Procurement & Tendering Flashcards
Tell me the difference between Management Contracting and Construction Management.
Management contracts – where the management contractor undertakes to manage the carrying out of the work through works contractors, who are contractually accountable to him.
Construction Management – where the construction manager undertakes to manage the carrying out of the work through trade contractors but the client is involved in the directing of the project, and the contracts with the trade contractors are directly with him
What would be an appropriate route if time was the driving factor of the client?
Negotiation
What do you consider to be the key documents to be issued during the tender process?
Contract documents
Employers Requirements
Why did you recommend a Minor Works Contract?
I recommended a Minor works Contract as the strip out works were simple in character, there was minimal design for the contractor, the drawings for the strip out were well defined and presented. There was unlikely to be any unforeseen site constraints or discoverables. It was a relatively small strip out of a vacant building.
Why not D&B or Intermediate?
D&B – no design for contractor – more risk – employer experienced.
Intermediate – advance payment not required – no testing or opening up required – does not meet recommended value for using a IC
Why would using a Minor Works contract attract more tenderers
Reduced risk on contractors side
Possession of the site remains with the employer – less cost and complication on contractors side for insurance/security etc
Where is the advice in this statement?
Once I had produced my report and analysed all the tender returns, I informed the client that the prices provided by the steel window contractors were exceptionally high and that I would advise reducing the scope, complexity and quantity of the steel windows/doors to the design team as a VE option to be progressed. This would reduce the overall cost of the steel windows and doors package.
On 4more london - how did you come to a preferred tenderer? How did you go about informing tenderers?
What was the process you took to make sure all tenders were equal?
Sideby side comparison which included normalising the tenders to exclude any abnormalaities or include costs where a contractor had not included for an item.
What would have been the negatives of procuring the enabling works early on 71 hopton?
What was in your ITT for 4more?
What is procurement?
The overall process of acquiring construction work or services.
What should be considered when selecting a procurement route?
- the specifics of the project
- the client objectives regarding:
- Cost
- Time
- Control
- Quality
- Risk
What are the main procurement methods?
- Traditional and General Contracting
- Design and Build
- Management Contracting
- Construction Management
What is traditional procurement?
The design is completed by the clients design team before competitive tenders are invited and a main contractor is employed to build what the designers have specified.