Project Schedule Management Flashcards

1
Q

activity list

A

a documented tabulation of schedule activities that shows the activity description, activity identifier, and sufficiently detailed scope of work description so project team members understand what work is to be performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

activity attributes

A

multiple attributes associated w each schedule activity that can be included within the activity list.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

milestone list

A

a list identifying all project milestones and normally indicates whether the milestone is mandatory or optional.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

name the type of dependencies

A

mandatory (aka hard logic)
discretionary (aka preferred or soft logic)
internal
external

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

mandatory (aka hard logic) dependencies

A

a relationship that is contractually required or inherent in the nature os the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

discretionary (aka preferred or soft logic) dependencies

A

a relationship that is established based on knowledge of best practices within a particular application area or an aspect of the project where a specific sequence is desired.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

internal dependencies

A

involve a precedence relationship between project activities and are generally inside the project team’s control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

external dependencies

A

involve a relationship between project activities and non-project activities; are usually outside of the team’s control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

logical relationships

A

a dependency between two activities, or between an activity and a milestone.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

lag

A

the amount of time whereby a successor activity is required to be delayed w respect to a predecessor activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

predecessor activity

A

an activity that logically comes before a dependent activity in a schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

successor activity

A

a dependent activity that logically comes after another activity in a schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

schedule management processes

A

includes the processes required to manage the timely completion of the project:

plan schedule management
define activities
sequence activities
estimate activity durations
develop schedule
control schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

transitioning from project scope management to project schedule management includes:

A

scope management:
- collecting requirements
- developing the scope statement
- creating a decomposed WBS (to the level of work packages)
- estimating the scope baseline

leads to…

schedule management:
- using WBS to further decompose work packages into activities
- creating a project schedule from the activities and the resource plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

define plan schedule management

A

process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

key benefit is that it provides guidance on how the schedule will be managed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

name inputs, tools & techniques, and outputs of plan schedule management

A

Inputs:
* Project Management Plan
* Project Charter
* Enterprise Environmental factors
* Organizational process assets

Tools and Techniques:
* Expert judgement
* Data analysis
* Meetings

Outputs:
* Schedule Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Data analysis techniques

A

Various techniques used to evaluate, analyze, or forecast potential outcomes based on possible variations of project or environmental variables and their relationships with other variables

18
Q

Schedule Management Plan

A

A component of the project management plan that establishes the criteria and the activities for developing, monitoring, and controlling the schedule.

should include control thresholds and performance measurement rules so that progress can be measured.

19
Q

Define Activities Process

A

The process of identifying and documenting the specific actions to be performed to produce the project deliverables.

The key benefit is that it breaks down the work packages in the WBS into specific activities.

20
Q

name inputs, tools & techniques, and outputs of Define Activities Process

A

Inputs:
* Project management plan
* Schedule Management Plan
* Scope baseline
* Enterprise environmental factors
* Organizational process assets

Tools and Techniques:
* Decomposition
* Rolling wave planning
* Expert judgement
* Meetings

Outputs:
* Activity list
* Activity attributes
* Milestone list
* Change requests
* Project management plan updates

21
Q

Milestone

A

is simply a significant point or event in a project, program, or portfolio

22
Q

Rolling Wave Planning

A

An iterative planning technique in which the work to be accomplished in the near term is planned in detail, while work further out in the future is planned at a higher level. As that further out work get’s closer, it is then planned in detail.

23
Q

Decomposition

A

In scope management, project deliverables are subdivided into smaller and more manageable items until the project product, service, and process outcome components are defined to the work package level

24
Q

Sequence Activities Process

A

the process of identifying and documenting relationships among the project activities.

key benefit is that it defines the logical sequence of work.

25
Q

name inputs, tools & techniques, and outputs of Sequence Activities Process

A

Inputs:
* Project Management Plan
* Schedule Management Plan
* Project documents
* Project Scope Statement
* Activity list
* Activity attributes
* Milestone list
* Requirements documentation
* Organizational process assets

Tools and Techniques:
* PDM
* Dependency determination
* Leads and Lags
* Project management information system

Outputs:
* Project Schedule network diagrams
* Project documents updates

26
Q

PDM (Precedence Diagramming Method)

A

A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.

27
Q

Dependency determination

A

A technique used to identify a type of dependency that is used to create the logical relationships between predecessor or successor activities.

28
Q

Project Schedule Network Diagram

A

A graphical representation of the logical relationships among the project schedule activities. This diagram is the result of the precedence diagramming effort and is an output of the Sequence Activities process.

can be thought of as a flowchart that shows the order and relationships between the work that must be performed, and the Precedence Diagramming Method (PDM) is the technique used to develop this schedule network diagram.

29
Q

There are four different precedence relationships:

A
  • Finish-to-start (FS) - A logical relationship in which a successor activity cannot start until a predecessor activity has finished (most common)
  • Finish-to-finish (FF) – A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
  • Start-to-start (SS) – A logical relationship in which a successor activity cannot start until a predecessor activity has started.
  • Start-to-finish (SF) - A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
30
Q

Precedence relationship

A

The term used in the precedence diagramming method for a logical relationship

31
Q

Estimate Activity Durations Process

A

the process of estimating the number of work periods needed to complete individual activities with estimated resources.

The key benefit is that it provides the time each activity will take to complete.

32
Q

name inputs, tools & techniques, and outputs of Estimate Activity Durations Process

A

Inputs:
* Project Management Plan
* Schedule Management Plan
* Project documents
* Activity list
* Activity attributes
* Project scope statement
* Risk register
* Enterprise environmental factors
* Organizational process assets

Tools and Techniques:
* Expert judgement
* Analogous estimating
* Parametric estimating
* Three-point estimating
* Data analysis
* Decision Making
* Meetings

Outputs:
* Activity duration estimates
* Basis of estimates
* Project documents updates

33
Q

Bottom-Up Estimating

A

A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).

34
Q

Activity resource requirements

A

The types and quantities of resources required for each activity in a work package.

35
Q

Analogous estimating

A

A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.

36
Q

Parametric estimating

A

An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters

37
Q

Effort

A

The number of labor units required to complete a schedule activity or work breakdown structure component, often expressed in hours, days, or weeks.

38
Q

Duration

A

The total number of work periods (not including holidays or other nonworking periods) required to complete a schedule activity or work breakdown structure component. Usually expressed as workdays or workweeks.

minimized if resources can be assigned full- time, this increasing productivity.

39
Q

Three-Point Estimating

A

a technique used to estimate cost or duration by applying an average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates.

40
Q

There are two types of three-point estimating:

A

PERT - Program Evaluation and Review Technique. It’s is also sometimes called Beta distribution. A technique for estimating that applies a weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates.

Triangular distribution – The more simple of the two types, here the most likely, optimistic and pessimistic estimate are simply summed and result is divided by 3.

41
Q

In three-point estimating, three values are individually estimated:

A

Most likely (m) - An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance. This is sometimes also called the best guess (BG) estimate.

Optimistic (o) - An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance. This estimate considers what the
estimate might be if positive factors do occur.

Pessimistic (p) – An estimate of the longest activity duration
that takes into account all of the known variables that could affect performance. This estimate considers what the estimate might be if negative factors do occur.