PX : Contract Administration Flashcards
177
What is a performance bond?
This is a statement by a surety company that obligates the surety company to complete construction of the owner’s project if the contractor defaults.
178
What is the purpose of a labor and material payment bond?
This is used to guarantee payment for labor and materials on a project if the contractor defaults or otherwise fails to make payments.
179
At an owner’s request, a contractor may include alternates in the bid documents. What is an alternate?
This is a construction item that could, at the owner’s discretion, be substituted for a similar item in the base bid to reduce project costs.
180
What is a unit price?
This is a set cost for providing a portion of the construction work that is based on an individual quantity, such as per unit or per square foot.
181
What is an allowance in interior design?
This is a set amount of money that the interior designer estimates will cover the cost of a particular item (construction or furnishing) when that cost cannot be determined precisely at the time of the bid or negotiated proposal.
182
What are the four types of written modifications that can be made after the execution of a contract?
Four examples of this are
a change order
an amendment to the contract
a written order for minor changes in the work
a written interpretation by the interior designer
183
What is retainage (also called holdback in Canada)?
This is a percentage (usually 10%) of each payment to a contractor or vendor that is withheld by the owner for the purpose of protecting the owner against incomplete or defective work.
184
What form does a vendor or contractor use to request a payment from the owner?
An application for payment form is used for this.
185
In regard to interior design, what is substantial completion?
In a construction project, this is the stage when work, or a designated portion of it, is sufficiently complete according to the contract documents that the owner can occupy or use the site, even though a few minor items may yet to be finished or corrected.
186
Who has the authority to stop construction?
On a construction project, only the owner can authorize this action.
187
What is a change order?
This is a form used to authorize a change in contract time, contract cost, or both, made after the execution of the contract. It is generally prepared by the interior designer and must be signed by the designer, contractor, and owner.
188
What are shop drawings?
These are detailed drawings, diagrams, and other data, prepared by a subcontractor or supplier, that show exactly how the provider intends to supply and install work to meet the contract requirements. They are submitted to the contractor and interior designer for approval.
189
What is the basic process for getting approval on submittals from subcontractors or suppliers?
First, the submittal is sent to the general contractor, who reviews it and then sends it to the interior designer for approval.
If the submittal also requires a review by one of the designer’s consultants, it is sent to the consultant for review.
The submittal is then sent back to the contractor, who returns it to the party who originally made the submittal.
190
What are the interior designer’s obligations during construction observation?
During this phase of the work, the interior designer
becomes generally familiar with the progress and quality of the work
keep the owner informed about the progress of the work
endeavor to guard the owner against defects in the work
determine, in general, if the work is progressing in such a way that it is in accordance with the contract documents
191
Who has the authority to reject work that does not conform to the contract documents?
The interior designer can reject work that does not conform to these.