Project Finance (Control and Reporting) SAVE Flashcards

1
Q

What does Post Contract Cost Control cover ?

A

Post contract cost control covers all financial matters post award of a construction contract in administering a construction budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does it include for QS ?

A

For a QS this typically includes preparing interim valuations, change management, preparing cost reports and cash flow forecasts, final accounts etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What measure QS can take during the post contract cost to effectively control cost during construction ?

A

Implement a robust change change control process
Proactive risk and contingency management
Management of provisional sums within budget
Regular cost reporting, including cost to complete forecast
Rolling final account & closure process for impact of change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How would you report forecasted cost throughout the life of a project ?

A

By producing monthly cost reports

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why is change control required and what it means ?

A

To provide a method of assessing and managing change by estimating consequent cost, programme and scope effect
To advise the client of the consequences of a potential change and the effect this will have on the project so the client can make an informed decision

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What legal and contractual constraints may influence project cost ?

A

Legislation e.g. planning and building regulations
Design risk allocation e.g. design change required
Cost risk allocation e.g. incorrect cost plan
Delays
Faulty materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When the contract sum can be amended ?

A

through:
1) Instructed variations to cover scope changes, non-scope change variations, expenditure of provisional sums
2) Extension of time -
3) Claims
4) Penalties
5) Liquidated Damages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What issues would you consider in advising the client on change control strategies/procedures ?

A

Client’s objectives: is it cost or quality or perhaps time ?
Who will be authorizing the change on behalf of the client ?
Who will raise initial change request ? Would it always be through contract administrator ?
Confirmation from client/project manager of what costs need to be included within the change, e.g. just the construction costs or also the professional fees if applicable ?
How will the change control procedure link with contract instructions and contract procedures (e.g. RFIs) during the construction process ?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How would you implement the change control procedure ?

A

Communicate the procedure with the rest of the project team
Report
flow chart
project execution plan
Issue proformas of Change Proposal / Change Request Form
Arrange regular Change Control meetings
Maintain Change Control Log
Ensure that a proper and timely change control procedure is followed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What information will you include in a Change Control form ?

A

Description of a proposed change
Cost implication
Any risks attached to the change
Programme implications
supporting documents e.g. drawings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the aim of cost reporting ?

A

The aim of the cost reporting is to provide the client with with a prediction of the anticipated final account.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Why financial reporting and control procedures are important ?

A

To monitor actual cost against and budget to assist in commercial administration and have formal records.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the purpose of cashflow in financial management ?

A

It projects forecast for client’s budget
It is programme management tool

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What a valuation / Final Account is likely to consist of ?

A

Preliminaries
Properly executed measured works
Contractor Design Portion
Materials on / off site
Prime cost sum and provisional sums
Variations / Claims
Advanced payment & recovery
Retention
Other deductions / credits
fluctuations
Milestone / Stage payments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are preliminaries ?

A

Items which are not directed related to any component, element or work section. These can include management and staff, site establishment, temporary services, security, site services, insurance, bonds, guarantees.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How would you claim preliminaries in an interim valuations ?

A

It depends on the contract conditions. It can be based on the percentage of measured works completed
Could be cost related, time-related, fixed price single payment or combination of two or more.

17
Q

Would you pay for materials of site ?

A

Depending if the contract allows for it, if it doesn’t then no.
If contract allows for it then I would check if all the contract requirements are met for such a payment to be issued. For example is the materials’ ownership vested in the Employer.
Also I would check if materials are properly:
stored
protected
insured
clearly labelled
I would follow the valuation rules, which may allow for payment of only 70% of the invoice for the materials off site.

18
Q

What is retention ?

A

It’s a sum generally deducted at each valuation to provide client with some security that the contractor will return to correct any defects during defects liability period.
If the contractor doesn’t come back to rectify any defects the retention money can be used to fund the rectification carried out by a different contractor.

19
Q

When is the retention released ?

A

Depends on the contract conditions, usually 50% is released upon completion of the works. The remaining 50% is released when the defects liability period has expired.
The release of retention is different if there is sectional completion, partial possession or the like under the contract.

20
Q

Are there alternatives to retention ?

A

Yes, there is retention bond, retention guaranties to

21
Q

What is Prime Cost sum ?

A

There are normally linked to the nominated in the contract subcontractor or supplier and any sums paid by the contractor to the nominated subcontractors/suppliers are called prime costs. It requires authorized instructions to expend the PC sums.

22
Q

What are provisional Sums ?

A

Sums included in the tender/contract for work, which cannot be entirely foreseen at the time of tendering. It requires authorized instructions to expend the provisional sums.

23
Q

How would you check daywork ?

A

Daywork is the work in question which cannot be properly measured. So first ensure it cannot be measured and it doesn’t overlap with measured work.
Method of valuation will be based on the prime cost if labour , materials and plant + O/P
Ensure the time claimed tallies with the timesheets signed by the authorized signatories as per the contract e.g. site supervisor
Check the plant was used solely for the daywork as claimed.

24
Q

How can fluctuation be implemented ?

A

Based on the formula mentioned in the contract to adjust for inflation
Based on basic list of materials / labour costs or published indices.

25
Q

What is loss and expense claim ?

A

It deals with the reimbursement of Contractor’s direct loss and / or expenses typically due to delays or disruption resulting from design changes, late instructions etc.

26
Q

What is delay ?

A

It’s lateness. It’s happens when the critical path of the project has been impacted and therefore is delayed. Sometimes delay may happen to activities on non-critical path, in this case the contractor is not entitled to claim for time only.

26
Q

What is disruption ?

A

It’s loss of productivity

27
Q

Will the delay to a project caused by the employer always result in loss to the contractor ?

A

No, simply because the contractor has been given extension of time does not always mean that the contractor is entitled to additional payment as well.

28
Q

Is it claim for delay if the contractor incurs losses due to the progress of their work being made less efficient as a result of employers actions ?

A

No, the contractor will have a claim for disruption in this case.

29
Q

Can the profit be included in the L&E claim.

A

No, the L&E claim is for direct loss and expenses.
The profit may be recoverable under loss of profit claim however the contractor must proof that if there was no delay they could have commenced another project on their list to which they would have allocated all resources and would have earned the profit which is now lost.

30
Q

What are the four categories of risk mentioned in NRM for Estimating and Cost Planning ?

A

Design development risks
Construction risks
Employer change risks
Employer other risks

31
Q

How risk can be expressed at the early stages ?

A

It can be expressed as a percentage of the construction total.

32
Q

How risk can be identified ?

A

It can be identified by running risk register.

33
Q

How risk can be evaluated ?

A

It can be evaluated by:

Qualitative evaluation - probability and impact - High, Medium, Low
Risk Ranking - which is evaluated by multiplying probability and impact

34
Q

What is contingency ?

A

It’s a sum of money kept in case the risk materialized.

35
Q

What is value management ?

A

Value management is a team-based approach used to define the client’s objectives and ensure best value, whole-life solutions are selected to satisfy those objectives. It is not necessarily about cost cutting. The process of value management includes value engineering.

36
Q

What is value engineering ?

A

Value engineering is used to solve problems and identify and eliminate unwanted costs, while improving function and quality.

37
Q

What headings would cost report include ?

A

The cost report heading’s will include variations and potential future variations, claims (L&E) the adjustment of provisional or PC sums and any other costs which may impact the final account.

38
Q
A