Design Economics and Cost Planning Flashcards
What types of estimate are there?
Budget / feasibility
Cost estimate
Cost plan
What is a feasibility estimate?
A high level exercise to assess whether a project is financially viable and to set an outline budget for the scheme
What is the format of a feasibility / budget estimate?
Rate per m2 or per functional unit
May be presented as a range
What is a functional unit?
The ‘factors which express the intended use of the building better than any other’
E.g. number of bedrooms in a hotel, number of beds in a hospital
What information do you need to be able to carry out a feasibility estimate?
Type of building (function) New build or extension Location Size Indication of quality Site visit
What is the % error on a feasibility estimate?
10%
What is a cost estimate?
A forecast of the possible cost of a building based on historical data
When would you do one?
Stage C/D
What are the principal components of a cost estimate?
Construction cost Preliminaries Contractor’s OH&P Contingency Inflation Assumptions – programme Exclusions Area Schedule Basis of Estimate – drawings / specifications list
Name the main elements of an elemental estimate
Substructure – excavation and substructure
Superstructure – frame, upper floors, external walls, roof, internal finishes
Services
External works
What is usually excluded from a cost estimate?
Professional fees VAT Client decant costs Loose fixtures and fittings Inflation Site acquisition costs Section 106s Removal of asbestos
Why is VAT excluded?
Because different clients will incur different levels of VAT, and might not be applicable.
We would not be in a position to know the correct rate unless informed of it
What is the % error on a cost plan?
5%
What is contingency?
A sum included in the estimate to cover unknown expenses or unmitigated risks during the project
How is contingency assessed?
The amount included should reflect the risks and unknowns specific to the project.
During early estimates when little information is available it is common to include a %
At the end of stage C it is usually 10%
This should reduce as more information becomes available and the unknowns decrease
At the end of Stage E it is usually 5% (2.5% design and 2.5% construction contingency)
It is common to have a higher % for refurbishment work due to the higher level of unknowns and therefore risks
What are preliminaries?
They define the scope of works
Include the project particulars, lists of drawings, desciprtion of the site, scope of work, details of management arrangements
Often contain items for pricing which are general items needed by the contractor to carry out the work that cannot be attributed to specific items of work
Where do you find the guidelines to prepare preliminaries?
NRM2 (used to be SMM7)
Name some preliminaries sections
NB This is SMM7 and needs revision *****
A10 – project particulars
A54 – provisional sums
What should be considered when assessing preliminaries levels?
Length of contract
Location – accessibility, space restrictions, accommodation possibilities etc
Type of project – new build / refurb, tower / one story etc
Size of project
Need for temporary works
Need for security
Limitations on method and sequencing of works, working hours – supervision requirements
Sectional completion
Availability of services
Level of contractor’s designed works
How do you take account of inflation when benchmarking / cost estimating?
Through the use of TPIs
What does TPI stand for?
What do TPIs show?
Tender Price Index
They reflect changes in the level of pricing contained in the lowest accepted tenders for new work to take account of market conditions – compares against base rates
Where can you get this information from?
BCIS
DL TPI forecasts – published in Building
In house forecasts