Project Management Processes Flashcards
When the project manager determines whether the business case can be met and does some high-level planning during initiating to verify that it is likely the project can be completed within the given constraints of scope, time, cost, ect…. What process is this?
Initiating
When a project is officially approved, it is in the ______ process.
Initiating
Once a project has been approved, it moves from initiating into the _____ process, where a plan is created for how planning, executing, monitoring and controlling, and closing the project will be done.
Planning process
When the team completes the work according to the processes and procedures detailed in the project management plan, it is in the ______ process.
Executing
While the work is being done, the work results aka work performance ___ are fed into the ______ process, to make sure the project is tracking to the baselines in the project management plan.
Work performance data
Monitoring and controlling phase
If there are variances from the plan that require changes, the change requests are evaluated during the ______ process to determine their impact on the project, identify the best options for dealing with them, and decide whether they should be approved or rejected.
Perform Integrated Change Control process
Approved changes (name examples) that don’t affect the baseline are fed back into the _____ process to be implemented as part of the project work. The implementation of these approved changes should help ____ the variances
Corrective action
Preventive action
Rework
Executing process
Fix
For approved changes that require adjustments to the baselines and project manager plan, what effort must be completed before the team can start working from the new updated version of the plan and baselines in executing.
Replanning effort
If the project gets so far off the baselines that it requires an analysis of whether the project should continue at all, it may move back into the _____ phase.
Initiating
The project management process groups don’t occur sequentially, they ALL ______.
Overlap
Management plans are required for each of the knowledge areas (integration, scope, time, cost, ect). The first thing to do when planning is figure out how you are going to ____, ____, and _____ each knowledge area.
Plan, execute, and control
Changes can be requested in both the _____ and ______ process groups. The change requests are then evaluated and approved/rejected as part of the _____ process.
Executing and the monitoring and controlling process groups.
Perform Integrated Change Control process
The process of continually refining estimates and scope is called _____.
Progressive elaboration
The results of the planning effort are the project mgmt plan and project documents that will guide the ____ and _____ of the project.
Project planning is _____.
Each planning process may use the results of the previous processes, and each process may ____ or ____ changes to the previous processes.
Then after _____, _____ & _____, and _____, you go back to finalize all the components of the project mgmt plan and project documents. This approach to planning ___ time & effort.
Execution and control
Iterative
Affect or cause
Risk indemnification, qualitative & quantitative risk analysis, and risk response planning
Saves
In an ______ life cycle approach, only the first part of the project may be fully planned, while the later pieces are planned at a higher level and then ______ when more is known about the project. Detailed planning for the next phase is done as the previous phase nears completion. This approach is called ______.
Adaptive life cycle
Progressively elaborated
Rolling wave planning