Formulas (Yellow Cards) Flashcards

1
Q

Actual Cost AC

A

Actual cost of work performed to date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Budget at Completion BAC

A

Planned total expenditure at the end of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Earned Value Management EVM

A

A methodology that combines scope schedule, and resource measurements to assess project performance and progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Earned Value EV

A

Budgeted cost of work performed to date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Planned Value PV

A

Budgeted cost of work scheduled to have been performed to date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cost Variance CV

A

EV - AC Negative is “bad”.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Schedule Variance SV

A

EV - PV Negative is “bad”.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost Performance Index CPI

A

EV / AC = Project is accomplishing $(CPI) of work for every $1 spent. CPI < 1.0 is “bad”.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Schedule Performance Index SPI

A

EV / PV = Project is progressing at (SPI x 100)% of the planned rate. SPI < 1.0 is “bad”.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate at Completion EAC1

A

AC + (BAC - EV) = As of now, how much will the project cost, if future work is performed as had been planned?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Estimate at Completion EAC2

A

AC + (BAC - EV) / CPI = As of now, how much will the project cost, if future work is performed as work has been completed to date?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Estimate at Completion EAC3

A

AC + (BAC - EV) / (CPI x SPI) = As of now, how much will the project cost, if future work is performed as to date and completion is by the original planned date?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Estimate to Complete ETC

A

EAC - AC = How much more will the project cost?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Variance at Completion VAC

A

BAC - EAC = How much over or under budget will the project be at completion?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

To-Complete Performance Index TCPI1

A

(BAC - EV) / (BAC - AC) = Cost performance needed from now to completion to meet the original budget goal. Note that TCPI > 1.0 is “bad”.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

To-Complete Performance Index TCPI2

A

(BAC - EV) / (EAC - AC) = Cost performance needed from now to completion, if the original BAC is revised to be the current EAC for the remainder of the project.

17
Q

Future Value FV

A

Present Value x ( 1 + Annual Interest Rate )^Years

18
Q

Net Present Value NPV

A

Present Value of Benefits - Present Value of Costs → Basis for Comparing Strategically-Equivalent Alternatives

19
Q

Expected Monetary Value EMV

A

Σ Probability of Event x Net Present Value of Event

20
Q

Number of communication channels

A

N(N-1)/2