Contract Practice Flashcards
What is a contract?
A legal agreement between two parties.
Why are Contracts required / relevant for the construction industry?
Provides protection for both the employer and the contractors. It also prevents disputes.
What are the different ways in which a contract can be made?
Verbally and written
What are the key requirements for a contract to be made binding?
- Offer
- Acceptance
- Consideration
- Intention to create legal relation
What are common main contract documents in JCT Design and Build.
Form of contract, employers requirements, contractors proposals, CSA, programme and clarifications.
What are common main contract documents in JCT Intermediate.
Contract Drawings, specifications, bill of quantities.
What standard forms of JCT contracts are you aware of?
Intermediate, Design and Build, Intermediate, Major, and Minor.
Under what procurement route would you consider using a JCT Minor Works Building Contract.
Traditional procurement route.
When might a JCT Minor Works Building Contract be appropriate?
Small, low value, basic construction projects where the work involved is simple in character.
Under what procurement route would you consider using a JCT Intermediate Building Contract?
Traditional procurement route.
What is retention?
An amount of money owed to the contractor held by the employer, to ensure the contractor is completing the works in accordance with the contract, until the end of the rectification period.
How is retention released?
Typically 1/2 s released on practical completion and 1/2 released at the end of the rectification period. This may vary depending on what is agreed at contract negotiation.
What is a Notice of Completion of Making Good?
A certificate confirming that the contractor has made good any defects during the rectification period.
What are the advantages for standard contracts?
- Standardised contracts backed up by case law
- Known across the industry
- Reduced legal costs
What are the advantages for bespoke contracts?
- Contracts can be customised to address project specific needs
- Greater control over the agreed dispute resolution and payment methods.
What are the disadvantages for standard contracts?
- Can be overly complicated for smaller projects
- Limited flexibility to address specific project needs
What are the disadvantages for bespoke contracts?
- Increased legal costs to draft a bespoke contract
- Time consuming
- Lack of case law or precedent can make it difficult to resolve disputes
What is a relevant event?
An occurrence, such as delays caused by the client or external factors, that entitles the contractor to an extension of time for project completion.
What is a relevant matter?
An occurrence, such as changes in design or unforeseen site conditions, that affects the contractor’s ability to perform the work as originally agreed and may justify a claim for additional costs or time.
What are some examples of relevant events?
In JCT D&B
- Extreme weather
- Force Majeure
- Delay of possession of site
- Civil Commosion
What is a letter of intent?
A document that outlines the intentions of parties involved in a construction project before a formal contract is signed.
What are the benefits of a letter of intent?
- Alleviates time-constraints
- Allows more time for negotiations on the contract details
- Provides clarity of scope of works
Is a letter of intent legally binding?
Not necessarily. However, some elements include legally binding provisions. So it’s important that the client consults a solicitor to understand their obligations as it can sometimes be seen as legally binding.
What are the disadvantages of a letter of intent?
- Not necessarily legally binding, but can unintentionally become legally binding.
- Ambiguity on the project outcome
- May create a delay to create an official document