Project Finance (Control and Reporting) SAVE Flashcards
What does Post Contract Cost Control cover ?
Post contract cost control covers all financial matters post award of a construction contract in administering a construction budget.
What does it include for QS ?
For a QS this typically includes preparing interim valuations, change management, preparing cost reports and cash flow forecasts, final accounts etc.
What measure QS can take during the post contract cost to effectively control cost during construction ?
Implement a robust change change control process
Proactive risk and contingency management
Management of provisional sums within budget
Regular cost reporting, including cost to complete forecast
Rolling final account & closure process for impact of change
How would you report forecasted cost throughout the life of a project ?
By producing monthly cost reports
Why is change control required and what it means ?
To provide a method of assessing and managing change by estimating consequent cost, programme and scope effect
To advise the client of the consequences of a potential change and the effect this will have on the project so the client can make an informed decision
What legal and contractual constraints may influence project cost ?
Legislation e.g. planning and building regulations
Design risk allocation e.g. design change required
Cost risk allocation e.g. incorrect cost plan
Delays
Faulty materials
When the contract sum can be amended ?
through:
1) Instructed variations to cover scope changes, non-scope change variations, expenditure of provisional sums
2) Extension of time -
3) Claims
4) Penalties
5) Liquidated Damages
What issues would you consider in advising the client on change control strategies/procedures ?
Client’s objectives: is it cost or quality or perhaps time ?
Who will be authorizing the change on behalf of the client ?
Who will raise initial change request ? Would it always be through contract administrator ?
Confirmation from client/project manager of what costs need to be included within the change, e.g. just the construction costs or also the professional fees if applicable ?
How will the change control procedure link with contract instructions and contract procedures (e.g. RFIs) during the construction process ?
How would you implement the change control procedure ?
Communicate the procedure with the rest of the project team
Report
flow chart
project execution plan
Issue proformas of Change Proposal / Change Request Form
Arrange regular Change Control meetings
Maintain Change Control Log
Ensure that a proper and timely change control procedure is followed
What information will you include in a Change Control form ?
Description of a proposed change
Cost implication
Any risks attached to the change
Programme implications
supporting documents e.g. drawings
What is the aim of cost reporting ?
The aim of the cost reporting is to provide the client with with a prediction of the anticipated final account.
Why financial reporting and control procedures are important ?
To monitor actual cost against and budget to assist in commercial administration and have formal records.
What is the purpose of cashflow in financial management ?
It projects forecast for client’s budget
It is programme management tool
What a valuation / Final Account is likely to consist of ?
Preliminaries
Properly executed measured works
Contractor Design Portion
Materials on / off site
Prime cost sum and provisional sums
Variations / Claims
Advanced payment & recovery
Retention
Other deductions / credits
fluctuations
Milestone / Stage payments
What are preliminaries ?
Items which are not directed related to any component, element or work section. These can include management and staff, site establishment, temporary services, security, site services, insurance, bonds, guarantees.
How would you claim preliminaries in an interim valuations ?
It depends on the contract conditions. It can be based on the percentage of measured works completed
Could be cost related, time-related, fixed price single payment or combination of two or more.
Would you pay for materials of site ?
Depending if the contract allows for it, if it doesn’t then no.
If contract allows for it then I would check if all the contract requirements are met for such a payment to be issued. For example is the materials’ ownership vested in the Employer.
Also I would check if materials are properly:
stored
protected
insured
clearly labelled
I would follow the valuation rules, which may allow for payment of only 70% of the invoice for the materials off site.
What is retention ?
It’s a sum generally deducted at each valuation to provide client with some security that the contractor will return to correct any defects during defects liability period.
If the contractor doesn’t come back to rectify any defects the retention money can be used to fund the rectification carried out by a different contractor.
When is the retention released ?
Depends on the contract conditions, usually 50% is released upon completion of the works. The remaining 50% is released when the defects liability period has expired.
The release of retention is different if there is sectional completion, partial possession or the like under the contract.
Are there alternatives to retention ?
Yes, there is retention bond, retention guaranties to
What is Prime Cost sum ?
There are normally linked to the nominated in the contract subcontractor or supplier and any sums paid by the contractor to the nominated subcontractors/suppliers are called prime costs. It requires authorized instructions to expend the PC sums.
What are provisional Sums ?
Sums included in the tender/contract for work, which cannot be entirely foreseen at the time of tendering. It requires authorized instructions to expend the provisional sums.
How would you check daywork ?
Daywork is the work in question which cannot be properly measured. So first ensure it cannot be measured and it doesn’t overlap with measured work.
Method of valuation will be based on the prime cost if labour , materials and plant + O/P
Ensure the time claimed tallies with the timesheets signed by the authorized signatories as per the contract e.g. site supervisor
Check the plant was used solely for the daywork as claimed.
How can fluctuation be implemented ?
Based on the formula mentioned in the contract to adjust for inflation
Based on basic list of materials / labour costs or published indices.