Code of Measurement.
RICS code of measurement practice is now obsolete but described the different areas used in property.
NRM is measurement rules for construction and lifecycle costing work.
If I was a developer and told you that I had a site in the middle of London which I wanted to build a residential block on what would you advise me in relation to cost.
I would say this depends on site considerations, the method of construction, the procurement and the design, however most residential projects in London range between £2500 to £3500/M2 GIFA.
GIFA v GEA v NIA
“GEA - Gross external area (IPMS 1)
GIA - Gross internal area (IPMS 2)
NIA - Net internal area (IPMS 3)
Replaced by IPMS from January 2018, RICS professionals are expected to adopt the Property Measurement Professional Statement in place of the Code for offices and Residential unless local laws, or a client require an alternative. Professional Statements for other property classes including industrial and retail will be added over time as the IPMS is expanded.”
How do you quantify internal partitions? Cost Plan. Does this differ from contractor.
Section 2.7 of NRM1. details including thickness to be stated. Measured in m2 on the centre line. No deduction made for openings.
Talk me through how you would measure concrete foundations.
For piles the pile mat would need to be measured in m2. A cost for the piling plant and moving the piling rig would need to be factored in and measured by nr. The pile details would need to include diameter (mm) and depth of piles (m) and measured in nr. The disposal of excavated material would need to be cost and measures in m3. Cutting off tops of the pile would need to be measured by nr.
How do you measure steel. What is the current cost?
Under NRM1 steel needs to be measured in tonnage. The fire protection detail needs to be in the description. The tonnage for each steel member can be found on the structural engineers schedule.
What is the difference between IPMS and code of measurement practice?
IPMS defines GEA, GIA and NIA as IPMS 1, IPMS 2, IPMS3. It is used worldwide not just the UK, and there are slight measurement differences, most notably internal dominant face.
What are the ways of valuing change?
”- Similar nature – use pricing schedule
- Contractors quotes
- Dayworks
- First principle
- Schedule 2 quote”
What is the internal dominant face?
The inside finished surface comprising 50% or more of the surface area for each vertical section forming an internal perimeter.
What is a schedule 2 quotation?
The procedure in Schedule 2 aims to regulate the prices of quotations submitted by the contractor. The contractor’s quotation must cross reference, where relevant, to the rates and prices in the contract bills. Therefore, the contractor cannot simply disregard its tender rates and offer inflated prices when quoting for variations.