Project Management Cost Formulas Flashcards
Budget at Completion - BAC
Planned total expenditure at the end of the project
Actual Cost - AC
Actual cost of work performed to date
Earned Value - EV
Budgeted cost of work performed to date
Planned Value - PV
Budgeted cost of work scheduled to have been performed to date
Cost Variance - CV
EV - AC Negative is “bad”.
Schedule Variance - SV
EV - PV Negative is “bad”.
Cost Performance Index - CPI
EV / AC = Project is accomplishing $(CPI) of work for every $1 spent. CPI < 1.0 is “bad”.
Schedule Performance Index - SPI
EV / PV = Project is progressing at (SPI x 100)% of the planned rate. SPI < 1.0 is “bad”.
Estimate at Completion - EAC
AC + (BAC - EV) = As of now, how much will the project cost, if future work is performed as had been planned?
AC + (BAC - EV) / CPI = As of now, how much will the project cost, if future work is performed as work has been completed to date?
AC + (BAC - EV) / (CPI x SPI) = As of now, how much will the project cost, if future work is performed as to date and completion is by the original planned date?
Estimate to Complete - ETC
EAC - AC = How much more will the project cost?
Variance at Completion - VAC
BAC - EAC = How much over or under budget will the project be at completion?
To-Complete Performance Index - TCPI
(BAC - EV) / (BAC - AC) = Cost performance needed from now to completion to meet the original budget goal. Note that TCPI > 1.0 is “bad”.
(BAC - EV) / (EAC - AC) = Cost performance needed from now to completion, if the original BAC is revised to be the current EAC for the remainder of the project.
Future Value - FV
Present Value x ( 1 + Annual Interest Rate )Years
Net Present Value - NPV
Present Value of Benefits - Present Value of Costs → Basis for Comparing Strategically-Equivalent Alternatives
Expected Monetary Value - EVM
Σ Probability of Event x Net Present Value of Event