Project Procurement Management Flashcards
In a standard contract, ________ are bound.
A.
Buyer and seller
B.
Project manager and sponsor
C.
Seller and sponsor
D.
Buyer and project manager
A
The seller agrees to furnish products/services, and the buyer agrees to provide ________.
A.
Time
B.
Effort
C.
Consideration
D.
Facilities
C
For the examination, procurement is discussed using the ________ relationship.
A.
Technical
B.
Buyer/seller
C.
Vendor/seller
D.
Purchasing
B
In PMBOK, the buyer is ________ to the project team, and the seller is ________ to the project team.
A.
Assigned, allocated
B.
Important, secondary
C.
Related, outside
D.
Internal, external
D
Market conditions are a part of ________.
A.
Organizational process assets
B.
Project management concerns
C.
Enterprise environmental factors
D.
General management concerns
C
Formal or informal policies that pertain to procurement are part of the ________.
A.
Organizational process assets
B.
Project management concerns
C.
Enterprise environmental factors
D.
General management concerns
A
Needed delivery dates and availability of resources can be found in the details of the ________.
A.
WBS
B.
SOW
C.
Project Scope Statement
D.
Project Charter
A
A Risk Register is a detailed part of the ________.
A.
Project Scope Statement
B.
Project management plan
C.
Project scheduling plan
D.
Project Charter
B
When doing make-or-buy analysis, you should make sure that both ________ and ________ costs are included so that the comparisons are equal.
A.
Tactical, strategic
B.
Management, project
C.
Delayed, sunk
D.
Direct, indirect
D
Technical judgments made to assess inputs and outputs of the planning of purchases and acquisition are an example of using ________.
A.
Expert judgment
B.
External assets
C.
Internal assets
D.
Computers
A
There are three general types of contracts: cost reimbursable, time and materials, and ________.
A.
Cost required
B.
Fixed price
C.
Simple cost
D.
Reimbursed time
B
Which type of contract has the highest risk for the buyer?
A.
Fixed price
B.
Reimbursed time
C.
Time and materials
D.
Cost plus
C
In the cost plus contract with the initials CPFF, the FF stands for ________.
A.
Formula foundation
B.
Free fixed
C.
Founded fixed
D.
Fixed fee
D
Which type of contract has the highest risk for the seller?
A.
Fixed price
B.
Reimbursed time
C.
Time and materials
D.
Cost plus
A
The type of contract where the buyer and seller share in the savings is ________.
A.
Fixed Price
B.
Cost reimbursable with incentive fee
C.
Cost reimbursable with fixed fee
D.
Time and materials
B
Which type of contract uses a percentage of cost as a part of the agreed upon contract?
A.
T&M
B.
CPFF
C.
CPIF
D.
CPPC
D
A buyer negotiates a fixed-price incentive contract with the seller. The target cost is $200,000, the target profit is $35,000, and the target price is $250,000. The buyer negotiates a ceiling price of $280,000 and a share ratio of 70/30. If the contract is completed with actual costs of $180,000, how much profit will the buyer pay the seller?
A.
$49,000
B.
$41,000
C.
$38,000
D.
$29,000
The answer is B. This is how to work this problem out. The numbers that you need to be concerned with are the target cost, $200,000, the target profit, $35,000, the share ratio of 70/30, and the actual costs of $180,000. (In a share ratio, the first percentage goes to the buyer and the second number is the percentage that the seller will get.) Using these numbers, the calculation goes like this. You subtract the actual costs from the target cost, which gives you $20,000. Seventy percent of that goes to the buyer, whereas thirty percent goes to the seller. In this case, that would be 30% of $20,000 or $6,000. Add $6,000 to the target profit of $35,000, and you have your answer, which is $41,000.
Definition of contract types to be used, how to handle lead times for procurement, and metrics used to manage contracts are all found in the ________.
A.
SOW
B.
Procurement management plan
C.
WBS
D.
Scope Statement
B
The document that gives detail to prospective sellers concerning item or items to be purchased is the ________.
A.
SOW
B.
Charter
C.
WBS
D.
CSOW
D
The document that contains information such as identified risks and risk owners is called a ________.
A.
Risk Register
B.
SOW
C.
WBS
D.
Risk locator
A
The evaluation criteria are determined by the ________.
A.
Seller
B.
Project manager
C.
Buyer
D.
Sponsor
C
Procurement documents are documents seeking information from the ________.
A.
Seller
B.
Project manager
C.
Buyer
D.
Accountant
A
Meetings with prospective sellers to ensure they have a clear understanding of the requirements are known as ________.
A.
Bidder conferences
B.
Vendor conferences
C.
Contract conferences
D.
All of the above
D
The system that assigns a value to evaluation criteria is known as the ________.
A.
Weighting system
B.
Screening system
C.
Expert judgment
D.
Rating system
A