Project Time Management Flashcards

1
Q

Planning schedule management

A

Determining the policies procedures and documentation that we use for planning executing a controlling the project schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Defining activities

A

Identifying the specific activities at the project team members and stakeholders must perform to produce the project deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Activity

A

An element of work normally found on the work breakdown structure that has an expected duration, cost, resource requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Sequencing activities

A

Involves reviewing activities and determining dependencies, a dependency is the sequencing of project activities or test

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Mandatory dependencies

A

Inherent in the nature of the work being performed on a project sometimes referred to as hard logic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Discretionary dependencies

A

Define by the project team, sometimes referred to as soft logic and should be used with care since they may limit later scheduling options

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

X ternal dependencies

A

Involves relationships between project and non-project items, such as deliveries from another company

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Finish to finish

A

Task B cannot start until task A finishes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Start to finish

A

Task B cannot finish until task a starts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Duration

A

The Actual amount of time worked on an activity plus elapsed time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Effort

A

The number of work days of work hours required to complete a task

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Gantt chart

A

Is standard format for displaying project schedule information by listing project activities in a corresponding start and finish dates in the calendar format

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Critical path

A

The series of activities that determine the earliest time I wish the project can be completed, it is the longest path through the network diagram and has the least amount of slack

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Buffers

A

Additional time to complete a task

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Murphy’s Law

A

If something can go wrong it will

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Parkinson’s law

A

Work expands to fill the time allowed

17
Q

PERT

A

A network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates. The estimates are based on an optimistic and pessimistic or three point estimate approach