Contract Practice Flashcards
What does CDM stand for?
Construction Design Management
What is a QS defined as under CDM Regulations?
A designer
What is a Parent Company Guarantee?
A PCG is a guarantee given by one contracting party’s ultimate or intermediate holding company in favour of the other contracting party to secure and underwrite the performance of that party’s obligations under the contract.
What are the 5 types of bond?
Performance bond
Retention bond
Off-site materials bond
Advance payment bond
Tender bond
What is a performance bond?
A performance bond is a form of security provided by a contractor to a developer or employer.
It consists of an undertaking by a bank or insurance company to make a payment to the employer in circumstances where the contractor has defaulted under the contract.
What bond type would you recommend to your client?
PCG if available
Why would you recommend a PCG?
A performance bond is a finite sum of money where the damages claimed may be higher than the sum. A PCG is not limited.
What are Third Party Rights?
The third Party rights act 1999
The act allows third parties to enforce terms of contracts that they are not party to, but which benefits them in some way, or which the contract allows them to enforce.
What is a collateral warranty?
Forms a contractual link between two parites where one would no usually be present.
When is a collateral warranty used?
Employer —> Main Contractor –> sub-contractor
^
—
> Sub-contractor
What is the difference in co-operation principles between the two? (JCT & NEC)
NEC is considered a more collaborative approach to working. Parties are required to work in the spirit of “mutual trust and co-operation”
What happens if you don’t issue a completion/non-completion certificate?
Time is at large – LDs are unenforceable.
What is required to issue a completion certificate?
- PC is a term under the JCT form of contract. This is the point at which the contractor has completed the project and hands over to the client.
- Its is called “practical completion” because it is fit for purpose. The project is sufficiently complete for the employer to take over in that nothing remains outstanding that prevents the employer from using the works, although there may be some outstanding works or defects which remain to be completed.
- Works are so substantially complete that the building can be put to its intended use with safety and convenience.
NOTE - It is common practice for PC to be granted when the works are substantially complete – i.e. there may be minor defects or omissions BUT nothing that would prevent the employer taking occupation.
NOTE - The PC certificate cannot be rescinded once issued
ONCE ISSUED
a. 50% retention is released (subject to the contract)
b. The 12-month defect period starts
c. The client needs to start insuring and securing the building
d. The ability to impose LDs is ceased.
What is the process for issuing a non-completion certificate?
- Issued by the CA/EA to certify that the works/section has not been completed by the contractual completion date.
- The employer has the right to withhold liquidated damages (a pay less notice is also required)
- Certificate of non-completion is required
- Employer must write to the contractor notifying them of the intent to withhold LDs
- Employer to issue pay less notice.
What is time at large?
The need for comprehensive EOT provisions in construction contracts was illustrated by early case law, e.g. Holme v Guppy (1838) – ‘an act of prevention’ (handing over the site late) in the absence of an EOT clause, results in time becoming ‘at large’. With time at large, the liquidated damages provisions are unenforceable.
What is meant by the term “Prevention Principle”
Prevention Principle – one party may not enforce a contractual obligation against the other party where it has prevented the other party from performing that obligation. If a contract contains a specified completion date but no EoT provisions, the prevention principle prevents the Employer from enforcing the date for completion where it has caused the delay (e.g. issuing an instruction). If this occurs, time becomes at large; and the original completion date falls away, and any LADs regime falls away and the contractor will only be obliged to complete within a ‘reasonable time’.
What happens once PC is achieved?
Half of retention is released
12-month defects period starts
Client needs to start insuring and securing the building
The ability to deduct LDs is ceased
What is required for Final account?
Certificate of Making Good defects
Certificate of Practical Completion
Final account Statement
How was this contract executed?
As a deed
In what capacity did you issue the Practical Completion Certificate?
Which contract, were you CA? Engineer?
As contract administrator on a minor works contract
What is the contractor required to do to achieve Practical Completion?
Works are to be substantially completed so that the building can be put to its intended use with safety and convenience.
What is Assignment?
Transferring
What if the client tells you the LADs are you be £100,000 per week?
- I would check that the LAD figure is based on a genuine pre-estimate of financial loss and explain that in the event LADs are to be applied, they would need to substantiate this figure.
- I would also explain that if the figure inserted into the contract is shown to be punitive and not based on genuine financial loss it is not likely to be enforceable.
- In this scenario the employer will have to pursue the Main Contractor for any actual direct loss that can be substantiated through a formal dispute resolution procedure.
What are extensions of time?
Extensions of time adjust the completion date and relieves the contractors liability to pay liquidated damages for the period of the extension.
What is the importance of a relevant event?
A relevant event is one that impacts the programme of the works by the MC. For example a variation or instructions, or deferment of possession of the site.
What impact could a relevant event have on the price of a project?
A delay to the works and therefore an extension of time could be granted.