PX : Project Coordination Flashcards

1
Q

1 What is building commissioning?

A

This is the process of inspecting, testing, starting up, and adjusting building systems and then verifying that the systems are operating as intended ans that they meet the design criteria.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

2 How does an independent furniture rep differ from a manufacturer’s rep?

A

This type of furniture representative is self-employed and may represent more than one manufacturer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

3 What type of schedule is this?

A

This is a graphic representation of a critical path method (CPM) schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

4 What type of scheduling chart looks like a bar graph?

A

A Gantt chart.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

5 What client-approved document should be available to the designer before the schematic design process begins?

A

Good business practice requires that a client-approved program be available before this phase of work begins.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

6 What are 5 of the most common variable that can affect the cost of a project when bidding occurs?

A

-actual costs to the contractor and subcontractors -current competitiveness of the market -project schedule -desire of a contractor to get the job -level of profit required by the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

7 On an interior construction project, who is responsible for the final electrical drawings?

A

The electrical engineer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

8 Which consultant is responsible for designing new openings in the floor of an existing building?

A

Structural engineer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

9 Which consultant must assist the interior designer with a project requires installation of heavy equipment?

A

Structural engineer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

10 Who may design a building’s sprinkler system?

A

Mechanical engineer, fire protection engineer or fire protection contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

11 In determining the total time required for a project, who is responsible for estimating the construction time?

A

The contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

12 Who is responsible for determining the accuracy and completeness of dimensions, detail and quantities on shop drawings?

A

The contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

13 Who is responsible for providing any laboratory tests, inspection, and reports required by the contract documents?

A

The owner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

14 What is involved in generating a fee projection?

A

The total fee the designer will receive, after amounts for profit, overhead and other expenses are deducted is allocated to the schedule and to the various staff members who will be completing the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

15 What four tasks does the interior designer normally perform during the schematic design phase of a project?

A

-diagrams and drawings showing the general functional relationship required by the project. -develops preliminary space plans. -prepares design concepts, including color, finishes and furniture. -prepares a preliminary statement of probably project costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

16 What is the difference between a contractor’s general overhead and project overhead?

A

Contractor’s general overhead is the cost of running a business. Project overhead is the expenses incurred in completing a specific job that are not, labor, material or equipment.

17
Q

17 What is the parameter method?

A

This method of estimating allows the interior designed to itemize components along with their unit costs.

18
Q

18 What is life-cycle cost analysis?

A

A method of determining the total cost of a building or building component or system. Initial costs are added to the costs of financing, operation, maintenance, and disposal, estimated over the useful life of the material or system.

19
Q

19 When a project is complete, who takes ownership of the contract documents?

A

The interior designer.

20
Q

20 What is considered to be the project cost?

A

This is the total cost to the owner of all components of a project, including construction, furniture, equipment, the contractor’s overhead and profit and the costs of managing or supervising construction.

21
Q

21 What kinds of expenses are NOT included in the project cost?

A

designer’s fees, consultant’s fees, financing cost

22
Q

22 What are the four stages of a product’s life cycle cost?

A

-raw material acquisition -manufacturing -use and maintenance -disposal