Formulas (Yellow Cards) Flashcards
Actual Cost AC
Actual cost of work performed to date
Budget at Completion BAC
Planned total expenditure at the end of the project
Earned Value Management EVM
A methodology that combines scope schedule, and resource measurements to assess project performance and progress
Earned Value EV
Budgeted cost of work performed to date
Planned Value PV
Budgeted cost of work scheduled to have been performed to date
Cost Variance CV
EV - AC Negative is “bad”.
Schedule Variance SV
EV - PV Negative is “bad”.
Cost Performance Index CPI
EV / AC = Project is accomplishing $(CPI) of work for every $1 spent. CPI < 1.0 is “bad”.
Schedule Performance Index SPI
EV / PV = Project is progressing at (SPI x 100)% of the planned rate. SPI < 1.0 is “bad”.
Estimate at Completion EAC1
AC + (BAC - EV) = As of now, how much will the project cost, if future work is performed as had been planned?
Estimate at Completion EAC2
AC + (BAC - EV) / CPI = As of now, how much will the project cost, if future work is performed as work has been completed to date?
Estimate at Completion EAC3
AC + (BAC - EV) / (CPI x SPI) = As of now, how much will the project cost, if future work is performed as to date and completion is by the original planned date?
Estimate to Complete ETC
EAC - AC = How much more will the project cost?
Variance at Completion VAC
BAC - EAC = How much over or under budget will the project be at completion?
To-Complete Performance Index TCPI1
(BAC - EV) / (BAC - AC) = Cost performance needed from now to completion to meet the original budget goal. Note that TCPI > 1.0 is “bad”.