Project Planning: Schedule and Cost Management Flashcards
Project Schedule Management definition
involves the processes required to ensure timely completion of a project
What do we need to do here?
1.Planning schedule management
–> determining the policies, procedures, and documentation that will be used for planning, executing, and controlling the project schedule
What is it relating to?
- Define activities
–> identifying the specific activities that the project team members and stakeholders must perform to produce the project deliverables
In which order?
- Sequencing activities
–> identifying and documenting the relationships between project activities
What do we need to get it done?
4.Estimating activity resources
–> estimating how many resources a project team should use to perform project activities
How long will it take?
5.Estimating activity durations
–> estimating the number of work periods that are needed to complete individual activities
How does it look over time?
- Developing the schedule
–> analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule
Recurringly: are we still good to go?
7.Controlling the schedule
–> controlling and managing changes to the project schedule
activity (or “tasks”)
is a distinct, scheduled portion of work performed during the course of a project.
The goal of the defining activities process is..
to ensure that project team members have a complete understanding of all the work they must do as part of the project scope so that they can start scheduling the work.
the activity list
is a tabulation of activities to be included on a project schedule
What should be included in an activity list?
-the activity name
-an activity identifier
-number
-a brief description of the activity
The activity attributes provide
schedule-related information about each activity
for example: predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activit
Activity list and attributes should be in agreement with..
the WBS and WBS dictionary and be reviewed by key project stakeholders
milestone
is a significant point or event in a project
–> is like a marker to help identify necessary activities
how much time it take to complete a milestone
There is usually no cost or duration for a milestone
–> takes several activities and a lot of work to complete a milestone
Sample milestones for many projects include:
-Sign-off of key documents
-Completion of specific products
-Completion of important process-related work, such as awarding a contract to a supplier
Who focuses on the major milestone project?
project sponsors and senior managers
sequencing activities
involves evaluating the dependencies (or relationship) between activities
determine dependencies
in order to use critical path analysis
critical path
for a project is the series of activities that determine the earliest time by which the project can be completed.
3 types of dependencies
-Mandatory dependencies
-Discretionary dependencies
-External dependencies
mandatory dependencies
are inherent in the nature of the work being performed on a project
Discretionary dependencies
are defined by the project team
External dependencies
involve relationships between project and non-project activities
Network diagram
are the preferred technique for showing activity sequencing
–> is a schematic display of the logical relationships among, or
sequencing of, project activities
Two main formats are:
-The arrow diagramming: Activity-On-Arrow (AOA) approach, also known as the Arrow
Diagramming Method (ADM)
-The Precedence Diagramming Method (PDM)
Process for Creating AOA Diagrams
- Find all of the activities that start at node 1. Draw their finish nodes and draw arrows between node 1 and those finish nodes. Put the activity letter or name and duration estimate on the associated arrow
- Continuing drawing the network diagram, working from left to right. Look for bursts and merges
3.Continue drawing the project network diagram until all activities that have dependencies are included in the diagram.
- As a general rule, all arrowheads should point to the right and no arrows should intersect on an AOA network diagram.
Bursts
occur when a single node is followed by two or more activities
Merge
occurs when two or more nodes precede a single node
Precedence Diagramming Method (PDM)
-Activities are represented by boxes
-Arrows show relationships between activities
-More popular than AOA / ADM method and used by project management software
-Better at showing different types of dependencies