Quantification and Costing Flashcards
1). What is GEA?
– Gross External Area
– This is the area of the building measured externally to outside face of the external wall at each floor level.
1a). What would be included in GEA?
– Thickness of external Wall – Plant Rooms – Lift Shaft and stair Core Voids at each level – Atria (Measured at base level only) – Internal Walls and Columns – Adjoining out buildings
2). What is IPMS 2 / GIA?
– Gros Internal Area
– The area of the building measured to the perimeter of the inside of the external wall, and includes loading bays.
– Includes balconies (but should be stated separately)
– This excludes open sided balconies, fire escapes, canopies, external walls, large voids.
3). What is IPMS 3 / NIA?
– Net Internal Area
– This is the area of usable / lettable space measured to the internal face of the perimeter of the external wall at each level.
– Includes balconies (but should be stated separately
– Excludes external voids, internal structural walls & columns, spaces with headroom less that 1.5m, circulation space in common area, permanent lift lobbies, toilets, cleaners cupboards, plant rooms.
4). Where are all these defined?
CoMP (Code of Measurement Practice) and IPMS (International Property Measurement Standards)
– IPMS 1 : Exterior / GEA (Also includes balconies, but stated separately)
– IPMS 2 : Interior / GIA (Also includes balconies, but stated separately)
– IPMS 3 : Occupancy / NIA (But includes internal walls and columns within an occupant’s exclusive area, balconies must allows be stated)
5). What is the purpose of the International Property Measurement Standard?
– Provides precise definitions to permit the accurate and consistent measurement of buildings
– IPMS will bring greater confidence and consistency in the global property market and allows greater transparency.
– Offers a globally recognised standard for measurement.
6). What are the main elements of an Elemental estimate?
- Demolition & Enabling
- Sub–Structure
- Super Structure
- Finishes
- FF&E
- Services
- External Works
7). What do you measure in accordance with, when cost planning?
NRM1 (New Rules of Measurement 1)
8). What do you measure in accordance with, when creating a BoQ?
NRM2 (New Rules of Measurement 2)
9). What does NRM do?
– Provides an elemental approach which identifies the unit to which the works are measured and the requirements for measuring the works.
10). How would you carry out measurement for a BoQ?
– I would follow the guidance set out in NRM2 – Following this guidance I would start by doing a take off of the available design information, working through elementally.
– Once I had completed the take off I would carry out a working up of the quantities into a BoQ.
– The key to a good BoQ is to as clear as possible with the notes and assumptions at the time of the measurement.
– This will leave a trail of information for reviewing the BoQ.
11). How would you measure RC Insitu concrete?
– Depends on the element (column, structural wall, upper floor, pile caps etc.)
– But would if it was a column I would start by measuring the dimensions of the column, Width, Height, Length.
– This would then allow me to calculate the cubic meters of concrete required.
– The dimensions would also allow me to calculate the square meters of formwork required.
– Then using the structural information I would be able to calculate the reinforcement required using tonnage per cubic meter.
12). How would you carry out a measurement for a Cost Plan?
– I would follow the guidance in the NRM 1.
– Following this guidance I would measure the available design information in an elemental format.
– Depending on the available information this would either be as items, quantities, or provisional allowances.
13). What is a provisional sum?
– An allowance for a specific element of the works that is not yet defined in enough detail for accurate measurement / pricing.
– These can be defined and undefined.
14). What are defined and undefined provisional sums?
–Defined provisional sums are considered to have been accounted for within the contractor’s price and programme.
– In effect the contractor is taking the risk that their estimate will be sufficient.
– Undefined provisional sums are not accounted for in the contractor’s price and programme.
– This means that the client is taking the risk for the works and the contractor may be entitled to an extension of time and additional payments.