The best type of communication method for passing information to stakeholders is _____________.
A.
Smoke signals
B.
Face-to-face
C.
Email
D.
Telephone
B
The key factor in closing issues is the person to whom you will ________ the issue in order to resolve it.
A.
Communicate
B.
Write
C.
Send
D.
Escalate
D
You are the PM of the server update project for your co. this project has 543 stakeholders, many of which are end users. Some of the end users are critical of the server update because they’re concerned about where the data is stored, how they will access the data in the future and their mapped drivers. You’ve communicated with all of the users that the server update will change how the users will access their files and home folders in the future. Now some of the end users have been complaining to their functional managers about the change. In this scenario, what type of stakeholder are the end users?
A. Uninformed
B. Negative
C. Unresponsive
D. Low influence/ low interest
B
Beth is the PM of a new construction project for her organization’s client. This project will construct a new bridge in a major thoroughfare in her city. Beth is preparing for stakeholder identification because she wants to capture all of the internal and external stakeholders who may influence and be influenced by this project. In her preparations, Beth will need all of the following documents as inputs except for which one?
A. Project charter
B. Enterprise environmental factors
C. Organizational process assets
D. Communications management plan
D
You are the PM for a software development project for your co. this project will create a web-based application that will allow users to create maps for different hiking trails in America. You will be working with developers who are employees of your co. and developers who are contract-based. Your project will also include information from the National Parks Service, local communities, and hikers from around the USA. You and the project team will first complete stakeholder analysis to make certain that you have captured all of the project stakeholders. What are three logical steps to stakeholder analysis?
A. Identify the stakeholders, prioritize stakeholders, anticipate stakeholder responses
B. Identify stakeholders, confirm stakeholders, communicate project plan
C. Identify stakeholders, confirm project scope, create a response strategy
D. Identify stakeholders, meet with stakeholders to address concerns, create stakeholder response plan
A
You have been working on a project that will affect your entire co. of 1233 people. You and the project team should create a stakeholder register for the stakeholders, but id it necessary to create 1233 entries in the register?
A. Yes, all stakeholders should be identified
B. Yes, but it I appropriate to group the stakeholder for easier management
C. No, only the key stakeholders need to be identified in the stakeholder register
D. No, only negative stakeholders and key stakeholders must be documented in the stakeholder register
B
If Anna, the project sponsor, asks Mike, the PM, to create a visual diagram showing which stakeholders can affect the project the most based on their power in the co, which chart should Mike create?
A. Power/ influence diagram
B. Pareto
C. Tornado
D. Ishikawa
A
Which one of the following inputs would help a PM most to create a strategy for stakeholder management and engagement?
A. Project management plan
B. Stakeholder register
C. Enterprise environmental factors
D. Communications management plan
B
In an analysis of stakeholders, the PM and project team have discovered that some of the project stakeholders didn’t know about the change in the co’s approved computer operating systems. How would you classify these stakeholders?
A. Unaware
B. Uninformed
C. Lacking
D. Target for positive
A
If a functional manager is not in favor of a change of operating system for their employees laptops, how would you classify these stakeholders?
A. Neutral
B. Resistant
C. Leading
D. Hesitant
B
What is the purpose of the stakeholder management plan?
A. To convert all stakeholders to positive, supportive stakeholders
B. To identify the stakeholders who re opposed to the project
C. To manage the stakeholder’s attitudes toward the project
D. To communicate with the stakeholders about the project status
C
In the stakeholder management plan, a PM has identified the tactics for managing the stakeholders, and she has identified the positive stakeholders with which categorization?
A. Happy
B. Leading
C. Supportive
D. Informed
C
The stakeholder management plan includes all of the following components except for which one?
A. The relationships among stakeholders
B. The relationships among the project team
C. The schedule of stakeholders information distribution
D. Communication requirements for stakeholders
B
If there is a scheduling conflict in a project, which will cause a two-week delay, what should the PM do?
A. Report the problem to management
B. Report the problem to the stakeholders
C. Say nothing unless the delay becomes greater than two weeks
D. Propose a solution to management
D
If a PM has overlooked some stakeholders in the planning phase, right before beginning the first phase of execution, what should the PM do?
A. Immediately contact the stakeholders, apologize and analyze the stakeholders
B. Begin the project execution but contact the stakeholders for a meeting
C. Determine whether the oversight has damaged the project’s objectives
D. Schedule a meeting with stakeholders to catch them up of the project
A
How should a PM manage an unhappy but compliant stakeholder?
A. Ignore their complaints
B. Explain the benefits of the project
C. Categorize them as resistant
D. Some stakeholders may just be unhappy
B
Which one of the following is not one of the inputs for stakeholder engagement?
A. Change log
B. Org process assets
C. Communications management plan
D. Issue log
D
As a PM you have met with a functional manager and a sales manager to resolve their conflict, negotiate the difference and come to an agreement about the project requirements . what stakeholder tool and technique was used effectively in this scenario? What is the best answer?
A. Active listening
B. Stakeholder resolution
C. Management skills
D. Interpersonal skills
D
All of the following are examples of management skills except which one?
A. Presenting project information
B. Negotiating with stakeholder
C. Public speaking
D. Analyzing work performance
D
What type of communication is a secured e-mail considered to be?
A. Push
B. Interactive
C. Sensitive
D. Passive
A
You are the PM for your co. and you have contracted two organizations to complete parts of the project. The project requires that these two different co’s work together on parts of the project. One of the vendors will need to install network cables throughout a building, while the other co is responsible for connecting the networking cables to a central patch panel and to the individual networking receptacles. The vendors are in disagreement about how the work should take place. What is the best approach to manage this scenario?
A. The vendors are not stakeholders and must live up to the terms of their contract
B. The vendors are stakeholders and you should determine who will do what activities in the project
C. The vendors are not stakeholders but you should use conflict resolution to find the best solution for the contracted work
D. The vendors are project stakeholders and you should utilize conflict resolutions to find the best solutions for the project
D
Which one of the following examples best describes the concept of interactive communication in stakeholder management?
A. Sending an email to select project stakeholders
B. Creating a report on the project team
C. Hosting a project status meeting
D. Creating a secured project repository that only allowed stakeholders can access
C
One of the inputs to controlling stakeholders engagement is the issue log. How does the issue log help you prepare to control stakeholder engagement?
A. This is false; the issue log is not an input to control stakeholder engagement
B. The issue log will help you determine which stakeholders are causing the project issues
C. The issue log is needed only when issues are defined by stakeholders
D. The issue log will help you track and respond to issues and communicate issue status
D
Your project sponsor has requested that you find a software package to serve as a central repository for all project information. They would like for the software to capture, store and provide data analysis on key performance metrics. The software should be able to help complete reports, analyze data and track overall project performance. What is the project sponsor requesting?
A. Reporting system
B. Earned value management system
C. Project management information system
D. Integrated change control system
A
All of the following are types of communications that are related to stakeholder engagement except for which one?
A. Pull communications
B. Push communications
C. Interactive communications
D. Ad hoc communications
D
Stakeholder engagement is key to a successful project, so you and the project team have created a stakeholder management plan that includes many different methods for engaging stakeholders. As part of your plan, you should also reference what other project management plan component?
A. Project communications management plan
B. Project procurement contracts
C. Project scope statement
D. Milestone charts for the project schedule
A
A project has 78 stakeholders and will last 18 months. If two of the employees at the co are leaving soon and won’t be available as resources on the project, in addition to the project staffing document, what other document should be updated?
A. Stakeholder register
B. Risk register
C. Change log
D. Project schedule
A
A document containing all details related to identified stakeholders like name, organizational position, role in the project, main expectations, potential influence on the project, etc. is:
- Stakeholder analysis
- Stakeholder register
- Stakeholder log
- Identified stakeholder log
2
If a stakeholder has high interest in your project and high power or authority, then such stakeholders should be managed with following action plan:
- Manage closely
- Keep satisfied
- Keep informed
- Monitor closely
1