Project life cycle approach Flashcards
1
Q
Predictive
A
A more traditional approach, with the bulk of planning occurring up-front, then executing in a
single pass; a sequential process
2
Q
Iterative
A
An approach that allows feedback for unfinished work to improve and modify that work
3
Q
Incremental
A
An approach that provides finished deliverables that the customer may be able to use immediately
4
Q
Adaptive
A
The detailed scope is defined and approved before the start of an iteration