Contact Procurement Flashcards
Who must be considered during a construction project?
The client, the users and the stakeholders
What are the 7 steps of a development process?
Assess need Assess funding Begin design Assess design options Choose and develop design Choose contractor Build and deliver project
At what point in the development process does money begin to be paid out?
The initial design phase
How does the development process aim to prevent systematic issues with a construction?
Implementing gateways between each main development stage
What are the two roles typically appointed by the client to overlook the development?
Project manager
Site supervisor
What happens if the site supervisor finds that the contractor is not working to the specifications?
They need to consult with the architects about whether this is allowable
What happens to cost of changes and stakeholder influence as the project progresses?
Cost of changes increases
Influence decreases
What are the typical limits for cost estimation at stages 3 and 5 of the development process?
20% of the final price at stage 3
5% of the final price at stage 5
List three entities considered to be ‘parties’
Any from:
Architects, Builders, Designers, QS, Contractors
List three entities considered to be ‘stakeholders’
Any from:
Banks, local authorities, neighbours, environmental groups
What is the difference between involved parties and stakeholders?
Parties have a legal, contractual link to the project. Stakeholders simply have an interest in the project outcomes
What is a tender?
A collection of documents including design drawings which inform contractors of the type of works which will be required
What must a tender package include?
Design drawings, tender instructions, contract terms, method of payment, preliminary site information, H&S documentation and specifications
What are the 4 main single bid tender methods?
Open tender
Selective tendering
Pre-qualification
Negotiated
When is two stage tendering used?
When contractor input is required to finalise a design
Is it possible to change contractors if the price returned by stage 2 tendering is too high?
Yes, but it is complicated and therefore not often done
What must happen if a tender applicant requests further information?
The requested information must be sent to all other tender applicants
How long is a typical tender return period?
1-2 months
What is a good estimate for the price a tender should return?
20-5% of the QS estimate before tendering
How does choice of material, if left flexible, affect tendering?
A specified quality must be met regardless of material used
What do the EU procurement directives require public bodies to do periodically?
Send out indicative notices of future works that are being planned
What must happen if a tender is unsuccessful?
They are told the terms of the winning contract and their score relative to the winner
If a contractor provides a tender PIN to the employer, what does this mean?
Their tender application must be considered
How do regulations aim to prevent exclusive tendering?
Technical specifications for a project are not allowed to be designed such that only one contractor is able to meet them