Project Planning Flashcards

1
Q

What must be considered when a completion date is set?

A

The potential for unexpected delays

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is contained in a master programme?

A

The design period, each individual construction programme and other time sinks such as site investigation and tendering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the ‘free float’ of a construction task?

A

The amount of time by which the task beginning can vary without affecting the overall works completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the critical path and what is true of all the tasks on it?

A

The series of successive tasks which take the longest to produce their final product. None of these tasks can have float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How must a network begin and end?

A

With milestone tasks that have zero duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

From top left to bottom right, what do the numbers in a network entry mean?

A

Earliest start, earliest end

Latest start, latest end

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

List the benefits of a bill of quantities pricing method

A
All tenderers price from the same information
Standard method means pricing is clear
Monthly payments are easily valued
Variations are easily priced
Low risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

List the disadvantages of a bill of quantities

A

Later start date
Disagreements possible over measurements
Discourages teamwork
Cannot be used on D&B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

List the advantages of an activity schedule

A

Reduces employer risk
Allows good prediction of cash flow
Saves time in producing a BoQ

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

List the disadvantages of an activity schedule

A

Difficult to compare tenders
Difficult to use as a basis for costing variations
Activity scope can be disagreed upon

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

In a bill of quantities, what is a provisional item?

A

Work which is known to be required but is unknown in its extent and character

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How are provisional items priced in a bill of quantities?

A

By lump sum, to be used in full or in part as decided by the contract admin

How well did you know this?
1
Not at all
2
3
4
5
Perfectly