Project Management Flashcards

1
Q

Network Planning technique?

A

deterministic: Process certain, event durations certain -> CPM, MPM

stochastic: process certain, event durations uncertain -> PERT

process and event durations uncertain -> GERT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Critical Path Method - CPM?

A

certain processes and event durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Characteristic of critical path

A

no buffer time

extension of process -> extension of the duration

not reverse

can be many critical paths

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

PERT method?nFormel? Inclination?

A

Programm Evaluation and Review Technique

processes certain, event duration uncertain

three-point time estimate of the process duration

Optimistic duration, pessimistic duration, probable duration, -> expected duration

symmetric: tpr= te
asymmetric right: tpr < te
asymmetric left: tpr >te

How well did you know this?
1
Not at all
2
3
4
5
Perfectly