Project Finance Flashcards

1
Q

What is a cashflow S curve

A

Visual representation of cashflow.
Low at the start, goes up during and then low at the end

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

RICs guidance note

A

Cashflow forecast

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Defined provisional sum

A

Benchmark data & defined scope
programme is bought (know the length of time itll take roughly)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Undefined provisional sum

A

Not defined scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Not to exceed

A

NTE under instruction so cannot contractually be exceeded

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is in a cost report

A

Instructions to date
Expected instructions
Movement in cashflow
Valuations in line with programme
Overall budget - draw downs to date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How do you test financial stability

A

Past 3yrs turnover
Forecast turnover
Dan & broadsheet report
Balance sheet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what would you ask for in the PQQ

A

cashflow
budget
balance sheet
profit & loss from last 3yrs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

how do you review a companies credit rating

A

the dun and bradshaw report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

typical design contingency for a D&B contract

A

3%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what may affect cost of a project

A

pricing clarifications
provisional sums
contract amendments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

valuation process

A

Interim Valuation Date is built into all JCT 2016 contracts
Interim Valuation Date is to be agreed by the parties in the Contract Particulars
Same day in each month, or the nearest business day in that month
contractor prepares application for this
QS attendees site and values work in totality
QS reviews the application & submits to EA/CA
EA/CA drafts payment certificate
application is approved
GC then submits invoice against the PO number
client pays invoice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

quantity surveyors role in valuations

A

The quantity surveyor’s function is to assess value as
distinct from cost, particularly with reference to prices of
certain items in the preliminaries section and temporary
works.
Interim valuation involves a revaluation of the whole work,
not the work done since the last interim certificate or
payment notice was issued.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

what does it mean to be ahead on cashflow

A

ahead on valuations- too much has been signed off. may lead to future valuations being less

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

what acts are relevant to payment

A

Housing Grants and construction regeneration act 1996
&
local Democracy, Economic Development and Construction Act 2009

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

what did the HGCR act include

A

fair payment for contractors- to stop clients not paying/ contractors not paying their subcontractors

17
Q

what did the LDEDC act include

A

dispute resolution