Project Management Process group and Knowledge areas Flashcards

1
Q

PROJECT INTEGRATION MANAGEMENT

A

Initiating- Develop Project Charter
Planning- Develop Project Management Plan
Executing- Direct and Manage Project work
Monitoring and Controlling- Monitoring and Controlling Project Work
Monitoring and Controlling- Perform Integrated Change Control
Closing- Close project or phase.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

PROJECT SCOPE MANAGEMENT

A
Planning- Plan Scope Management
Planning- Collect Requirements
Planning- Define Scope
Planning- Create WBS
Monitoring and Controlling- Validate Scope
Monitoring and Controlling-Control Scope
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

PROJECT TIME MANAGEMENT

A
Planning- Plan Schedule Management
Planning- Define Activities
Planning- Sequence Activities
Planning- Estimate Activity Resources
Planning- Estimate Activity Duration
Planning- Develop Schedule
Monitoring and Controlling Control Schedule.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly