Project management, del 1 Flashcards
What is PERT?
Programme Evaluation and Review Technique
Firstly developed by US navy for Polaris missile project
Developed to handle uncertain activity times
What is CPM?
Critical Path method
Developed by Du Pont & Remington Rand
Developed for industrial projects for which activity times generally were known
How are the two methods used today and for what?
Todays project management software packages have combined the best features of both approaches.
Used to plan, schedule and control:
Individual activities that make up a project
R&D of new products and processes
Construction of buildings and highways
Maintenance of large and complex equipment
Design and installation of new systems
What is a complicating factor with many activities?
Projects may have thousand of activities. Some activities depend on the completion of other activities, meaning that they can’t be started before others are completed. This is a complicating factor, the delay.
What does PERT/CPM answer?
– What is the total time to complete the project?
– What are the scheduled start and finish dates for each specific activity?
– Which activities are critical and must be completed exactly as scheduled to keep the project on schedule?
– How long can noncritical activities be delayed before they cause an increase in the project completion time?
What is a project network, nodes, arcs and critical path?
A project network is constructed to model the precendence of the activites
The nodes of the network = activites
The arcs of the network = precedence relationships of the activites
A critical path = a path consisting of activites with zero slack
What 2 (3) stages has CPM?
Step 1 = mowing forwards
Earliest start and finish times
Step 2 = moving backwards
Latest start and finish times
Step 3 = Determining the critical path
Slack
Calculate earliest finish time
Earliest start time (EF för tidigare aktivitet) + Time to complete activity (formel finns)
Vad är latest finish time för sista aktiviteten i projeketet om earliest finish är 20?
- Alltid samma
Calculate latest start time
Latest finish time (LS för aktiviteten innan) – Time to complete activity i
Calculate slack
Slack = Latest start – Earliest start
Slack = Latest finish – earliest finish
Slack = 0 –> critical and no delay is available