Project Schedule Mgmt Flashcards

1
Q

What are the main outputs of the plan schedule management process?

A

Schedule management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the main outputs of the device activities process?

A

Activity list, activity attributes, milestone list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the main outputs of the sequence activities process?

A

Project schedule network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the main outputs of the estimate activity durations process?

A

Activity duration estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the main outputs of the develop schedule process?

A

Schedule baseline, project schedule, schedule data, project calendars

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the main outputs of the control schedule process?

A

Work performance information, change request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Describe the schedule management plan

A

Documents the steps needed to conduct the other 5 processes - how the project defines activities, sequences activities, estimates resources, develops schedule, and controls schedule.

Also states how the measure schedule, and fix it if there are variances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Describe decomposition as part of the define activities process

A

Taking work packages within the WBS and breaking them into specific activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Describe rolling wave planning

A

A form of progressive elaboration used in the define activities process group - work packages happening later in the project will be decomposed when more details are known

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Describe activity list

A

Main output of define activities process. A list of all scheduled activities on the project. Each activity should map to only one work package, and have a unique identifying number

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Describe activity attributes

A

Main output of define activities process group. More detailed information about each individual activity.

Can include resources, location, cost, assumptions, constraints, leads/lags, and relationships

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Describe milestone list

A

Consists of all project or phase milestones. A milestone is an activity that has no duration and is used to represent a major accomplishment or event.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Describe PDM used in the Sequence Activities process

A

Precedence Diagramming Method. Used to create the network diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Describe AON PDM

A

Activity-On-Node precedence diagramming method. Boxes used to represent activities, with numbers above them representing durations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Name the four types of activity relationships

A

Finish to start (FS), finish to finish (FF), start to start (SS), start to finish (SF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why are the four types of dependencies?

A

Mandatory, discretionary, external, internal

17
Q

Describe leads and lags in the sequence activities process

A

Leads: an overlap between activities (eg, you can start an activity halfway through the previous)

Lags: delays between activities (eg, needing to wait for a time after completion to begin the next activity)

18
Q

Describe project schedule network diagrams

A

A diagram showing all the activities, and the order in which they are performed

19
Q

Describe the basis of estimates

A

Output of “estimate activity durations”. It is how the estimates were developed and their ranges. It can also include assumptions and constraints.

20
Q

Describe project calendars

A

Displays the working days and shifts for the activities.