Project Scheduling Management Flashcards

1
Q

Define Sequencing

A

The identification and documentation of relationships among Project Activities. This is done to help develop an estimated time of completion and to further contribute to the development of the project schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Identify precedence relationships

A

There are 4:

Finish-To-Start (FS): Where once an activity finishes, another can start

Finish-To-Finish (FF): Where one activity can finish only if a different activity finishes as well

Start-To-Start (SS): Where an activity can start once a different one has started

Start-To-Finish (SF): Where an activity can finish once a different activity starts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the Critical Path Method?

A

The critical path method is the calculation of both early AND late start to end dates for all activities. These calculations are than used to determine the critical path and any flexibility in the schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the Critical Path?

A

The critical path is the longest path in the project. One that has no slack

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is Slack?

A

Slack is the flexibility in the schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How do you calculate Slack?

A

Slack = Late Finish - Early Finish = Early Start - Late Start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What processes are included in Project Schedule Management, and in what order?

A
  1. Plan Schedule Management
  2. Define Activities
  3. Sequence Activities
  4. Estimate Activity Durations
  5. Develop Schedule
  6. Control Schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Define Activity

A

Specified work that needs to be performed in order to contribute to the production of a deliverable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define Duration

A

The amount of time that it takes from the start of an activity to when the activity is finished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly