Contact Procurement Flashcards

1
Q

Who must be considered during a construction project?

A

The client, the users and the stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the 7 steps of a development process?

A
Assess need
Assess funding 
Begin design
Assess design options
Choose and develop design
Choose contractor
Build and deliver project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

At what point in the development process does money begin to be paid out?

A

The initial design phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How does the development process aim to prevent systematic issues with a construction?

A

Implementing gateways between each main development stage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the two roles typically appointed by the client to overlook the development?

A

Project manager

Site supervisor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What happens if the site supervisor finds that the contractor is not working to the specifications?

A

They need to consult with the architects about whether this is allowable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What happens to cost of changes and stakeholder influence as the project progresses?

A

Cost of changes increases

Influence decreases

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the typical limits for cost estimation at stages 3 and 5 of the development process?

A

20% of the final price at stage 3

5% of the final price at stage 5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

List three entities considered to be ‘parties’

A

Any from:

Architects, Builders, Designers, QS, Contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

List three entities considered to be ‘stakeholders’

A

Any from:

Banks, local authorities, neighbours, environmental groups

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the difference between involved parties and stakeholders?

A

Parties have a legal, contractual link to the project. Stakeholders simply have an interest in the project outcomes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a tender?

A

A collection of documents including design drawings which inform contractors of the type of works which will be required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What must a tender package include?

A

Design drawings, tender instructions, contract terms, method of payment, preliminary site information, H&S documentation and specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the 4 main single bid tender methods?

A

Open tender
Selective tendering
Pre-qualification
Negotiated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When is two stage tendering used?

A

When contractor input is required to finalise a design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Is it possible to change contractors if the price returned by stage 2 tendering is too high?

A

Yes, but it is complicated and therefore not often done

17
Q

What must happen if a tender applicant requests further information?

A

The requested information must be sent to all other tender applicants

18
Q

How long is a typical tender return period?

A

1-2 months

19
Q

What is a good estimate for the price a tender should return?

A

20-5% of the QS estimate before tendering

20
Q

How does choice of material, if left flexible, affect tendering?

A

A specified quality must be met regardless of material used

21
Q

What do the EU procurement directives require public bodies to do periodically?

A

Send out indicative notices of future works that are being planned

22
Q

What must happen if a tender is unsuccessful?

A

They are told the terms of the winning contract and their score relative to the winner

23
Q

If a contractor provides a tender PIN to the employer, what does this mean?

A

Their tender application must be considered

24
Q

How do regulations aim to prevent exclusive tendering?

A

Technical specifications for a project are not allowed to be designed such that only one contractor is able to meet them

25
Q

What is the process of ‘tendering’ a designer called?

A

Appointment

26
Q

What factors about the employer affect the contract strategy that should be used?

A
Experience
Acceptable risk
Funding 
Certainty of project requirement
Timescale
27
Q

What factors about the design affect contract strategy?

A

Extent of employer involvement
Experience of team
Potential benefit of contractor involvement

28
Q

What is a ‘traditional contract’?

A

Contractual separation of designer and contractor

Full design is completed before tendering

29
Q

What is a ‘design & build contract’?

A

An integration of design and contractor processes
Design input specifies a set of requirements which are used to tender
Contractors return design suggestions based on these requirements

30
Q

What is a Novation?

A

A legal mechanism which allows the preliminary design team of a D&B contract to be substituted in for the contractor’s design team

31
Q

How do partnering, alliances and joint ventures differ?

A

Partnering is a non binding collaboration between two or more contractors
An alliance is where companies agree to work together and are contractually linked but have separate contracts with the client
A joint venture is where companies create a new legal entity to allow them to work together on a specific project. The client only signs one contract with this new entity

32
Q

What is a private finance initiative?

A

When a public body needs to complete a project such as a new hospital but does not have the funds, they allow a private company to maintain and operate the site for 20 years in exchange for a lower cost

33
Q

What contract strategy allows the employer to have direct communication with the works contractors?

A

A management contract

Note: this is only applicable to clients with a lot of industry experience

34
Q

What is the NEC3 ECC option for a management contract?

A

F

35
Q

What are some advantages of a traditional contract? (4)

A

Design requirements are fully understood
Approvals requiring early designs can be obtained
Designers can assist project development
Project can be changed or stopped cheaply

36
Q

What are some disadvantages of a traditional contract? (5)

A
Slower overall
Delays are client liable
Poor teamwork
Frequent misunderstandings
Liability for defects is difficult to determine
37
Q

What are some advantages of a design and build contract? (5)

A
Incorporating buildability 
Design delays are not client liable
Fewer misunderstandings
More price certainty
Quicker start and completion
38
Q

What are some disadvantages of a design and build contract? (5)

A
Poor flexibility
Higher tender price
Longer tender period
Bad where architecture is important
Difficult to compare tenders