Procurement & Tendering Flashcards
1). What is procurement?
– The overall process of acquiring construction work or services
2). What should be considered when selecting a procurement route?
– The specifics of the project – The key client objectives regarding: Cost, Time, Control, Quality, and Risk
3). What are the main procurement methods?
– Traditional – Design & Build – Management Contracting – Construction Management
What is traditional procurement?
– The design is completed by the client’s design team before competitive tenders are invited and a main contractor is employed to build what the designers have specified.
4). How does traditional procurement work?
– The contractor takes on the responsibility and financial risk for the construction of the works to the design produced by the client’s design team for the contract sum within the contract period. – The client takes the responsibility and risk for the design and the design team performance.
5). When might it be appropriate to consider a traditional route?
– If the employer has already had the design fully prepared. – If the design is substantially completed at time of contractor selection. – The client wishes to retain control over the design and specification – Cost certainty at start on site point is important to the client. – The shortest overall programme is not the client main priority.
6). What contracts might be used for traditional procurement?
– JCT: Minor Works – JCT: Intermediate – JCT: Standard Building Contract with Bill of Quantities
7). What are the advantages of traditional procurement?
– Quality Control; Design led so can ensure the design is up to the client’s expectations before tender. – Cost Certainty; as design already complete gives a much better position for cost certainty. – Well known procedure / most simplistic procurement route. – Suitable for clients with limited construction experience. – Offers a transparent process as all tenderers pricing the same design and spec. – Offers competitive fairness due to the transparent process (pricing same design information). – Changes are relatively easy to arrange and value (known starting point).
8). What are the disadvantages of traditional procurement?
– Time; overall project duration may be longer than other routes – sequential process – Buildability; No input into design and planning by contractor – Strategy based on price competition – could lead to adversarial relations – Dual point of responsibility; client & design team for the design and contractor for the construction. – If design is not complete at time of tender then cost and time certainty is significantly reduced.
9). What is design & build?
– This is where the contractor is responsible for the design, planning, organisation, control and construction of the works to the employer’s requirements.
10). How does a design & build route work?
– The employer gives the tenderers the Employer’s Requirements, and the contractors respond with the Contractor’s Proposals, this will often include the price for the works.
11). When might it be appropriate to consider a D&B route?
– Programme; when there is a need to start on site as soon as possible (overlap design & construction) – Risk; if the client wants to minimise their risk – transfer of design risk to the contractor. – Technically complex projects – will get the benefit of buildability advice from the contractor. – Where the client does not wish to retain control over the design development.
12). What contracts might be suitable for a D&B route?
– JCT Design and Build 2011 – JCT Design & Build 2016
13). What are the advantages of a D&B procurement route?
– Programme; allows earlier start on site as you can overlap design & construction. – Risk; Single point of responsibility, the contractor is responsible for the design and the construction. – Buildability; Benefit of early contractor engagement and advice around buildability, logistics, site management etc. – Cost Certainty; Single stage lump sum design and build can give early point of cost certainty (potentially after Stage 2).
14). What are the disadvantages of a D&B route?
– Quality Control ; detailed design will be carried out by the main contractor not the client’s design team. – Client Brief Requires a sufficiently comprehensive brief to ensure the Employer’s Requirements match client expectations. – Client will have to commit to a concept design earlier in the process. – Change; Variations from the original brief are often hard to arrange and often expensive. – Harder to compare tenders – harder to normalise and determine if you’re getting value for money. – Ease of fabrication / construction may be prioritised over aesthetic quality. – Reduced competition as there are less companies capable of delivering under design & build.
15). How much of the design input will the contractor have?
– This will depend on how much design information is available at the point of tender. – This can range from Stage 2 (concept design), Stage 3 (developed design / partially coordinated), Stage 4 (Technical Design, fully coordinated and specified). – Even if the design is well developed the contractor will still be taking on the risk and responsibility for the design.
16). Who carries out the design for the contractor?
– This will be covered in the Employer’s Requirements or the Contractors Proposals. – The contractor will always retain responsibility of the design under D&B though. – This can be in the form of: > Outsourcing the design > Novating / the main contractor retaining the Client’s Design Team (transfer of rights and obligations) > Using in–house design team
17). What is novation?
– A new contract that transfers the rights and obligations of one contractual party to a new third party. – In this case it would be the design rights and obligations of the architect transferred to the contactor.
18). If the design team is novated, what should the client put in place?
– A collateral warranty between the client and the design team to give them remedies for breach of contract. – This is because once rights and obligation shave been transferred under novation, the client no longer has a contractual relationship with designer. – This gives the employer (now a 3rd party to the Contractor & Designer contract) the right to enforce contract terms.
19). What is management contracting?
– A management contractor is employed to contribute their expertise to the design and to manage the construction on site, and is paid a fee to do so.
20). How does management contracting work?
– The management contractor has direct links with all the works contractors. – The have the responsibility for the construction of the works without actually carrying them out. – Not all the design needs to have been completed before the first works contractors start on site. – The MC selects the works contractors through competitive open book tenders. – The client reimburses the cost of these packages to the MC plus their fee. – The MC’s role is low risk – get prime cost plus a fee.
21). When might it be appropriate?
– Time; when an early start on site is a priority – Cost Certainty; when cost certainty is not a top priority for the client. – Quality; when the client wants to retain control of the design. – Risk; if the client is not concerned with carrying design risk.
22). What contract might be used?
– JCT Management Contract 2011, 2016
23). What are the advantages of Management Contracting?
– Time; can reduce overall project duration as can overlap design and construction. – Buildability; Early contribution on design from the contractor around buildability, logistics, etc. – Changes; can be accommodated in packages not let yet (as long as they do not have an impact on other aspects). – Competition; The works packages are let competitively at current market prices on a firm basis.