Project finance, Design Economics & Cost Planning and Quantification & Costing Flashcards
What are the typical cost manager responsibilities on a construction project?
- Manage risk allowance expenditure
- Initiate action to avoid overspend
- Prepare pricing documents for tendering
- Evaluate and analyse tender bids
- Prepare interim valuations
- Value variations and compensation events
- Assess the contractor’s financial claims
- Negotiate and agree final accounts
- Issue financial reports or statements
- Provide initial cost advice on capital investment plans
- Produce cost estimates and cost plans
- Produce cost reports, estimates and forecasts
- Prepare and maintain the cashflow forecast
If you are producing estimates and cost plans, which measurement rules represent industry best practice?
New Rules of Measurement (NRM)
Can you name the 3 documents in the NRM suite?
- NRM 1 - Order of cost estimate and cost planning for capital building works
- NRM 2 - Detailed measurement for building works
- NRM 3 - Order of cost estimating and cost planning for building maintenance works
Can you provide a brief overview of each of the NRM documents please?
NRM 1
Provides guidance on the quantification of building works for the purpose of preparing cost estimates and cost plans. It is the ‘cornerstone’ of good cost management of construction projects, enabling more effective and accurate cost advice to be given to clients and other project team members, as well as facilitating better cost control.
NRM2
Is written mainly for the preparation of bills of quantities and quantified scheduled of works, although the rules will be invaluable for designing and developing standard or bespoke schedules of rates
NRM 3
Gives guidance on the quantification and description of maintenance works for the purpose of preparing initial order of cost estimates. The rules also aid the procurement and cost control of maintenance works
What is the structure of the NRM 1?
- Part 1: General introduction
- Part 2: Measurement rules for order of cost estimate
- Part 3: Measurement rules for cost planning
- Part 4: Tabulated rules of measurement for elemental cost planning
- Appendices
What is the structure of the NRM 2?
- Part 1: General introduction
- Part 2: Rules for detailed measurement of building works
- Part 3: Tabulated rules of measurement for building works
- Appendices
What is the structure of NRM 3?
- Part 1: General introduction
- Part 2: New rules of measurement for building maintenance works
- Part 3: Measurement rules for order of cost estimating (renewal and maintain)
- Part 4: Measurement rules for cost planning of renewal (R) and maintain (M) works
- Part 5: Calculation of annualised costs for renewal (R) and maintain (M) works
- Part 6: Tabulated rules of measurement for elemental cost planning
- Appendices
Why is it important to measure the works according to industry standards and best practice?
- To provide consistency and greater accuracy of pricing
- To ensure that all parties price on the same basis and therefore reduce the risk of dispute
Is it mandatory for chartered surveyors to follow the procedures set out in NRM?
Following NRM is not a mandatory requirement. However, when an allegation of professional negligence is made against a surveyor, the court is likely to take account of the contents of any relevant guidance notes published by RICS in deciding whether the surveyor had acted with reasonable competence
What items are included within the standard NRM 2 preliminaries (main contract) list?
Employer requirements
- Site accommodation
- Site records
- Completion & post-completion requirements
Contractor cost items
- Management & staff
- Site establishment
- Temporary services
- Safety and environmental protection
- Control and protection
- Mechanical plant
- Temporary works
- Site records
- Completion & post-completion requirements
- Cleaning
- Fees & charges
- Site services
- Insurances, bonds, guarantees and warranties
How is risk dealt with under NRM?
NRM recommends that risk allowances are not a standard percentage, but a properly considered assessment of the risk, considering completeness of the design and other uncertainties such as the amount of site investigation undertaken
Can you tell me the 4 risk categories identified in NRM?
- Employer Change Risk
- Employer Other Risk
- Design Development Risk
- Construction Risk
What is an order of cost estimate?
- Order of cost estimate is a term using by RICS under the New Rules of Measurement, specifically NRM 1 for capital building projects
- The key purpose is to establish if the proposed building project is affordable and if so, to set a realistic cost limit for the development project
How are professional fees presented in order of cost estimate?
Fees can be presented as an item (if actual fees are known) or a percentage applied to the ‘works cost estimate’
Which RIBA Stage is the order of cost estimate typically produced?
RIBA Stage 1 - Preparation and Briefing
What are the RIBA stages of work?
- Stage 0 - Strategic Definition
- Stage 1 - Preparation and Briefing
- Stage 2 - Concept Design
- Stage 3 - Spatial Coordination
- Stage 4 - Technical Design
- Stage 5 - Manufacturing and Construction
- Stage 6 - Handover
- Stage 7 - Use
What is the difference between an order of cost estimate and cost plan?
- An estimate provides a possible cost based on the employer’s requirements and is the initial phase of the cost planning process. The estimate is usually completed using m2 areas of functional units
- A cost plan is a more detailed elemental breakdown and shows how the costs are distributed across the project
What additional information should accompany an order of cost estimate?
- Covering letter
- Executive summary
- Cost limit
- Specification notes
- Assumptions
- Exclusions
- Drawings and other information upon which the estimate is based
- A schedule of value enhancing options
- Risk register
- Cash flow information
What is a cost plan?
- The cost plan is typically prepared by the cost consultant and provides an estimate of what the actual project cost is likely to be
- The cost plan identifies the client’s agreed cost limit and how the money is allocated to the different parts of the project
Other than predicting the final project cost, what other benefits does the cost plan provide to the project and project team?
- Designers are aware of the cost implications of their proposals which enables them to arrive at practical and balanced designs
- Provides information upon which the employer can make informed commercial decisions
Do you need a programme to complete the cost plan?
Preliminaries are typically presented as a weekly rate in developed cost plans; therefore, a programme or at least some high-level dates will be required. The key information usually required is:
- Design and tendering periods
- Start of site date
- Construction period
- Completion date
How do you structure a cost plan?
NRM 1 recommends a template to be following within appendix G of the NRM 1
What sources of cost information and data are available when preparing a new estimate or cost plan?
- Information produced by the BCIS (Building Cost Information Service); data is available of a wide range of building types
- Published pricing books such as SPON’s and BCIS (the information may need adjusting for inflation)
- Pricing documents and other information from previous projects
- Cost analysis and cost models produced in-house
- Speaking direct to contractors, subcontractors and suppliers for cost information
How do you take account of the project location and why?
A location factor is usually applied to recognise differences in construction prices. For example, a project in London is typically more expensive that a similar project in Nottingham