Project Management Flashcards
Network Planning technique?
deterministic: Process certain, event durations certain -> CPM, MPM
stochastic: process certain, event durations uncertain -> PERT
process and event durations uncertain -> GERT
Critical Path Method - CPM?
certain processes and event durations
Characteristic of critical path
no buffer time
extension of process -> extension of the duration
not reverse
can be many critical paths
PERT method?nFormel? Inclination?
Programm Evaluation and Review Technique
processes certain, event duration uncertain
three-point time estimate of the process duration
Optimistic duration, pessimistic duration, probable duration, -> expected duration
symmetric: tpr= te
asymmetric right: tpr < te
asymmetric left: tpr >te