Project Management Flashcards

1
Q

Duration

A

scope of work/(productivity x crew size)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

work crowding

A

having too many workers in a small space

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

learning curve

A

productivity increases when tasks are repetative

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

out of sequence

A

workers unable to have a continuous work flow and are interrupted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

WBS

A

work breakdown structure (sometimes called a dictionary) - work identified in the SOW and serves to help with scheduling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

AON

A

Activity on Node precedence diagram - could be finish to start (most common)/ start to start/finish to finish/finish to start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

finish to start

A

task 1 has to end for task 2 to start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

finish to finish

A

task 1 has to end before task 2 can end, but they can be worked on at the same time. eg. report can be started while data collection is happening, but data collection must end before the report can finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

start to start

A

two things can happen at once - milling can happen at the same time as paving

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

start to finish

A

task 2 has to start before task 1 can finish - a building with an elevator can start to be built, but the electricity has to be in before the elevator can be installed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

AOA

A

Activity on Arrow precedence diagram - finish to start precedence only, people oriented flow chart based.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

float

A

flexibility in a project - could be the amount of time between early and late start dates, early and late finish dates, or TF = LF - ES - Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

labor burden

A

the cost to a company to carry their labor force aside from salary. burden is the benefits and taxes that a company must pay on their payroll.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly