Project Schedule Management Flashcards
activity list
a documented tabulation of schedule activities that shows the activity description, activity identifier, and sufficiently detailed scope of work description so project team members understand what work is to be performed.
activity attributes
multiple attributes associated w each schedule activity that can be included within the activity list.
milestone list
a list identifying all project milestones and normally indicates whether the milestone is mandatory or optional.
name the type of dependencies
mandatory (aka hard logic)
discretionary (aka preferred or soft logic)
internal
external
mandatory (aka hard logic) dependencies
a relationship that is contractually required or inherent in the nature os the work.
discretionary (aka preferred or soft logic) dependencies
a relationship that is established based on knowledge of best practices within a particular application area or an aspect of the project where a specific sequence is desired.
internal dependencies
involve a precedence relationship between project activities and are generally inside the project team’s control.
external dependencies
involve a relationship between project activities and non-project activities; are usually outside of the team’s control.
logical relationships
a dependency between two activities, or between an activity and a milestone.
lag
the amount of time whereby a successor activity is required to be delayed w respect to a predecessor activity.
predecessor activity
an activity that logically comes before a dependent activity in a schedule.
successor activity
a dependent activity that logically comes after another activity in a schedule.
schedule management processes
includes the processes required to manage the timely completion of the project:
plan schedule management
define activities
sequence activities
estimate activity durations
develop schedule
control schedule
transitioning from project scope management to project schedule management includes:
scope management:
- collecting requirements
- developing the scope statement
- creating a decomposed WBS (to the level of work packages)
- estimating the scope baseline
leads to…
schedule management:
- using WBS to further decompose work packages into activities
- creating a project schedule from the activities and the resource plan
define plan schedule management
process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
key benefit is that it provides guidance on how the schedule will be managed.
name inputs, tools & techniques, and outputs of plan schedule management
Inputs:
* Project Management Plan
* Project Charter
* Enterprise Environmental factors
* Organizational process assets
Tools and Techniques:
* Expert judgement
* Data analysis
* Meetings
Outputs:
* Schedule Management Plan