Quantification and Costing of Construction works Flashcards
What are the primary purposes of a BoQs?
To provide a coordinated list of items with their descriptions and quantities, that comprise the works, which in turn enables contractors to prepare tenders efficiently, and accurately.
BoQs provide a basis for the valuation of executed works for the purpose of making interim payments to contractors
BoQs provide also basis for the valuation of varied works.
Who must quantify the extent of works to be executed ?
The extent of works to be executed can be quantified either by Employer’s QS/Cost manager or the main contractor or the work package contractor.
What are the benefits of preparing detailed measurement for the purpose of bill of quantities ?
- It saves time of several contractors measuring the same design in order to calculate their bids.
- It provides a consistent basis for obtaining competitive bids.
- It provides an extensive and clear statement of the works to be executed
- It provides a a very strong basis for budgetary control and accurate cost reporting of the contract such as post contract cost control, including:
a) preparation of cash flow forecasts
b) basis of valuing variations
c) basis for the preparation of interim payments. - It provides data to support claims for tax benefits (e.g. capital allowances, value added tax).
What are the types of BoQs ?
1) Firm BoQ - Prepared when design is complete based on completed detailed design. Firm BoQ allows obtaining a lump-sum price for a fully designed project.
2) Approximate - Used on projects where it is not possible to prepare a firm BoQ at the time of tender. Approximate BoQ is subject to a remeasurement as built.
3) Elemental - Prepared using the elements of a building as sections i.e. wall elevations, structural frame, roof structure etc.
Who prepares each type of BoQ?
1) Firm and approximate BoQ - These types of BoQ for a lump sum contract is normally prepared by Employer’s QS, whereas under D&B the Employer’s team will prepare ‘employer’s requirements’ and BQ or quantified schedules of works will be prepared by by either the main contractor or main contractor’s work package contractor.
2) Elemental BoQ - This type of BoQ suits the Employer’s Qs as means of checking cost plan and preparing a cost analysis but it may not suit a contractor from a programme planning perspective.
What section BoQ comprises of ?
Form of Tender (document used to record the main contractor’s price for completing the building project), including certificate of Bona Fide tender.
Main Summary
Preliminaries (Information and Requirements and Pricing schedule)
Measured Works
Risks
PS
Credits for materials arising from the works
Daywork Provisional
Annexes
What are preliminaries ?
Preliminaries consist of items NOT directly related to the measured works, such as:
- Management of the building project
- Site establishment
- Security
- Safety
- Environmental protection
- Mechanical plant
- Employer’s completion and post-completion requirements
What two main sections do Preliminaries consist of?
Information & Requirement and Pricing Schedule
Explain the purpose of Information & Requirement
The purpose of I&R section is to describe the building project particulars:
The drawings upon which BoQ was based
The work in general
The site and any adjoining properties
The form of contract
Employer’s specific requirements
Any specific limitations or restriction that may impact on the sequence or method of working
Including any special methods of measurement when it’s deviated from NRM2
What is pricing schedule ?
Pricing schedule is simply a schedule in which the contractor inserts preliminary costs relating to the employer’s requirements and all contractors’ cost items (including management and staff, site accommodation, services and facilities, mechanical plant and temporary works items.
What is the main part of the BoQ ?
Measured works, which list all items of work to be undertaken. The quantities and description of items should be determined in accordance with a set of tabulated rules of measurement.
What is contingency ?
A residual risk, which is possible but can not be predicted with a certainty, which the Employer wishes to transfer to the contractor. The contractor is required to provide a lump-sum fixed price for taking, managing and dealing
with the consequences of the identified risk should it materialise.
What are provisional Sums ?
Provisional sums are sums included for any items of work that are anticipated, but for which no firm design
has been developed, including any sums listed for any items of work that are to be executed by a statutory
undertaker.
What are defined provisional sums
Defined provisional sums are those which have been described in sufficient detail that the contractor is expected to have made allowance for them in their programming, planning and pricing preliminaries.
An example might be where a defined amount of brickwork is required, but the exact design has not be finalised and so the price cannot be accurately determined. Or the cost of installing a timber frame where the specific type of timber has not yet been specified and so its price is not known.
What are undefined provisional sums
Undefined provisional sums are less well described as they refer to work which is not completely designed. As such, the contractor cannot be expected to make allowance for them in their programming, planning and pricing preliminaries. This means the contractor may be entitled to an extension of time and/or additional payments when the actual works are undertaken.
An example of an undefined provisional sum might be work required below an existing structure, where the ground conditions, and so the extent of work required, cannot be determined until the structure is demolished and the ground opened up.
What are Credits for materials arising from the works ?
This section of the BQ comprises a list of materials arising from the works for which the employer requires
the contractor to offer a credit.
What are dayworks provisional?
This section of the BQ gives provision for the contractor to competitively tender rates and prices for works,
which might be instructed to be carried out on a daywork basis.
What are Annexes ?
The annexes comprise information referred to in the BQ where it is not contained in, or to be issued as, a
separate document. Examples are: performance specifications (if not included in project specification);
copies of quotations; and copies of communications with statutory undertakers
What information are required for measurement ?
Specification (Prescriptive and performance)
Drawings GA drawings comprising of component drawings, schematic drawings, drawing register of existing building.
Schedules
Reports and other information
What is Works Breakdown Structure (WBS) ?
A tree structure to which can be used to define and divide a building projects into key aspects. It is developed by starting with the end objective (i.e. WBS Level 0 - the entire building project) and successively subdividing it into the main components and sub-components that
make up the entire building project
What is cost breakdown structure ?
CBS is initiated by WBS and is used to allocate cost to each aspect/facet of the building at each level of WBS.
What are prescriptive specifications ?
Prescriptive specifications are written documents that give details about the project’s materials and instructions for their installation. Architects and engineers usually determine prescriptive specifications. Therefore, they are responsible for the proper installation of materials, not the contractor.
What are performance specifications ?
Performance (open) specifications describe the result that is required from particular items and leave it to the contractor or supplier to satisfy that requirement. In effect it requires the contractor or supplier to complete the design.
How dimensions should be measured ?
Dimensions should be measured to the nearest 10mm. 5mm and over shall be regarded as 10mm and less
than 5mm shall be disregarded.
How quantities less than one unit should be given ?
Quantities less than one unit should be given as one unit. Quantities measured in tonnes (t) shall be given to
two decimal places.