Contact Procurement Flashcards

1
Q

Who must be considered during a construction project?

A

The client, the users and the stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the 7 steps of a development process?

A
Assess need
Assess funding 
Begin design
Assess design options
Choose and develop design
Choose contractor
Build and deliver project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

At what point in the development process does money begin to be paid out?

A

The initial design phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How does the development process aim to prevent systematic issues with a construction?

A

Implementing gateways between each main development stage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the two roles typically appointed by the client to overlook the development?

A

Project manager

Site supervisor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What happens if the site supervisor finds that the contractor is not working to the specifications?

A

They need to consult with the architects about whether this is allowable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What happens to cost of changes and stakeholder influence as the project progresses?

A

Cost of changes increases

Influence decreases

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the typical limits for cost estimation at stages 3 and 5 of the development process?

A

20% of the final price at stage 3

5% of the final price at stage 5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

List three entities considered to be ‘parties’

A

Any from:

Architects, Builders, Designers, QS, Contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

List three entities considered to be ‘stakeholders’

A

Any from:

Banks, local authorities, neighbours, environmental groups

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the difference between involved parties and stakeholders?

A

Parties have a legal, contractual link to the project. Stakeholders simply have an interest in the project outcomes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a tender?

A

A collection of documents including design drawings which inform contractors of the type of works which will be required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What must a tender package include?

A

Design drawings, tender instructions, contract terms, method of payment, preliminary site information, H&S documentation and specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the 4 main single bid tender methods?

A

Open tender
Selective tendering
Pre-qualification
Negotiated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When is two stage tendering used?

A

When contractor input is required to finalise a design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Is it possible to change contractors if the price returned by stage 2 tendering is too high?

A

Yes, but it is complicated and therefore not often done

17
Q

What must happen if a tender applicant requests further information?

A

The requested information must be sent to all other tender applicants

18
Q

How long is a typical tender return period?

A

1-2 months

19
Q

What is a good estimate for the price a tender should return?

A

20-5% of the QS estimate before tendering

20
Q

How does choice of material, if left flexible, affect tendering?

A

A specified quality must be met regardless of material used

21
Q

What do the EU procurement directives require public bodies to do periodically?

A

Send out indicative notices of future works that are being planned

22
Q

What must happen if a tender is unsuccessful?

A

They are told the terms of the winning contract and their score relative to the winner

23
Q

If a contractor provides a tender PIN to the employer, what does this mean?

A

Their tender application must be considered

24
Q

How do regulations aim to prevent exclusive tendering?

A

Technical specifications for a project are not allowed to be designed such that only one contractor is able to meet them

25
What is the process of ‘tendering’ a designer called?
Appointment
26
What factors about the employer affect the contract strategy that should be used?
``` Experience Acceptable risk Funding Certainty of project requirement Timescale ```
27
What factors about the design affect contract strategy?
Extent of employer involvement Experience of team Potential benefit of contractor involvement
28
What is a ‘traditional contract’?
Contractual separation of designer and contractor | Full design is completed before tendering
29
What is a ‘design & build contract’?
An integration of design and contractor processes Design input specifies a set of requirements which are used to tender Contractors return design suggestions based on these requirements
30
What is a Novation?
A legal mechanism which allows the preliminary design team of a D&B contract to be substituted in for the contractor’s design team
31
How do partnering, alliances and joint ventures differ?
Partnering is a non binding collaboration between two or more contractors An alliance is where companies agree to work together and are contractually linked but have separate contracts with the client A joint venture is where companies create a new legal entity to allow them to work together on a specific project. The client only signs one contract with this new entity
32
What is a private finance initiative?
When a public body needs to complete a project such as a new hospital but does not have the funds, they allow a private company to maintain and operate the site for 20 years in exchange for a lower cost
33
What contract strategy allows the employer to have direct communication with the works contractors?
A management contract | Note: this is only applicable to clients with a lot of industry experience
34
What is the NEC3 ECC option for a management contract?
F
35
What are some advantages of a traditional contract? (4)
Design requirements are fully understood Approvals requiring early designs can be obtained Designers can assist project development Project can be changed or stopped cheaply
36
What are some disadvantages of a traditional contract? (5)
``` Slower overall Delays are client liable Poor teamwork Frequent misunderstandings Liability for defects is difficult to determine ```
37
What are some advantages of a design and build contract? (5)
``` Incorporating buildability Design delays are not client liable Fewer misunderstandings More price certainty Quicker start and completion ```
38
What are some disadvantages of a design and build contract? (5)
``` Poor flexibility Higher tender price Longer tender period Bad where architecture is important Difficult to compare tenders ```