Project Finance Flashcards

1
Q

What is the purpose of a cost report?

A

‘To inform the client in a construction project of the likely outturn cost of the construction project and enable them to make informed decisions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What would you include in a cost report?

A
  • Contract Sum
  • Value of Instructions
  • Anticipated Employer’s Instructions
  • Ongoing Claims
  • Provisional Sum Adjustments
  • Anticipated Final Account
  • Cash Flow
  • Risks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What could affect a contractor’s cash flow post-contract?

A
  • Contract Instructions
  • Provisional quantities or sums
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a cash flow forecast?

A

A graph or table that shows the projected costs needed to fund the project throughout its programme. It allows the employer to track their actual expenditure against the forecast.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How would you put together a cash flow? What is it used for?

A

By valuing the work against the programme. You map out how much work should have been completed month by month and usually present this data in a table and a graph format.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Talk me through how you would complete an interim valuation from receiving the contractor’s application to issuing the documents, including timescales.

A

JCT Design & Build
- Schedule a site walk to agree the valuation within 7 day of reciept.
- Review and agree the preliminaries, works completed on site, materials on site, any variations or adjustments, materials off site (if applicable / via vesting). Then agree the amount payable which is the total amount executed to date less the amount previously paid.
- The due date is 7 days after the date of issue and the tender recommendation needs to be issued to the employer on this date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What would you advise a Client if a Contractor’s Application for Payment was grossly different to your cash flow forecast?

A

The advice I give would depend on whether the application was higher or lower than anticipated.

Higher - front end loading, possible stokpiling of materials on site, or contractor might be having cashflow issues.
Lower - contractor may be behind programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

If the contractor has submitted a valuation which is much greater than the forecast final account and the EA/CA doesn’t issue a payment notice, what happens?

A

If the QS doesn’t issue a payment notice by the due date then the contractors valuation becomes the payment notice and the employer has to pay the contractor the sum they have applied for. In this instance, the employer would need to issue a pay less notice.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the benefits of plotting actual expenditure against predicted?

A

It gives the client opportunity to get additional funding if required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why do we have a change control procedure on a project? How does the QS contribute to this?

A

The change control procedure is used to monitor additional expenditure. The QS Will be able to advise the client of predicted costs prior to them being formally agreed with the contractor, and value them to ensure the contractor is getting best value for money.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

In cash flow forecasting how is retention dealt with?

A

You would reflect the retention in the cash flow.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What should you do if a Contractor fails to submit a valuation?

A

JCT Intermediate
You should contact them and advise them of their contractual obligations to submit a valuation 7 calendar days before the due date. If the contractor still doesn’t submit a valuation the QS will then undertake their own valuation of the works.

JCT Design & Build
In D&B you wait for the contractor to issue a valuation. The due date and payment certificate date remains the same and if missed under D&B then the dates slide back.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When carrying out a valuation, the previous months Payment Recommendation and Payment Notice are different, which one takes precedence?

A

The payment notice as this includes any pay less notices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are day works? What are the risks associated with using them?

A

Day works are used when a variation or change is instructed on the basis of the cost of labour, materials and plant plus a mark up.

Difficult to monitor and record whether or not the contractor has spent the whole day doing the works or not.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly